What the contract price covers and what it does not

📐 Article

By , construction economist

Information verified on 12 min read

What you will learn How the subject matter of the contract is read from the signed documents, what the Supreme Court's case-law says about works that "should have been" in the tender, why the design stage determines the number of disputes and which terms let the client close the scope of the price in the contract.

The question "is this in the price?" looks technical, but it is above all a legal one. The price covers the subject matter of the contract, and the subject matter is what is written in the signed documents and what can be inferred from them on interpretation, not what would be technically necessary to build. The more is left to interpretation, the larger the share of the final cost that only becomes clear on site.

The price is the price of an agreed result

The Law of Obligations Act (võlaõigusseadus, VÕS) defines the contract for work through its result. The töövõtja (the contractor) undertakes to make or alter a thing or to achieve another agreed result (the work), and the tellija (the client) undertakes to pay a fee for it (§ 635(1)). The fee is therefore tied to the agreed work. Anything that falls outside the agreement needs a separate agreement or ends up in dispute.

The agreement is read under VÕS § 29. First, the parties' actual common intention is sought (subsection 1). If it cannot be established, the contract is interpreted as a reasonable person would understand it in the same circumstances (subsection 4). Account is taken, among other things, of the preliminary negotiations, the parties' conduct after the contract was concluded, the usual meaning of expressions in the relevant field of activity and practices (subsection 5), and contract terms are interpreted in relation to one another (subsection 6).

For the client, this has two practical consequences. The scope of the price is not written in one sentence but in all the documents together. And what the parties do on site or say at a meeting may later influence the interpretation of the contract, which is why agreements must be in writing.

Technical necessity does not prove that work is in the price

The trend of decisions described in the Supreme Court's case-law review is uncomfortable for the client: the mere fact that work should have been in the tender, or was technically necessary, does not prove that it was in the price (Supreme Court civil chamber judgment of 19.12.2017, 2-15-15662/55, para 13; Supreme Court civil chamber judgment of 20.09.2017, 2-13-40856/124, para 14). In a dispute over the final invoice, the client therefore cannot rely solely on the argument that a professional contractor should have foreseen the work.

According to the same review, lisatööd (additional works) are works that fall outside the subject matter of the contract and require an agreement; without an agreement, there is no contractual basis for claiming a fee. The protection therefore works in both directions. The contractor cannot claim a fee under the contract for work that was not agreed, but where the work genuinely falls outside the subject matter, the client cannot require it to be done for the agreed price either. Without a clear contract, nobody wins: the result is a dispute settled on the basis of the documents and their interpretation. The distinction between additional work and changed work is covered in the article Additional work or changed work: why the difference matters.

The third trend concerns the client's own contribution. According to the Supreme Court's case-law review, the client is responsible for the conformity of the design it gives to the contractor (2-15-15662/55, para 19). If the design on which the price was based is deficient, it does not go without saying that the gap is filled at the contractor's expense. In that case, the client turns to its own designer under the contract between them.

The design stage determines how much is left to interpretation

The more precise the document on which the price is given, the less interpretation there is in the final invoice. The regulation on requirements for a building design (regulation no 97) divides design into three stages: eelprojekt (the preliminary design), põhiprojekt (the main design) and tööprojekt (the working design) (§ 5(1)). The content of each stage is described in the regulation, and that content also tells you how much of the price can be fixed on its basis.

Stage What the regulation requires What it means for the contract price
Preliminary design the architectural solution and technical principles; an analysis of the suitability and economy of the solutions (§ 8(1) and (3)) enough for an order of magnitude; if a fixed price is given, much of the content is left to the contractor's interpretation
Main design solutions and quality "with a level of detail that makes it possible to determine the budgeted cost of the building, organise the construction procurement and prepare a quotation for construction" (§ 9(1), unofficial translation) the stage that the regulation itself links to the quotation
Working design a level of detail that makes it possible to build (§ 10(1) and (3)) reduces interpretation further, but may be completed only after the contract is signed

The stages are also linked in law. A previous stage approved by the client becomes the binding brief for the next stage (§ 5(3)). If the contract is signed on the basis of the main design and the working design is prepared later, it is worth stating in the contract whether the refinements in the working design are included in the price, or in what case they are treated as a change. Which surveys and permits a design requires and how they affect costs is covered in the article on design, surveys and permits; what matters here is only that the uncertainty left by a missing survey reaches the price either as a reservation or as a later claim for additional work.

