Blog

How to determine the applicable requirement

📐 Focus6 min read

What you will learn Six questions in the right order, why the date is the first question, what to check in the regulation, buildings with several uses, and the most frequent errors.

The applicable requirement cannot be taken from memory. The limit values changed in 2025, which makes earlier experience a source of risk rather than an advantage.

1. Six questions in the right order

Each narrows the possibilities, and the order is substantive. The questions are asked in a fixed order.

# Question Note
1 When the application is or was submitted determines the applicable version
2 Whether the building is new or existing two different regimes
3 If existing, whether this is substantial reconstruction the definition comes from the regulation
4 What the intended use is, and whether there are several several uses require a separate calculation
5 What the room-temperature area is within the meaning of the regulation, not the register's
6 Whether an exemption or a relief applies an exemption removes the requirement, a relief lowers the level

Only then should the limit value be taken from the annex to the regulation in force. A value taken earlier may be wrong.

2. Why the date is the first question

Here is the practical core of the article, and one specific trap. The trap concerns the application date.

According to information published by the Ministry of Climate, updated requirements apply to buildings whose building permit application or building notice is submitted from the date of entry into force, and earlier requirements apply to documents submitted before it. The date belongs in the document.

The trap lies in the dating: some published materials give the date of entry into force as 1 March 2025, whereas entry into force was later changed to 1 June 2025. The date must therefore be checked against the legislation in force rather than against commentary, which may date from before the amendment. This is exactly the same pattern as in the building permit procedure.

3. What to check in the regulation

Four things no summary provides and none of which can safely be memorised. They must be taken from the regulation in force.

The applicable limit value, which depends on the intended use and, for houses, on area. The definition of substantial reconstruction, where the building is existing. The definition of room-temperature area, which differs from the area recorded in the building register. And the precise wording of the exemptions, where an exemption is relied on.

4. Buildings with several uses

A separate case requiring a separate calculation, covered by its own article. It concerns buildings with several uses.

According to information published by the Ministry of Climate, each use whose heated area exceeds 10 per cent of the building's total heated area is assigned the energy performance value corresponding to that use. The building's energy performance value is the weighted average of the parts' values by heated area, and the maximum permitted value is likewise a weighted average, calculated from the parts' limit values.

The weighted average must therefore be calculated twice: for the result and for the requirement. Doing it once gives the wrong answer.

5. The most frequent errors

Four errors all lead to the wrong requirement, and the first is the likeliest with an experienced designer. Experience can mislead here.

Error Why it happens
Reusing an earlier project's limit value the values changed on 01.06.2025
Using the wrong date some materials name 1 March
Using the register's area the regulation's concept of area is different
Assuming an exemption without checking an exemption must be evidenced

The first arises precisely from experience: anyone who has made similar calculations before trusts memory where the text has changed in the meantime. The requirements have changed in the meantime.

Summary and four practical rules

The applicable requirement is determined by six questions running from the application date to the plot's exemptions and reliefs, and only then is the limit value taken from the annex to the regulation in force. The date comes first because it determines the applicable version, and there is a common trap here: some materials date the 2025 changes to 1 March, whereas entry into force is 1 June 2025. In a building with several uses the weighted average has to be calculated twice, for the result and for the limit value.

Four rules: fix the application date before anything else. Check the date of entry into force against the legislation in force, not commentary. Take the limit value from the annex to the regulation for every project afresh. Use the regulation's concept of area, not the register's.

This article offers professional orientation as at the date of verification. It replaces neither the regulations in force nor the assessment of a competent specialist.

Frequently asked questions

Through a sequence of questions, each narrowing the possibilities. Only then is the limit value taken from the annex to the regulation in force.

The application date, on which the applicable version depends. The date belongs in the document.

Because four things must be taken from the regulation in force. They cannot safely be memorised.

Four errors, the first of which arises precisely from experience. The requirements have changed in the meantime.

Building energy performance in Estonia