The example project's structural scheme
In the baseline variant the walls between flats are load-bearing and continue straight down into the car park. The car park column spacing has been chosen so that two or three parking spaces fall between two walls and the walls do not obstruct the driving aisle. The load travels from the roof to the foundations along a single straight path, without beams or thickened slabs.
Such alignment does not happen by itself. A parking space is approximately 2.5 m wide, and a spacing of two or three spaces gives a distance between partition walls of approximately 5 or 7.5 m. If the layout of the flats requires a different spacing, one of the two must be adjusted, and that decision is made during the sketch design.
Variant 1: walls do not line up with the car park columns
If the partition walls between flats are positioned without regard to the car park, they cannot continue down into it. At the level of the car park roof slab the load must be transferred by beams or a thickened slab bearing on the car park columns.
Transfer raises the price in several ways at once. Beams and a thicker slab need more concrete and reinforcement, the columns take a greater load and need larger foundations, and the car park height may increase, which lengthens the ramp and deepens the excavation. In addition, design and construction become more complex, because the transfer structures must be complete before the upper storeys can be built.
Variant 2: walls or columns in the flats
A load-bearing wall scheme is common in apartment buildings, because the walls simultaneously provide support, sound insulation and fire separation. A column scheme gives a freer plan and simplifies later alterations, but the partition walls must then be built separately and must meet the acoustic and fire safety requirements on their own.
Which is cheaper depends on what the client values. For an apartment building built for sale, where the layout will not be changed later, the load-bearing wall scheme is often simpler. For a rental building, or one whose flat sizes may change over time, the flexibility of a column scheme may be worth more than its additional cost.
The price logic of timber and prefabricated construction and of masonry and block construction is covered in the articles timber frame and prefabricated and masonry and block construction. Only one conclusion is repeated here: factory-made elements require solutions to be decided before production, which makes an early decision on the structural scheme even more important.
Variant 3: cantilevers, balconies and projecting volumes
A cantilever is a structure that extends beyond its support. A small balcony is common and its solutions are well known, but large projecting volumes that carry rooms require stronger slabs, beams or ties and complex thermal bridge solutions.
The price of balconies also depends on how they are connected to the building. A balcony that is structurally separate from the building or rests on its own columns may be simpler to build than one fixed to the edge of the slab that needs an insulated connection. Which solution fits is decided by the structural engineer, but the client should know that the choice affects the price of both the frame and the facade.
Fire safety and material
The fire resistance requirements for the structural frame depend on the building's use, height and fire safety class, as set out in § 5 and § 6 and annexes 3 and 4 of regulation no. 17 of the Minister of the Interior Ehitisele esitatavad tuleohutusnõuded (fire safety requirements for buildings). A four-storey apartment building with an underground car park must meet the requirements for both the flats and the car park, and the car park requirements may differ.
The requirements affect the choice of material and therefore the price. A timber structure may need additional protection, a concrete structure a greater cover. These requirements must be checked during the sketch design together with a fire safety specialist, not after the structure has been chosen.
What must be aligned before the preliminary design
The most important thing is to overlay the car park and flat layouts before either of them is final. At least three things must be checked:
- whether the load-bearing walls or columns of the flats continue into the car park;
- whether the car park column spacing suits the parking spaces and the driving aisle;
- whether the stairwells and lift shafts are in the same place on both plans.
If these three things are consistent, most of the transfer structures disappear. If not, a decision must be made whether to change the flat layout, change the car park layout or pay for the transfer.
Summary
The price of the structural scheme depends more on the load path than on the material. Aligning the walls of the flats with the car park columns is the most beneficial decision, because it eliminates transfer beams and thickened slabs. Walls or columns and the number of cantilevers are the next choices, and their price must be assessed together with layout flexibility and the facade.
Legal sources: riigiteataja.ee, Building Code (ehitusseadustik); regulation no. 17 of the Minister of the Interior “Ehitisele esitatavad tuleohutusnõuded” (fire safety requirements for buildings, § 5, § 6). Checked on 26 November 2026.