By hand and with software

📐 Article⏱ 5 min read

What you will learn What the current tools are, what software solves and what it does not, what it presupposes, and what that means for the market.

Software does not replace the estimator. It speeds up one part of the work, and the other part stays the same.

1. What the current tools are

The description in professional sources shows a division that follows company size. Larger firms use software, smaller ones spreadsheets.

Larger construction companies use various software solutions to simplify and speed up the calculation of quantities, but most construction companies work classically by hand. According to professional sources, the software used for measuring quantities recognises drawings in DWG, IFC and PDF formats.

The tools therefore exist, but their use is uneven, and that unevenness matters for the market. The gap carries into the comparability of tenders.

2. What software solves

Three things, and the third is underrated. It concerns keeping track of revisions.

What it gives When it counts
Speed of measurement especially with repeating elements
Fewer arithmetic errors addition and multiplication are automatic
Fast recalculation of the effect of a change when the design changes

The third matters particularly in reconstruction, since the design changes often: with a manual calculation, every design change means repeating part of the calculation. Tracking variations then becomes hard.

3. What software does not solve

Four things remain for a person to decide, and the fourth is the most important. Software does not replace them.

What remains with the person Why
Choosing the measurement rule see measurement rules
Choosing the technology how the work is actually carried out
Material consumption norms they require knowledge of technology and materials
Noticing omissions seeing what is not on the drawing

Software measures what is on the drawing and does not know what is missing. A wrong or incomplete drawing gives the same wrong result with software, only faster.

4. What it presupposes

Two conditions must be met, and they tie pricing to design. Without them the calculation stays imprecise.

The drawings must be in machine-readable form, that is DWG or IFC, or at least in correct PDF form, and where the IFC format is used the model must have been built consistently. Software cannot read quantities from a scanned or hand-drawn document.

The practical conclusion for a client is broader than a question of software: a sound design is a precondition not only of building but also of pricing. The quality of the design sets the quality of the tender.

5. What that means for the market

Three consequences, and the third is the most practical conclusion in this article. It concerns the field of participants.

A larger company tenders faster and can take part in more procurements, while a smaller one has to choose, which reduces competition in each procurement. A common schedule of quantities levels that difference entirely, because then neither of them calculates.

A client who provides the quantities receives more tenders, including from smaller companies. Competition widens.

Summary and four practical rules

Larger construction companies use software that reads DWG, IFC and PDF drawings to calculate quantities, but most companies work by hand. Software speeds up measurement, reduces arithmetic errors and allows the effect of a change to be recalculated quickly, but it does not choose the measurement rule or the technology and does not notice omissions. It presupposes machine-readable drawings, which ties the quality of pricing to the quality of design.

Four rules: do not assume software replaces knowledge of technology. Check for omissions yourself, since software does not see what is missing. Ensure machine-readable drawings if you want fast and precise pricing. Provide the quantities if you want tenders from smaller companies too.

This article offers professional orientation as at the date of verification. It replaces neither a quotation nor the assessment of a competent specialist.

Frequently asked questions

Both are used. According to professional sources larger construction companies use software and smaller ones spreadsheets, so the use of tools is uneven.

Four things remain for a person to decide, including the choice of measurement rules and the assessment of conditions on site. Software speeds up the calculation but takes no decisions.

In reconstruction, where the design changes often and reworking a manual calculation is laborious. Tracking variations is hardest there.

More than a choice of tool: a sound design and agreed quantities reduce imprecision whatever the tool. The quality of the design sets the quality of the tender.