The starting point of a renovation

📐 Topic6 min read

What you will learn Why a renovation does not begin with works, three things that must be known beforehand, what the baseline decides, in what order to proceed, and what happens when the order is wrong.

A renovation usually begins with a list: facade, windows, roof. The logic of the support says something else, and that changes the order of the whole preparation.

1. Why a renovation does not begin with works

Three reasons, all leading to the same conclusion. Support funds not the works but the result, and what matters is whether the building's energy class improves, as covered by the article on the logic of the support. The result is measured against the initial situation, so the initial situation must be known first. And some works may already have been done, which limits later options, as covered by the article on works already done.

Beginning from a list of works is therefore the wrong end. The right end is the building's present condition, in energy terms, in technical terms and in terms of the register data.

2. Three things that must be known beforehand

Each answers a different question, and the third is the most often left aside. It concerns the technical condition.

What to know What it answers
The building's current energy class the baseline for measuring the result
Whether register data match reality the precondition for applying
Technical condition what actually needs doing

The third is left aside because it is not directly tied to the support. What is eligible is not, however, the same as what is necessary: a leaking roof has to be repaired whether or not it raises the energy class.

3. What the baseline decides

Four things depend on the current class, and the first may end the exercise altogether. The class sets the class gain required.

Whether support is available at all, since according to professional sources it cannot be applied for where the building already has the best possible class. How large a gain is required, that is class C for full reconstruction and at least a one-class gain for partial. What volume of work that gain requires. And whether the full or the partial route is realistic, as covered by the article on the two routes.

None of these questions can be answered without the baseline, and commissioning a design before it risks a solution that does not meet the conditions. The baseline therefore comes first.

4. In what order to proceed

Five steps whose order saves money, and the fourth decides the programme. Reversing the order costs money.

# Step
1 Check the building register data (register data)
2 Establish the current energy class
3 Assess the technical condition (audits)
4 Check the support conditions and the position of the round
5 Only then commission the design

The fourth step matters particularly because rounds open and close cyclically, as covered by the article on the rounds. Preparation must be ready when a round opens.

5. What happens when the order is wrong

Three typical consequences, and the second is the most frequent. It concerns redoing the design.

Consequence When it appears
The design is commissioned but does not meet the support conditions at application, and the design has to be redone
The register data are wrong the application is inadmissible until corrected
Works are partly done this limits the type of support available

The second is also the most easily avoided, since register data are not looked at until they are needed. Correcting them takes time, and that time does not exist once a round is already open.

Summary and four practical rules

A renovation begins not with works but with the building's present condition, because support funds a result and the result is measured against the initial situation. Before the design one must know the current energy class, whether the register data match reality, and the technical condition, of which the last is the most often left aside even though what is eligible is not the same as what is necessary. The order of the five steps saves money, and of the three consequences of getting it wrong the most frequent is discovering wrong register data when there is no time left to correct them.

Four rules: check the register data before anything else. Establish the class before commissioning a design. Assess the technical condition, including works the support does not cover. Check the position of the round before commissioning the design, not after.

This article offers professional orientation as at the date of verification. It does not replace the conditions of the body granting the support.

Frequently asked questions

With establishing the baseline: the building's current energy class, the register data and its technical condition. Without them a designer cannot start work.

Because the class gain required, and therefore the whole volume of work, depends on it. Where the gap to the required class is too large, it can reshape the entire exercise.

Five steps whose order saves money, the fourth of which decides the programme. The design is commissioned only once the baseline and eligibility are clear.

Three typical consequences, the most frequent being that the design has to be redone. Redoing it costs more than the preparation that would have prevented it.