Foundations: what the soil survey changes in the budget

📐 Topic

By , construction economist

8 min read

What you will find in this article What remains unknown about a site as long as no test has been carried out, when to commission the geotechnical investigation, what the Brussels regulations on soil status add, how foundation types compare, and what allowance to hold until the uncertainty is removed. The reasoning is applied to the same block of 20 flats in Brussels.

Soil is the only parameter design does not choose

A shape can be simplified, a basement reduced or a facade changed. The soil cannot be changed. The article on site and siting complexity says it plainly: the site is the only major factor that design cannot neutralise, and it is also the one whose uncertainty is removed latest if it is not dealt with early.

On the example project of the guide to reducing construction costs in Belgium, the soil carries a five-storey building over a 600 m² basement, excavated to approximately 3.50 m between two party walls. Three unknowns then govern the cost of the foundations: the bearing capacity of the layers found below the excavation level, the presence of water, and the quality of the soil to be removed. None of them can be read from a cadastral plan.

What remains unknown without a survey

Without tests, every foundation assumption is a gamble. The table shows what each of the three unknowns can change on the example:

Unknown Reference assumption If it turns out to be unfavourable
Bearing capacity below excavation level Bearing soil at shallow depth, shallow foundations or raft Deep foundations (piles), thickened raft, longer construction period
Water No water table at basement level Dewatering during the works, tanking or watertight raft, pumping
Soil quality Uncontaminated soil, standard removal Analysis, sorting, treatment route, or even prior remediation
Neighbouring foundations Neighbours founded deeper than the excavation level Underpinning along the 2 × 20 m of party walls

The last row is specific to the Brussels urban fabric. A basement that goes below the foundations of the neighbouring houses requires them to be underpinned before digging, with joint condition surveys and slow phasing. The soil survey also provides information on this point, together with the investigation of the existing foundations.

The geotechnical investigation, and when to commission it

Timing matters more than content. Commissioned before the land is acquired, under a condition precedent, the investigation makes it possible to build the cost of the foundations into the price of the land. Commissioned after the permit, it uncovers a cost that the financial appraisal can no longer absorb. The blog sums it up: doing the survey after signing for the land amounts to discovering the price after the purchase.

For a single house, a geotechnical investigation costs from a few hundred to just over a thousand euros depending on the extent of the tests, according to the guide to construction costs per m². For a building over a basement, the campaign is more extensive, with several tests spread over the footprint and, if there is doubt about water, a reading of the water table level. No public source gives a price for such a campaign; its order of magnitude bears no comparison with the difference between shallow foundations and piles.

Foundation design falls under Eurocode 7, published in Belgium as NBN EN 1997 with its national annex, which covers geotechnical design and the investigations that feed into it. The survey is therefore commissioned with the structural engineer's use of it in mind: depth of the tests below excavation level, number of test points, water measurement.

Soil status, a Brussels question

In Brussels, soil quality is governed by the ordinance of 5 March 2009 on the management and remediation of contaminated soils. A plot listed in the soil status inventory, or on which a risk activity has been carried out, may require a reconnaissance de l'état du sol (preliminary soil assessment) before certain permits or certain transactions, then, depending on the results, a detailed study and treatment.

Bruxelles Environnement states that a preliminary soil assessment costs on average 5,000 €, as does a detailed study, and that a risk study requires approximately 3,000 €. These amounts do not include the remediation itself, whose cost depends on the contamination found. For a project with a basement, the stakes are twofold: any contamination has to be treated, and all the excavated soil must go to a destination suited to its quality.

The soil status inventory is consulted before the purchase, like the geotechnical investigation. The two studies answer different questions, but they are commissioned at the same time and sometimes from the same consultant.

Foundation types and their differences

The type of foundation follows from the soil, the loads and the presence of water. The table places the common solutions for the example, without amounts: no accepted public reference costs them for an apartment building.

Solution When it is required What drives its cost
Footings under walls and columns Bearing soil at shallow depth below excavation level Concrete and reinforcement, little special equipment
Raft foundation High loads, average soil, or water to be held back Thickness and reinforcement over the whole basement footprint
Piles Deep bearing layers Drilling equipment, pile length, verification tests, longer programme
Watertight raft or tanking Basement below the water table Waterproofing, anchorage against uplift, dewatering during the works

The difference between the two extremes runs into tens of thousands of euros even for a single house, according to the blog, and much more on a residential block. On the example, the 600 m² of basement and the underpinning along the party walls multiply this difference, and the presence of water alone can change the order of magnitude of the basement, dealt with in the page on the cost of a basement parking space.

The structure also affects the foundations. A misaligned grid concentrates the loads on a few columns and strengthens the foundations at those points, as the page on the grid and the structure explains.

The allowance to hold while the soil is unknown

Until the survey has been carried out, the foundation risk is provided for separately. The blog recommends it: make a specific allowance for this risk rather than drowning it in a general contingency. A separate line, labelled and justified, is released when the survey arrives; a general percentage across all items gets used up without anyone knowing on what.

This allowance is distinct from the contingency reserve for the works, which Homegrade recommends in Brussels at around 10 % of the cost of the works. The latter covers construction risks, the former a design uncertainty that can be removed. The article on contingency by project stage explains how these reserves are sized and released.

In summary

The soil survey costs little compared with what it avoids, provided it is commissioned before the land is bought. In Brussels, it comes with a soil status question, governed by the ordinance of 5 March 2009, whose preliminary assessment costs on average 5,000 € according to Bruxelles Environnement. As long as the soil is not known, the foundation risk is provided for on a separate line, which is released with the survey.

Nature of the values cited

Texts are cited with their reference. The areas and depths come from the example project, calculated on fictitious assumptions, and the prices are given as examples: they do not replace a geotechnical investigation or a contractor tender.

Sources: Prices given as examples, established in November 2026 from public references: Bruxelles Environnement, page "Reconnaissance de l'état du sol" (preliminary soil assessment); range for the soil survey of a house taken from this blog's guide to costs per m²; Homegrade, brochure "Maîtriser son chantier" (keeping control of your building project), 2022, taken from this blog · Brussels ordinance of 5 March 2009 on the management and remediation of contaminated soils · NBN EN 1997 (Eurocode 7) and its national annex.

Frequently asked questions

Before the land is acquired whenever possible, under a condition precedent. It is the only moment when the cost of the foundations can still be passed on to the price of the land or to the brief.

Bruxelles Environnement gives an average cost of approximately 5,000 €, as for a detailed study, and approximately 3,000 € for a risk study. Any remediation is not included.

Yes, as long as the survey is not available. A separate line for the foundation risk is released when the soil is known, whereas a general contingency gets used up without being allocated.

← Reducing construction costs in Belgium: the decisions that set them at sketch design