From works budget to total project cost

📐 Article

By , construction economist

Information verified on 12 min read

What you will learn The items that separate the works budget from the total cost, for each one who invoices it, when it becomes known and where its value comes from, then a method for keeping a two-column budget, certain and estimated.

The works budget is the figure given to the architect; the total cost is what the maître d'ouvrage (bouwheer, the client) pays. Between the two, a dozen items become certain at very different moments, and it is that order, more than their amount, that structures the budget. This article follows on from Setting the budget before the drawings and gives no values: orders of magnitude are covered in the guide on prices per m².

One budget, two scopes

The works budget covers what the contractors will invoice, excluding VAT. It is the limit for design: the code of ethics of the Ordre des architectes (Order of Architects) of 16 November 2022 (art. 16) requires the architect to design "within the limits of the brief set in the appointment and of the budget" (unofficial translation).

The total project cost covers everything the client pays out for the building to be built, permitted, insured, connected and financed. It is the client's own limit, and often the one set by its lender or its board.

The classic mistake is to compare one with the other. An architect's estimate "within budget" can push the total cost over if the items outside the works have never been costed. The items a price per m² leaves out are listed in what a price per m² never includes.

The table of items

Item Who invoices it When it becomes known Where its value comes from
Works (excl. VAT) contractors at award, then at the final account estimate, then tenders, then interim valuations
Architect's fees architect when the agreement is signed negotiation (no fee scale)
Engineers' fees (structure, building services) engineering consultancies on their appointment tender or agreement
Health and safety coordination design-stage and construction-stage coordinators on their appointment (by the client from 500 m²) coordinator's tender
PEB or EPB assignment responsable PEB (Wallonia), EPB-verslaggever (Flanders) on appointment provider's tender
Insurance insurers, or included in providers' prices before the works begin policies and certificates
Utility connections network operators late, often during the works operator's quotation
Planning taxes and charges municipality or region when the permit is issued regional and municipal rules
VAT collected by each provider once the applicable regime is established the project's tax conditions
Finance costs bank or lender when the financing is signed, then as drawdowns are made loan agreement and payment schedule
Price adjustment contractors during the works adjustment clause and indices
Contingency nobody (internal reserve) released up to the final account identified risks

Read this table by its third column. Fees are known early; the works become certain at award; connections, charges and price adjustment stay open for a long time. At any date, the budget must therefore carry a certain part and an estimated part, and the second must shrink.

Items known early: fees

Fees are the first certain amounts in the project. The 2022 code (art. 20) requires a written agreement "at the latest when the appointment has been defined": by that date, the amount or the way it is calculated is fixed.

There is no longer a fee scale. The Order's former scale was sanctioned by the European Commission on 24 June 2004, and the 2022 code contains none: fees are negotiated. How they are calculated matters as much as their level. Fees expressed as a proportion of the works amount rise when the estimate rises, which is worth reading before signing. Orders of magnitude are covered in the article on fees and ancillary costs.

Engineers come next. Structure, building services, acoustics depending on the brief: they are often appointed later than the architect, and their cost is only certain at that point. Until they are appointed, the item is an estimate.

Involving an architect is compulsory for works that need a permit, subject to exemptions (Act of 20 February 1939, art. 4, a federal law applicable in all three regions). This item therefore cannot be optimised by removing it, only by defining the appointment.

Items the client triggers itself

Some required participants go into the client's budget, even when the client does not appoint them. That is the case for health and safety coordination and the energy performance assignment.

Health and safety coordination. On temporary or mobile construction sites where several contractors are involved, the Act of 4 August 1996 requires a coordinator to be appointed for the design stage and one for the construction stage (art. 16 and 21). The Royal Decree of 25 January 2001 specifies who appoints them: the client for a structure with a total area of 500 m² or more (art. 5 and 15), and below that the designer and then the party in charge of supervising execution (art. 4bis and 4decies), roles held by the architect where the architect's involvement is compulsory (Act, art. 14). A health and safety plan is drawn up before the site opens (Act, art. 16, 2°), replaced on some small sites by a written agreement between the parties involved (Decree, art. 29), and a file for subsequent works is compiled. The cost is that of the coordinators' tenders; it is known as soon as they are appointed, which must happen early for design-stage coordination.

The PEB or EPB assignment depends on the region. In Wallonia, an approved responsable PEB (energy performance adviser) must be appointed; the initial PEB declaration is attached to the permit and the final declaration follows the works. In Flanders, the bouwheer appoints an EPB-verslaggever (energy performance reporter) before the works begin. In Brussels, for a new build or a major renovation, the declarant appoints a conseiller PEB (energy performance adviser) under the Brussels Code of Air, Climate and Energy Management. The item is costed on the basis of a tender, and the differences between regions are covered in how the region changes the budget.

