Blog

Cost calculation at the third level of the cost structure

📐 Article8 min read

What you will learn Why the cost calculation is the most important stage of the whole project, what depth standard and ordinance each require and why they diverge, what the determination rests on, and what deviation from the later final cost statement remains defensible.

The Kostenberechnung is the third stage of cost determination and is prepared from the developed design. It serves the decision on that design.

Its real significance, however, lies not in that decision-making function but in the fact that the fee for all basic services is derived from it. A single determination therefore reaches through to work phase 9.

Why this stage carries the whole project

Since the 2009 revision the so-called cost calculation model applies. Under it, the fees for all basic services within a service profile are determined exclusively from the results of the cost calculation, exceptionally from those of the cost estimate. It replaced the earlier stage-by-stage accounting.

An asymmetry follows that is underestimated in practice: a determination made in work phase 3 sets the remuneration for services running into work phase 9. An allowance set too low acts across the entire project duration and can no longer be corrected by later stages.

Where costs rise during construction without any change of scope, the fee basis stays unchanged. Where the commissioned scope changes by agreement and chargeable costs change as a result, a written agreement on adjusting the fee calculation is provided for.

The system of chargeable costs is covered in the branch on chargeable costs under the HOAI. That branch also sets out which cost groups enter in full, conditionally or not at all.

Standard and ordinance require different things

At this stage the divergence between the two bodies of rules becomes especially tangible. The standard describes a procedure, while the regulation attaches a legal consequence to it.

Body of rules Required depth of treatment
DIN 276 in its 2018 edition third level of the cost structure
HOAI in its 2021 version at least the second level

Up to the 2008 edition the standard likewise required only the second level. The deepening to the third level came with the reissue, and the ordinance did not follow.

In practice this means: working in conformity with the standard requires the third level and potentially delivers more than the basic service demands. Confining oneself to the basic service means working at the second level and departing from the current edition of the standard.

Both routes are defensible, but the choice belongs in the contract rather than in the final account. The boundary between basic and additional services is covered in the separate article.

What the determination rests on

The standard names the bases expressly, and they differ markedly from those of the preceding stage. The middle entry is the decisive one.

Basis Scope
Design documents worked-up design drawings at a scale appropriate to the type and size of the scheme, with detail drawings of repeating room groups where applicable
Calculation of the quantities of the reference units of the cost groups
Explanations of the assumptions made

The second point is the decisive difference from the cost estimate. There, costs are derived from area and volume benchmarks; here, quantities are measured from the design and priced.

How costs are determined in detail is left to the designer. In practice a kind of coarse bill of quantities based on quantities and reference units frequently emerges. The results of the specialist designers for structure and building services are incorporated.

A note on structure: accuracy rises noticeably when calculation proceeds by building elements rather than by lump allowances per cost group. The side effect is transparency, since every item remains traceable to a quantity and a unit rate.

What a deepened cost calculation is

Beyond the depth owed, a cost calculation may be prepared and maintained by individual items, lead items, execution types or single building elements. That deepening is a special service rather than a basic one.

Such a deepened cost calculation is always an additional service to be remunerated separately. It must offer the client a discernible added value over the determination owed, or the separate remuneration is hard to justify.

That added value regularly lies in connectivity: a calculation built by building elements and execution types can be carried directly into the tender documents and eases subsequent cost control across procurement. The effort of the deepening is thus recovered in the following phase.

Specialist designers contribute, but not automatically

The lead designer's cost calculation also covers the cost of technical installations and the structure. Those figures are determined by the respective specialist designers, whose services in practice are frequently commissioned only after work phase 4 is complete.

A recurring situation arises: the cost calculation is to be prepared in work phase 3, but the specialist design from which a substantial part of its figures should come has not yet been commissioned at that point. The conflict cannot be resolved, only decided.

Three routes are open, and the choice belongs on the record. It determines how robust the basis for the fee ultimately is.

Route Assessment
Commission the specialist designers earlier professionally the best route, since the cost calculation rests on plant actually designed rather than on assumptions
Work with benchmarks and flag the assumption workable, but the origin of the figures and the assumed specification must be stated, or the item cannot be explained later
Update once the specialist design is available permissible, but the cost calculation is a one-off determination at a defined point in time

The defensible deviation

For deviation between the cost calculation and the later final cost statement several figures circulate side by side, which rules out their use as a calculation quantity. A tolerance that varies by half depending on the source is no yardstick for a breach of duty.

Source of the figure Range quoted
widespread figure ± 20 %
narrower figure 10 to 20 %

No prescribed tolerance limit exists. Neither the standard nor the ordinance contains one. What does exist is case law on liability for incorrect cost determinations, which provides orientation. The magnitudes cited there run at roughly 15 to 25 per cent, with the individual case always governing.

The distinction matters in practice because it changes the argument. A deviation is not impermissible because it exceeds a percentage; it becomes problematic where it rests on a faulty or incomplete determination. Conversely, even a smaller deviation can be assailable where the determination omitted obvious items.

The most effective safeguard follows: documenting the assumptions. A cost calculation showing, for every material item, the quantity applied, the unit rate and its origin remains explicable even where a deviation later arises. One showing only totals does not.

Net or gross

The standard permits both presentations and requires only that the form chosen be stated. For a client unable to reclaim input tax, such as in private housing, the gross presentation is the one that matters in practice.

For the chargeable costs derived from it, however, the HOAI governs: value added tax is not part of them. Working gross therefore requires converting back for the fee determination. The clean solution is to work net and carry value added tax as a separate line.

This article reflects the position at the date of checking and serves professional orientation. It does not constitute legal advice and does not replace assessment of the individual case.

Frequently asked questions

The stage that fixes the project on the cost side, at the third level of the classification. It rests on the design development.

Because it forms the basis for decisions and for the fee. Later corrections are laborious.

On quantities from the design development and on benchmarks per item. The specialist designers contribute without taking on responsibility.

A determination going beyond the basic service, to be agreed separately. The article describes the boundary.

Cost planning under DIN 276: cost groups and cost determination