Blog

KG 300 building fabric: structure and allocation

📐 Article8 min read

What you will learn How cost group 300 is built at the second and third levels, what logic the ordering follows, where the boundaries with cost groups 200, 400 and 500 run, and how strip-out work in conversions is to be allocated.

Cost group 300 captures the fabric of the building. It is the largest group in the standard and carries the greater part of building cost in most building types.

Since the 2018 edition it applies uniformly to building construction, civil engineering and infrastructure works. The formerly separate structures were consolidated.

The second level

Cost group Designation
KG 310 Excavation and earthworks
KG 320 Foundations and substructure
KG 330 External walls and external vertical elements
KG 340 Internal walls and internal vertical elements
KG 350 Floors and horizontal elements
KG 360 Roofs
KG 370 Infrastructure installations
KG 380 Built-in fixtures
KG 390 Other measures for building fabric

The ordering follows the construction sequence from the ground up: excavation, foundations, rising structure, floors, roof. That logic eases checking for completeness, because a missing item stands out within the sequence.

Groups 330 to 350 each carry the addition of vertical or horizontal elements. It stems from consolidation with civil engineering, where the terms wall and floor do not always fit.

A look at the third level

Cost group 330 shows how finely the standard subdivides. The third level reaches the individual element.

Cost group Designation
331 Loadbearing external walls
332 Non-loadbearing external walls
333 External columns
334 Openings in external walls
335 External wall claddings, external face
336 External wall linings, internal face
337 Unitised external wall systems
338 Solar shading
339 Other items relating to external walls

Two points are notable. First, the standard separates loadbearing from non-loadbearing elements, which is sensible for cost determination because the two carry entirely different unit rates. Second, claddings appear separately for the external and internal face, which eases allocation in a facade refurbishment.

Position 334, openings in external walls, covers windows and external doors. They are therefore part of the fabric and not of the technical installations, even where motorised. The drive itself may belong to building automation.

The boundary with cost group 200

Cost group 200 covers preparatory works, that is preparing the site and servicing it. It must be kept apart from cost group 300, because it is not chargeable.

The dividing line runs at the building. Full demolition of an existing building belongs to preparatory works. Partial demolition within a conversion, by contrast, belongs to cost group 300, and specifically to the group whose element it affects.

This rule applies expressly to repair, temporary support and dismantling in conversions and modernisations too: the costs are to be shown within the cost groups affected and form no group of their own. The element reference therefore governs in existing buildings as well.

In practice this means a cost determination in existing buildings carries strip-out costs distributed across the whole of cost group 300. Consolidating them into a single collective item instead loses comparability with new build benchmarks by element, which in existing buildings would be the most important test.

The boundary with cost group 500

What governs is connection to the building. Roof, facade and interior planting belonging to the building count within cost group 300. External works outside the building and designed open spaces count within cost group 500.

The boundary is not always clear-cut at ground-level junctions. A canopy structurally part of the building belongs to cost group 300; a freestanding shelter in the external area to cost group 500. In such cases an explicit determination within the cost estimate is advisable, so that the allocation stays the same across every stage.

The boundary with cost group 400

This is the most fee-relevant allocation question in the whole standard, because it governs application of the special rule for technical installations. It governs the level of the fee basis.

As a rule of thumb: cost group 400 covers the technical installations or parts of installations built into the structure, connected to it or permanently joined to it. Cost group 300 covers what is fabric.

Typical borderline cases:

Element Allocation
Service riser as a constructed element KG 300, fabric
Pipework within the riser KG 400, technical installation
Openings and chases for services KG 300, within the element group affected
Lift shaft KG 300, fabric
Lift installation KG 400, conveying installations
Window with motorised drive window KG 300, drive and control by installation

The details and the system of technical installations are covered in the article on KG 400. It also sets out which installations belong to that group.

Using position 390 correctly

Like every cost group, 300 ends with a catch-all position, here 390 other measures for building fabric. It is not a collecting point for anything unclear.

It is intended for costs belonging to the fabric in substance but not attributable to any element group, such as overarching measures connected with the fabric. A high share in that position indicates an incomplete structure.

It is not intended as a repository for items whose allocation is troublesome. A conspicuously large position 390 is a warning sign: it makes the determination incomparable with benchmarks, since comparison proceeds by element group, and it is hard to explain to a client.

Reference units by cost group

Every cost group has a reference unit in which quantities are measured. It is the quietest and simultaneously most effective part of the structure, because it governs whether an item is comparable at all.

Cost group Usual reference unit
310 Excavation cubic metres of excavation
320 Foundations square metres of foundation area
330 External walls square metres of external wall
340 Internal walls square metres of internal wall
350 Floors square metres of floor
360 Roofs square metres of roof

The benefit shows when comparing two designs. A benchmark per square metre of gross floor area for the whole of cost group 300 does not reveal why one design costs more. Benchmarks per element area do: an articulated form carries more external wall area per square metre of usable area, and a design with long spans carries more expensive floors per square metre.

A recommendation follows for cost determination that costs little effort: alongside the amount per cost group, carry the corresponding quantity. Only then does a later deviation reveal whether quantity or unit rate was the cause.

What the structure achieves for cost control

The element structure of cost group 300 is why a target-actual comparison across the stages is possible at all. It stays identical through cost estimate, cost calculation and final cost statement while quantities and prices are refined.

That advantage is lost as soon as ordering by procurement package begins with the pre-tender estimate, because trades and element groups do not coincide. A drylining contractor works on internal walls, floors and fixtures simultaneously.

The workable solution is to retain the element structure as the leading one and carry the procurement packages as an additional allocation. The article on trade-oriented cost structure covers that variant.

This article reflects the position at the date of checking and serves professional orientation. It does not constitute legal advice and does not replace assessment of the individual case.

Frequently asked questions

The building construction, classified at the second and third levels. The article shows both levels.

At the preparatory measures, which precede the building itself. The allocation decides whether costs are chargeable.

Between construction and services, which blurs at penetrations. The article names the standard cases.

Because it affects the fee, comparability and later analysis. A wrong allocation carries through to the final account.

Cost planning under DIN 276: cost groups and cost determination