Blog

Procurement routes and thresholds

📐 Article6 min read

What you will learn Which routes the VOB/A recognises, which thresholds have applied since January 2026, why the same route has a different name under a different body of rules, and which figures states and municipalities may vary.

The choice of route determines effort, periods and competition. It is not free: the VOB/A ties it to admissibility conditions, and these largely hang on the contract value.

The routes

Route Field of tenderers Procedure
Open tendering unlimited, public invitation formal
Restricted tendering with prior call limited, after a public call for participation formal, two-stage
Restricted tendering without prior call limited, selected firms formal
Negotiated procedure selected firms simplified
Direct award one firm without a procedure

Open tendering is the default. It is always available to the client. The other routes are exceptions, permissible only where the VOB/A allows them.

The thresholds since 1 January 2026

The admissibility conditions were recast at the start of 2026. The figures are net of tax.

Route Threshold since 2026 previously
Direct award €50,000 considerably lower
Negotiated procedure €100,000 €10,000
Restricted tendering without prior call €150,000 civil engineering trades only

Two observations stand out.

The increase is substantial. The threshold for the negotiated procedure has risen tenfold. A considerable share of construction procurement thereby moves out of formal procedure.

The harmonisation is new. The €150,000 figure for restricted tendering without a prior call previously applied only to civil engineering trades and now applies to all.

The increase follows a decision to introduce a uniform direct award threshold across federal procurement from 2026, and an intention to treat construction procurement and supplies and services procurement alike. Behind it lay an intention to treat construction procurement in line with supplies and services.

Why the same route has a different name

A peculiarity of German procurement law regularly causes confusion, and it is purely terminological. The above- and below-threshold regimes use different names for the same thing.

Body of rules Designation
VOB/A, for construction works Freihändige Vergabe
Below-threshold ordinance, for supplies and services Verhandlungsvergabe

The same route is meant. Anyone working on one procedure for construction works and another for design services therefore meets two names for the same thing.

The distinction is not without consequence: the admissibility conditions and thresholds of the two bodies of rules do not coincide. Transferring one's figures to the other means choosing an impermissible route.

The same caution applies to design services generally: they are services and do not fall under the VOB/A. The article on above and below EU thresholds covers the classification.

The conditions beyond the thresholds

Below the figures given, the exceptional routes are permissible without particular justification. Above them they remain so only where certain grounds exist.

Typical grounds for a negotiated procedure can be set out briefly. Each must be evidenced in the individual case and recorded on the procurement file.

Only one firm comes into consideration, for instance because of patent protection, particular experience or particular equipment.

A fresh tender promises no acceptable result after a previous procedure was cancelled.

Grounds of confidentiality require it.

A small item of work cannot be separated from a larger one already awarded without disadvantage.

The grounds are to be construed narrowly and recorded on the procurement file. An inadequately justified choice of route is open to challenge.

What states and municipalities vary

The figures given reflect the federal framework. The thresholds for individual routes are set by federal and state governments, and they can vary considerably by state.

A checking sequence follows that cannot be shortened. Each step presupposes the result of the one before it.

  1. Estimate the contract value and compare it against the EU threshold.
  2. Below threshold, identify the applicable state law, because it may set its own figures.
  3. Check special rules, which may depart further still.

A point familiar from the other subjects in this field applies too: it happens that a state procurement act refers to a superseded edition of the VOB/A. The reference must then be checked rather than the current version assumed.

The link to competition

Higher thresholds mean fewer procedures and less effort. They also mean fewer tenderers per procurement.

Effect Consequence
Less formal effort faster awards, lower procedural cost
Smaller field weaker price pressure
Less transparency reduced scrutiny

For cost planning the middle row matters most. Procurement from three selected firms regularly produces a different price level than open tendering, and that effect belongs in the cost calculation.

Anyone pricing a project should therefore know how it will be procured. Benchmarks from openly tendered projects do not transfer readily to negotiated ones.

This article reflects the position of the rules at the date of checking and serves professional orientation. It does not constitute legal advice and does not replace assessment of the individual case.

Frequently asked questions

Open, restricted and negotiated procedures, each with its own conditions. The article sorts them.

Amounts below which simpler procedure types are permitted. They apply in updated form since 1 January.

Because different terms apply above and below the thresholds. The article contrasts them.

Yes, states and municipalities partly set their own value limits. The applicable rule must be checked locally.

Tendering and procurement under the VOB: a guide