One budget, two scopes
The works budget covers what the contractors will invoice, excluding VAT. It is the limit for design: the code of ethics of the Ordre des architectes (Order of Architects) of 16 November 2022 (art. 16) requires the architect to design "within the limits of the brief set in the appointment and of the budget" (unofficial translation).
The total project cost covers everything the client pays out for the building to be built, permitted, insured, connected and financed. It is the client's own limit, and often the one set by its lender or its board.
The classic mistake is to compare one with the other. An architect's estimate "within budget" can push the total cost over if the items outside the works have never been costed. The items a price per m² leaves out are listed in what a price per m² never includes.
The table of items
| Item | Who invoices it | When it becomes known | Where its value comes from |
|---|---|---|---|
| Works (excl. VAT) | contractors | at award, then at the final account | estimate, then tenders, then interim valuations |
| Architect's fees | architect | when the agreement is signed | negotiation (no fee scale) |
| Engineers' fees (structure, building services) | engineering consultancies | on their appointment | tender or agreement |
| Health and safety coordination | design-stage and construction-stage coordinators | on their appointment (by the client from 500 m²) | coordinator's tender |
| PEB or EPB assignment | responsable PEB (Wallonia), EPB-verslaggever (Flanders) | on appointment | provider's tender |
| Insurance | insurers, or included in providers' prices | before the works begin | policies and certificates |
| Utility connections | network operators | late, often during the works | operator's quotation |
| Planning taxes and charges | municipality or region | when the permit is issued | regional and municipal rules |
| VAT | collected by each provider | once the applicable regime is established | the project's tax conditions |
| Finance costs | bank or lender | when the financing is signed, then as drawdowns are made | loan agreement and payment schedule |
| Price adjustment | contractors | during the works | adjustment clause and indices |
| Contingency | nobody (internal reserve) | released up to the final account | identified risks |
Read this table by its third column. Fees are known early; the works become certain at award; connections, charges and price adjustment stay open for a long time. At any date, the budget must therefore carry a certain part and an estimated part, and the second must shrink.
Items known early: fees
Fees are the first certain amounts in the project. The 2022 code (art. 20) requires a written agreement "at the latest when the appointment has been defined": by that date, the amount or the way it is calculated is fixed.
There is no longer a fee scale. The Order's former scale was sanctioned by the European Commission on 24 June 2004, and the 2022 code contains none: fees are negotiated. How they are calculated matters as much as their level. Fees expressed as a proportion of the works amount rise when the estimate rises, which is worth reading before signing. Orders of magnitude are covered in the article on fees and ancillary costs.
Engineers come next. Structure, building services, acoustics depending on the brief: they are often appointed later than the architect, and their cost is only certain at that point. Until they are appointed, the item is an estimate.
Involving an architect is compulsory for works that need a permit, subject to exemptions (Act of 20 February 1939, art. 4, a federal law applicable in all three regions). This item therefore cannot be optimised by removing it, only by defining the appointment.
Items the client triggers itself
Some required participants go into the client's budget, even when the client does not appoint them. That is the case for health and safety coordination and the energy performance assignment.
Health and safety coordination. On temporary or mobile construction sites where several contractors are involved, the Act of 4 August 1996 requires a coordinator to be appointed for the design stage and one for the construction stage (art. 16 and 21). The Royal Decree of 25 January 2001 specifies who appoints them: the client for a structure with a total area of 500 m² or more (art. 5 and 15), and below that the designer and then the party in charge of supervising execution (art. 4bis and 4decies), roles held by the architect where the architect's involvement is compulsory (Act, art. 14). A health and safety plan is drawn up before the site opens (Act, art. 16, 2°), replaced on some small sites by a written agreement between the parties involved (Decree, art. 29), and a file for subsequent works is compiled. The cost is that of the coordinators' tenders; it is known as soon as they are appointed, which must happen early for design-stage coordination.