Conflicts within the documents

Even a precise design can be internally inconsistent, and a conflict is a price issue. Under regulation no 97, a design must be free of conflicts (§ 2(1)), and for conflicts between documents of the same stage, the seletuskiri (the explanatory memorandum, here called the specification) takes precedence first, then the drawings, then the other documents (§ 6(2)). The rule, its limits and why it pays to write the order into the contract itself are covered in the article When the drawings and the specification conflict.

How to close the scope of the price in the contract

The client cannot avoid disputes entirely, but can reduce the part of the contract that will need interpreting later. The terms below do this. They are questions of wording, not of pricing.

  • The list of contract documents. The contract should name every document that determines its content: the main text of the contract, the special conditions, the design with its stage, version and date, the technical description, the price schedule, the tender, the record of questions and answers. A document that is not on the list should not be part of the contract; a document that is on it is, as a rule, part of the contract together with its notes.
  • The order of documents. If the list contains several documents, the contract must say which of them prevails in the event of a conflict. Without this, the answer is left to the interpretation of the contract as a whole under VÕS § 29.
  • The tender's reservations. The assumptions and exclusions in the tender's covering letter or in the notes to the price schedule may become part of the contract if the tender is a contract document. The client should read them and accept, delete or amend them before signing, not discover them with the first claim for additional work.
  • Express exclusions and inclusions. The works that most often cause disputes are those on the boundary between the building and the plot: connections to utility networks, external networks, external structures and landscaping, demolition and opening up of existing structures, temporary site facilities, testing and as-built documentation. For each such item, the contract should show whether it is in the price, outside the price or for the client to organise.
  • Client supplies and obligations. If the client supplies materials, equipment or preconditions for the works, the contract must say what the contractor does with them and what is in the price, for example installation, acceptance on site and connection.
  • The change procedure. Since the subject matter cannot be complete, the contract must say how work that later proves necessary is handled: who may order it, in what form the agreement is made and when the work may start. The principles in this branch are described in the article on additional work and changed work, and the pricing side in the article on how a budget becomes a tender.

Before comparing several tenders, it is worth checking that they price the same subject matter; a separate article explains why two quotations are often not comparable. All the points above are gathered as questions in A construction contract checklist before signing.

When a dispute about scope arises on site

If the contractor states that a piece of work is not in the price, the client's first step is to read the documents, not to argue about necessity. The question is whether the work is in the subject matter of the contract, and the answer comes from the contract documents, their order and the preliminary negotiations. It helps to ask the contractor to show which document it relies on and to compare that with the version of the design that was priced.

The second step is to keep the dispute and the work separate. If the work is necessary, the client may have it done, but should record in writing that it does not accept the work being treated as additional work and that the question of payment will be settled separately. Such a note in the ehituspäevik (the construction diary) or in the minutes of a site meeting prevents a later claim that the client tacitly agreed to an additional fee.

The third step is to decide at the right time. A dispute postponed until the final invoice is settled when the client no longer has levers or options. A decision taken before the work starts allows the client, if necessary, to change the solution or reduce the scope.

A fictional example

The following example is fictional and intended only to illustrate the reasoning. A client signs a contract to build a warehouse on the basis of the main design. The contract lists as contract documents the contract, the main design and the price schedule, but not the tender's covering letter. The design shows the stormwater connection up to the boundary of the property, but not beyond.

During construction, it turns out that the connection must be taken to the public network. The contractor presents this as additional work. The client argues that the connection was technically necessary and should have been in the tender. According to the trend of case-law, technical necessity alone does not prove that the work was in the price; what is decisive is what the documents show. Since the design showed the connection only up to the property boundary, the contractor's position is stronger. If the contract had contained the sentence "the price includes all connections to public networks", the situation would be the reverse.

This article describes the legal rules as at the date of checking and is intended for professional orientation. It does not replace legal advice or a review of the specific case.

Frequently asked questions

Not necessarily. According to the Supreme Court's case-law review, neither technical necessity alone nor the fact that the work should have been in the tender proves that it was in the price; what is decisive is the interpretation of the documents under VÕS § 29.

They may be part of the contract if the tender is among the contract documents or if the parties have otherwise taken them into account. This is why the covering letter must be read before signing and, if necessary, the terms changed in the contract.

Regulation no 97 links the level of detail that allows a quotation to be prepared to the main design (§ 9(1)). A contract can be signed on the basis of an earlier stage, but then it must be accepted that a greater part of the content will be left to interpretation or later agreement.

According to the Supreme Court's case-law review, the client is responsible to the contractor for the conformity of the design it supplied. The client can claim its loss from the designer under the contract between them.