Tracking the final cost during the works

📐 Topic

By , construction economist

Information verified on 6 min read

What you will learn The lines of the client's dashboard modelled on the final account required by the 2018 law, why statutory increases sit on a line of their own, what can be paid and when, and the four articles in this branch.

Once the contract is signed, the budget changes nature: it is no longer an estimate but a forecast of the final cost that has to be kept up to date. In Luxembourg, a public client knows from day one what the end will look like: a final account comparing the estimate and, trade by trade, the contract price and the final cost, with the statutory increases shown separately. Building cost tracking on that grid prepares the final account, in public and private contracts alike.

A dashboard modelled on the final account

The amended law of 8 April 2018 on public procurement provides the structure for tracking. Its article 47 (1) requires, above €20,000 excluding VAT at index 100 value (an indexed amount to be updated), a final account (décompte final) "comprising a comparison with the estimate drawn up for the contract award procedure and a comparison, by trade, of the contract price and the final cost of the whole contract, additional contracts included" (unofficial translation). Here the estimate is the devis in the Luxembourg sense: the figure drawn up by the contracting authority (pouvoir adjudicateur), not the contractor's bid. The client (maître d'ouvrage) sets up the dashboard with these columns from the start of the works, package by package.

Line Content Source of the figure
Dated budget the works budget excluding VAT (HTVA), with its base date architect's agreement, council resolution, estimate
Contract price the price of the signed contracts, by trade accepted tenders (soumissions), contracts
Approved amendments signed changes, with their price amendments, written instructions and agreed prices
Amendments under discussion requests received, at their likely amount contractor's requests, own costing
Statutory increases the effect of price revisions, already paid and still to come clause in the special specifications (cahier spécial des charges)
Quantity variances the difference between contract quantities and projected quantities interim valuations, measurements
Final cost forecast contract price plus the four variance lines calculation by the client or its adviser

The statutory increases (hausses légales) line stays separate because the law requires it in the final account. Article 47 (2) provides: "Where the estimate or the agreed price is exceeded, the statutory increases are to be shown separately." Article 47 (3) adds that "a justification is to be provided for all overruns exceeding the statutory increases". Mixing price revision and changes on a single line makes it impossible to produce that justification at the end.

Amendments (avenants) under discussion appear at their likely amount, never at zero. What remains of the contingency, set against the variance lines, tells you whether the budget is holding.

What is paid, and when

In public contracts, payments are tightly regulated. Article 46 of the 2018 law allows interim payments only for services "performed and accepted". Advances are possible in justified cases, covered by guarantees, up to 25% of the total value of the contract (exceptionally 40% of the estimated amount for the State, on a reasoned decision).

The end of the contract has its own deadlines too. Under articles 135 and 136 of the implementing Grand-Ducal regulation of 8 April 2018, the final invoice is drawn up on the basis of the final acceptance report, and the contracting authority checks the items and notifies any dispute "within twenty-eight days".

In private contracts, the rhythm and the documents are those of the contract. For work in several parts or measured work, the Civil Code provides that inspection may be carried out in parts and is deemed done for the parts paid if the owner pays in proportion to the work done (art. 1791). Paying a valuation without checking it is therefore not neutral. What happens after signing (instructions, acceptance, quantities) is described in the article on what happens after the contract is signed, and the move from bill quantities to actual quantities in the one on the final account and actual quantities.

What weakens tracking

Three habits wreck a dashboard. Accepting a change orally and without a price. Mixing amounts excluding VAT with amounts including VAT. Leaving the budget undated, which later makes it impossible to separate the part of the variance caused by statutory increases from the part caused by the client's own decisions. The decision remains the client's: cut a future item, draw on the contingency, or accept a higher forecast with full knowledge of the facts.

The articles in this branch

This article sets out the Luxembourg rules as they stood on the date of checking and is intended as professional guidance. It replaces neither legal advice nor an examination of the specific case.

Frequently asked questions

At every interim valuation, since that is when executed quantities and change requests come in.

Because article 47 (2) of the 2018 law requires them to be shown separately in the final account, and only overruns exceeding them have to be justified.

Yes, in justified cases and against guarantees, up to 25% of the total value at most (40% of the estimated amount for the State, exceptionally and on a reasoned decision).

The implementing regulation gives the contracting authority 28 days to check the items and notify any dispute. In a private contract, the period is the one set by the contract.