The PEB or EPB assignment depends on the region. In Wallonia, an approved responsable PEB (energy performance adviser) must be appointed; the initial PEB declaration is attached to the permit and the final declaration follows the works. In Flanders, the bouwheer appoints an EPB-verslaggever (energy performance reporter) before the works begin. In Brussels, for a new build or a major renovation, the declarant appoints a conseiller PEB (energy performance adviser) under the Brussels Code of Air, Climate and Energy Management. The item is costed on the basis of a tender, and the differences between regions are covered in how the region changes the budget.
Items fixed at tender stage
The works amount becomes certain at award, not before. Until then, it is an estimate whose margin of uncertainty narrows from stage to stage: that is the subject of contingency by project stage. Even once awarded, it stays open until the final account: extras, quantity variances and price adjustment are added to it.
In public procurement, estimating is a legal obligation and the estimate is expressed excluding VAT. The Act of 17 June 2016 on public procurement (art. 16) requires the value of the contract to be estimated and specifies that its amounts are understood excluding value added tax. The pouvoir adjudicateur (contracting authority) must therefore add VAT to its budget itself.
Insurance is checked before the works begin. For housing whose construction requires an architect, the Act of 31 May 2017 requires contractors, architects and other providers to hold ten-year civil liability insurance, in force since 1 July 2018; the certificate is provided before the works begin (art. 12). This cost is borne by the providers and appears in their prices. Likewise, the professional civil liability insurance of the Act of 9 May 2019 covers architects, coordinators and the sector's other intellectual service providers. What remains with the client is the insurance it takes out itself, depending on its contract and its financing. The detail of these regimes is in the article on compulsory insurance.
Price adjustment is decided at tender stage and paid during the works. In public works contracts, the adjustment clause is compulsory, unless the estimated value is below 120,000 euros and the initial period is below 120 working days or 180 calendar days (general implementing rules, Royal Decree of 14 January 2013, art. 38/7). In private contracts, everything depends on the contract. In both cases, the budget must carry a line, even an estimated one, as soon as the clause exists.
Items that stay open for a long time
Utility connections come late. Water, electricity, gas where relevant, drainage, telecommunications: network operators' quotations are often requested when the project is already well advanced, sometimes during the works. Until they are received, the line remains an estimate and must be labelled as such.
Planning taxes and charges depend on the region and the municipality. They are only known when the permit is issued, and their rules differ between Brussels, Wallonia and Flanders. They cannot be costed from a national ratio.
VAT is not a percentage to apply automatically. Its regime depends on the nature of the project, the use of the building and conditions that must be checked project by project. Rates and their conditions are covered in the article on VAT on construction and its conditions. For a client who cannot recover VAT, it is part of the cost; for a VAT-registered client who recovers it, it weighs mainly on cash flow.
Finance costs follow the payment schedule. Interim interest, arrangement fees, the cost of a guarantee: their amount depends on the pace of interim valuations, and therefore on the programme. A project that slips also costs more in finance.
Keeping the budget in two columns
Each line carries a status: certain or estimated. A line becomes certain when a document commits it: a signed agreement, an accepted tender, an awarded contract, an operator's quotation, an issued permit. As long as no document exists, it is estimated, with its source and its value date.
The contingency is read against the estimated column. The larger the estimated share, the larger the contingency must be. As items become certain, part of the contingency can be released, or reallocated, by a written decision of the client.
Three checkpoints are enough for most projects. On signing the architect's agreement; on submitting the permit application; on awarding the works. At each one, the total cost is recalculated line by line, and the variance against the initial budget is explained item by item, not as a whole.
| Checkpoint | Lines that become certain | Lines still estimated |
|---|---|---|
| Architect's agreement | architect's fees | works, engineers, coordination, PEB, charges, connections, price adjustment |
| Permit application | engineers, design-stage coordination, PEB assignment | works, charges, connections, price adjustment |
| Award of the works | works (base amount), planning charges if the permit has been issued | connections, price adjustment, extras |
The budget is a dated document. Each version carries its date, its value date and the list of assumptions. That is what later makes it possible to show that an overrun comes from a named item and not from a general drift.
This article sets out the rules as at 21 October 2026 and is intended for professional orientation. It replaces neither legal advice nor an examination of the specific case.