Tracking the final cost during the works

📐 Topic

By , construction economist

Information verified on 6 min read

What you will learn The seven lines of the client's dashboard, the difference between committed amount and forecast final cost, an update rhythm set by progress statements, and the four sources of variance covered in this branch.

Once the contract is signed, the budget does not disappear: it changes nature. The maître d'ouvrage (bouwheer, the client) no longer tracks an estimate but a forecast final cost, and that forecast is revised at each état d'avancement (progress statement), not at the final account. Whatever is not seen during the works is discovered when there is no longer any lever left.

The dashboard in seven lines

Seven lines are enough, provided they are kept at the same date and in the same unit (HTVA, excluding VAT). Each answers a different question; the last is the only one used to decide.

Line What it contains Where the value comes from
Initial budget the approved works envelope, excluding VAT, with its value month architect's agreement, estimate
Committed amount the price of the signed contracts contracts and annexes
Approved extras changes accepted in writing, with their price written orders, agreements, addenda
Extras under discussion requests received and not yet accepted, at their probable amount contractor's requests, own estimate
Price revision the effect of the revision clause, invoiced and still to come contract formula, published indices
Quantity variances the difference between contract quantities and projected quantities progress statements, métré (meetstaat, bill of quantities)
Forecast final cost committed amount plus the four variance lines calculation by the client or the client's adviser

The contingency is read against the forecast. What remains of the contingency, compared with what the variances consume, tells you whether the envelope holds. A contingency half used up before the finishes have started is a warning sign, even if the committed amount has not moved.

Committed is not final

The committed amount is reassuring, and that is its flaw. It reflects only the signed contracts; extras, approved or under discussion, price revision and drifting quantities escape it.

Extras under discussion are entered at their probable amount, not at zero on the grounds that they are disputed. If they are finally rejected, the line is released.

Price revision and quantities are projected through to the end. What has been invoiced says nothing about the revision on the remaining works, and a quantity that already exceeds the contract quantity halfway through the item signals a final overrun.

The rhythm: every progress statement

The dashboard is updated at the rhythm of progress statements, because that is where the information arrives. Each statement shows what has been carried out, item by item. Reading variations and interim valuations is covered in the guide on measurement.

In a public contract, the timetable is regulated. Under article 95 of the RGE (general implementing rules, Royal Decree of 14 January 2013), the contractor submits a déclaration de créance (payment claim) together with a detailed statement of the works, which the pouvoir adjudicateur (contracting authority) checks and pays within 30 days (60 for certain contracting authorities in the healthcare sector). That period is also the window in which the forecast must be updated, before payment confirms the quantities.

In a private contract, the rhythm is the contract's. Requiring detailed progress statements by item, rather than an overall percentage, is the condition for spotting an item that is drifting.

The four sources of variance

A variance in final cost almost always has one of four causes. Each has its own regime and its own line in the dashboard:

  • changes in a private contract, where article 1793 of the old Civil Code makes any price increase conditional on written authorisation and an agreed price;
  • changes in a public contract, governed by the general implementing rules;
  • quantity variances;
  • price revision, whose effect depends on the budget's value date.

What weakens the tracking

Three practices ruin a dashboard. Each one erases a piece of information the forecast needs:

  • accepting an extra orally and without a price;
  • mixing amounts excluding VAT with amounts including VAT;
  • failing to date the initial budget, which makes it impossible to isolate the share of the variance due to price revision.

The decision remains with the client. The dashboard shows early enough where to make trade-offs: reduce an item still to come, draw on the contingency, or accept a higher forecast knowingly.

The articles in this branch

This article reflects the position of the rules at the date of checking and serves professional orientation. It does not constitute legal advice and does not replace assessment of the individual case.

Frequently asked questions

At every progress statement, since that is when the quantities carried out and the requests for extras arrive. An update only at the final account leaves no room for any trade-off.

Yes, at its probable amount, on a line separate from approved extras. Removing it from the dashboard because it is disputed amounts to underestimating the final cost.

The committed amount is the sum of the signed contracts. The final cost adds the approved extras, the extras under discussion, the price revision still to come and the projected quantity variances.

Identify the line carrying the variance, then make trade-offs while items remain to be carried out. The contingency is there to absorb an identified variance, not to hide it.