Why cost is decided before prices
The price per square metre is a consequence, not a starting point. The guide to construction costs in Estonia shows that the price of the same building can vary roughly twofold depending on the level of completion, and that the building's shape and size explain part of the difference. For an apartment building there is one more factor that the price ranges for detached houses do not show: the underground car park, which can be the most expensive single part of the building.
The stages of a building design, the eelprojekt (preliminary design), the põhiprojekt (main design) and the tööprojekt (working design), are laid down in § 5 of regulation no. 97 of the Minister of Economic Affairs and Infrastructure Nõuded ehitusprojektile (requirements for building design documentation). The preliminary design fixes the architectural solution and the principles of the engineering solutions and analyses their suitability and economy (§ 8), and when a building permit is applied for, the competent authority assesses the design against the preliminary design requirements, whatever stage is submitted (§ 13). The later a decision changes, the more parts of the design have to be redone, and after the construction contract has been signed every change becomes additional or variation work, whose price is no longer set by competition.
The accuracy of an estimate depends on how much has been decided. The article on estimate accuracy by design stage explains why an early estimate is a wide range. This article turns the question around: which decisions move that range the most.
Example project: a four-storey apartment building with 24 flats
All the articles in this branch use the same example project so that the effects are comparable. The figures are rounded and only show the logic of the calculation.
| Indicator | Value |
|---|---|
| Number of flats | 24 |
| Storeys above ground | 4 |
| Building dimensions | 40 m × 15 m, building footprint 600 m² |
| Above-ground gross floor area (brutopind) | approximately 2,400 m² |
| Facade area | approximately 1,320 m² (perimeter 110 m, height approximately 12 m) |
| Underground car park | 24 spaces with ramp and storage units, approximately 880 m², of which 280 m² under the courtyard outside the building footprint |
| Ground | load-bearing soil at shallow depth, groundwater below the car park floor |
The ratio of facade to gross floor area is 1,320 / 2,400 = 0.55. This ratio is the simplest measure of compactness and is used throughout the branch.
No amount is calculated for the example project here. The guide construction costs in Estonia gives its ranges by level of completion and by house technology (prefabricated, timber frame, block), and its worked example is a 160 m² timber frame house, so they do not fit a 24-flat apartment building and do not include an underground car park. Estonian public sources do not give a price per square metre for apartment buildings on which the calculation could reliably be based either, which is why the whole branch compares quantities and works, not euros.
Method: one assumption at a time
Each article changes only one assumption in the example project and keeps everything else the same. This shows which works a decision affects and in which direction, without several changes masking one another. The effects of decisions do not always add up: a car park that stays under the building also simplifies the structural scheme, and the combined effect of two decisions must be assessed together, not by summing.
The comparison is made on total cost, not on the price per square metre. If the car park is dropped, the floor area decreases and the price per square metre may rise even though the building becomes cheaper. For the same reason, the article why two quotations are not comparable says that the total sum and the scope must be compared.
Five decisions on the example project
Compactness and number of storeys
A building whose facade area is small relative to its gross floor area costs less both to build and to heat. If the plan depth of the example project falls from 15 metres to 12 metres with the same footprint, the facade grows to approximately 1,488 m², an increase of 168 m². Changing the number of storeys has opposite effects on the roof and foundations on the one hand and on the facade and stairwells on the other. More detail in the article building compactness.
Underground car park
The 280 m² of car park under the courtyard means additional excavation, a waterproof roof slab able to carry landscaping and a longer external wall. If the car park is limited to the building footprint, 12 spaces fit there and the other 12 must be provided above ground, if the detailplaneering (detailed spatial plan) and the plot allow it. The calculation is in the article underground car park or surface parking.
Structural frame
If the partition walls between flats do not line up with the car park columns and load-bearing walls, loads must be transferred by beams or thickened slabs. This is one of the most expensive mistakes in a structural scheme, because it cannot be seen on the facade or on the plan, yet it increases the quantity of concrete and reinforcement. The options are in the article structural frame.
Facade
The price of a facade is set by the system, the proportion of window area and the number of details. The same architectural idea can often be kept with a cheaper system if this is decided before the building permit drawings. The comparison is in the article facade cost.
Life-cycle costs
Not everything that lowers the construction price is a saving. Thinner insulation, simpler ventilation or a cheaper roof covering can raise costs that are later borne by the flat owners or the landlord. Who pays depends on whether the developer sells or remains the owner. This is covered in the article building life-cycle costs.
Foundations and ground
Ground is the sixth factor, but it is already covered in the article foundations and ground conditions. The example project's assumption, load-bearing soil and low groundwater, is favourable. On weak soil or with high groundwater the price of an underground car park changes the most, and it is therefore worth commissioning a ground investigation before the extent of the car park is decided.
Summary: what each decision moves
| Decision | Assumption changed | Works affected | Direction of effect |
|---|---|---|---|
| Compactness | plan depth 12 m instead of 15 m | facade, windows, insulation, heating energy | more expensive |
| Underground car park | car park under the building only, 12 spaces above ground | excavation, car park roof slab, external walls, ramp, outdoor parking area | cheaper |
| Structural frame | partition walls do not line up with the car park columns | transfer beams, slab thickness, reinforcement | more expensive |
| Facade | simpler system, same window area | cladding, substructure, details | cheaper |
| Life-cycle costs | thinner insulation, simpler building services | construction price and running costs | cheaper to build, more expensive to run |
The table contains no amounts, because Estonian public sources do not give prices for apartment building elements on which the example project calculation could reliably be based. The direction and the list of affected works are nevertheless what the designer and the client need to know during the sketch design.
The order in which to decide
The order follows from what is a precondition for the other decisions. The number of parking spaces and the extent of the car park come first, because they determine the excavation, the structural scheme and the use of the plot. Second come the number of storeys and the plan depth, which determine the facade area. Third is the structural scheme, which must suit both the flats and the car park. The facade system and the technical solutions come last, but before the building permit application.
The number of parking spaces is not the designer's free choice. It is set by the local authority's plans, above all the detailed spatial plan, or by the projekteerimistingimused (design conditions), whose tasks include setting the principles of traffic organisation (Planning Act § 126(1)(7), Building Code § 26(4)(9)). If the number can be reduced when the plan is drawn up, this is the biggest saving that can be made on the car park at all.
When it is already late
If the tenders have already come in and exceed the budget, the time for design decisions has passed. For a public contracting authority, the article when all tenders exceed the estimated value explains what the riigihangete seadus (Public Procurement Act) allows. If the budget is exceeded during construction, the client's rights are covered in the article substantial overrun of the estimate and the duty to notify. Preparing and monitoring the budget is covered in the guide construction budgeting and cost control.
Savings at the tender stage usually mean reducing the scope or choosing a cheaper tenderer. The lowest price is not always the cheapest, and this second route is risky, because a cheaper tender may cover a smaller scope.
Legal sources: riigiteataja.ee, Building Code (ehitusseadustik, § 26); regulation no. 97 of the Minister of Economic Affairs and Infrastructure “Nõuded ehitusprojektile” (§ 5, § 8, § 13); Planning Act (planeerimisseadus, § 126). Checked on 26 November 2026.