Items fixed at tender stage

The works amount becomes certain at award, not before. Until then, it is an estimate whose margin of uncertainty narrows from stage to stage: that is the subject of contingency by project stage. Even once awarded, it stays open until the final account: extras, quantity variances and price adjustment are added to it.

In public procurement, estimating is a legal obligation and the estimate is expressed excluding VAT. The Act of 17 June 2016 on public procurement (art. 16) requires the value of the contract to be estimated and specifies that its amounts are understood excluding value added tax. The pouvoir adjudicateur (contracting authority) must therefore add VAT to its budget itself.

Insurance is checked before the works begin. For housing whose construction requires an architect, the Act of 31 May 2017 requires contractors, architects and other providers to hold ten-year civil liability insurance, in force since 1 July 2018; the certificate is provided before the works begin (art. 12). This cost is borne by the providers and appears in their prices. Likewise, the professional civil liability insurance of the Act of 9 May 2019 covers architects, coordinators and the sector's other intellectual service providers. What remains with the client is the insurance it takes out itself, depending on its contract and its financing. The detail of these regimes is in the article on compulsory insurance.

Price adjustment is decided at tender stage and paid during the works. In public works contracts, the adjustment clause is compulsory, unless the estimated value is below 120,000 euros and the initial period is below 120 working days or 180 calendar days (general implementing rules, Royal Decree of 14 January 2013, art. 38/7). In private contracts, everything depends on the contract. In both cases, the budget must carry a line, even an estimated one, as soon as the clause exists.

Items that stay open for a long time

Utility connections come late. Water, electricity, gas where relevant, drainage, telecommunications: network operators' quotations are often requested when the project is already well advanced, sometimes during the works. Until they are received, the line remains an estimate and must be labelled as such.

Planning taxes and charges depend on the region and the municipality. They are only known when the permit is issued, and their rules differ between Brussels, Wallonia and Flanders. They cannot be costed from a national ratio.

VAT is not a percentage to apply automatically. Its regime depends on the nature of the project, the use of the building and conditions that must be checked project by project. Rates and their conditions are covered in the article on VAT on construction and its conditions. For a client who cannot recover VAT, it is part of the cost; for a VAT-registered client who recovers it, it weighs mainly on cash flow.

Finance costs follow the payment schedule. Interim interest, arrangement fees, the cost of a guarantee: their amount depends on the pace of interim valuations, and therefore on the programme. A project that slips also costs more in finance.

Keeping the budget in two columns

Each line carries a status: certain or estimated. A line becomes certain when a document commits it: a signed agreement, an accepted tender, an awarded contract, an operator's quotation, an issued permit. As long as no document exists, it is estimated, with its source and its value date.

The contingency is read against the estimated column. The larger the estimated share, the larger the contingency must be. As items become certain, part of the contingency can be released, or reallocated, by a written decision of the client.

Three checkpoints are enough for most projects. On signing the architect's agreement; on submitting the permit application; on awarding the works. At each one, the total cost is recalculated line by line, and the variance against the initial budget is explained item by item, not as a whole.

Checkpoint Lines that become certain Lines still estimated
Architect's agreement architect's fees works, engineers, coordination, PEB, charges, connections, price adjustment
Permit application engineers, design-stage coordination, PEB assignment works, charges, connections, price adjustment
Award of the works works (base amount), planning charges if the permit has been issued connections, price adjustment, extras

The budget is a dated document. Each version carries its date, its value date and the list of assumptions. That is what later makes it possible to show that an overrun comes from a named item and not from a general drift.

This article sets out the rules as at 21 October 2026 and is intended for professional orientation. It replaces neither legal advice nor an examination of the specific case.

Frequently asked questions

The works budget covers what the contractors invoice, excluding VAT, and acts as the design limit. The total cost adds fees, coordination, the PEB assignment, insurance, connections, charges, VAT, finance costs and contingency.

It depends on the structure, and only applies if several contractors are involved. For a total area of 500 m² or more, the client appoints a coordinator for the design stage and one for the construction stage; below that, the designer and then the party in charge of supervising execution do so. In both cases their cost is an item in the project budget, known as soon as they are appointed.

Yes in the total cost, with the regime that actually applies to the project, which the article on VAT helps to check. The budget given to the architect is more clearly expressed excluding VAT.

Those that become certain late: connections, planning charges, price adjustment and finance costs. Labelling them as estimated, with their source, is often enough to avoid the surprise.