Blog

Tracking costs during construction

📐 Topic5 min read

What you will learn Why the budget does not end when the contract is signed, what to track, three moments at which a problem is discovered, what makes tracking possible, and who tracks.

A budget is prepared before construction and then often set aside. In that case it is a forecast, and a forecast manages nothing.

1. Why the budget does not end when the contract is signed

Three reasons, and the third is the most painful for a client. It concerns the price of variations.

A construction project changes, because some things only become clear during the works, and changes cost money, so their price is added to the original total. Without tracking, the final total only becomes clear at the end, when nothing can be altered.

From this follows the starting point of the whole article: a budget overrun is not an event that happens at the end. It accumulates throughout construction and is discovered at the end.

2. What to track

Four things of different character, and only one of them is a management tool. The rest are reports after the fact.

What to track Character
The agreed contract sum the starting point
Approved variations added or deducted
Work carried out progress line by line
The forecast final sum calculable from the three above

The first three describe the past, the fourth says where things are heading. Only the fourth looks forward, which is why only it makes a decision possible.

3. Three moments at which a problem is discovered

The difference between them is critical for a client, and it is not financial. It lies in timing.

When it is discovered What can still be chosen
When the variation is being planned whether to do it at all
When the variation is being carried out only how to proceed
When the invoice arrives nothing

The third moment is the most common and the worst. What separates the three is not the amount of money but the choice still available, and from that follows the real purpose of tracking: not reducing cost but making a decision possible in time.

4. What makes tracking possible

Three conditions must be met before construction, not during it. Afterwards they can no longer be created.

A structured budget whose lines have been agreed. Unit prices, which allow a variation to be priced without negotiation. And an agreement on how variations are documented and approved.

All three are decided before the contract, as covered by the article on requiring a structured tender. Without them, tracking is possible only at the level of the total sum, which discovers the problem too late.

5. Who tracks

Three possibilities, and confusing the first two is a common mistake. They measure different things.

Who What they track
The contractor its own costs, which it tracks anyway for the sake of its profit
The client its own outgoings
An independent supervisor or construction manager both, where such a role is provided for

The first and the second are not the same thing: the contractor tracks its margin, the client its budget. The contractor's cost control gives the client no information, since it concerns the company's internal economy. A client tracks what it pays, not what the contractor spends.

Summary and four practical rules

A budget that is not tracked is a forecast, because an overrun accumulates throughout construction and is discovered at the end. Four things must be tracked, of which only the forecast final sum looks forward and is therefore a management tool. What separates the three moments of discovery is not the amount of money but the choice still available, so the purpose of tracking is to make a decision possible in time.

Four rules: calculate the forecast final sum, not only the amount spent. Decide the structure, the unit prices and the variation procedure before the contract. Track approved variations, not invoices received. Distinguish the contractor's cost control from tracking your own budget, since they answer different questions.

This article offers professional orientation as at the date of verification. It replaces neither a quotation nor the assessment of a competent specialist.

Frequently asked questions

Before construction, not during it. Three conditions, including agreed lines and a procedure for pricing variations, have to be created at the procurement and contract stage.

A commitment arises when work is ordered or a variation approved, while payment follows later. The payment position lags the commitment and therefore gives too optimistic a picture.

Where the overrun arose, which work has actually been done, and how the forecast of final cost is built. Line-level tracking is needed for that.

Only to a limited extent. Line-level tracking presupposes agreed lines, and without them the only instrument left is the total, which is not a management tool.

Explore the articles in this guide

Construction budgeting and cost control