Substantial overrun of the estimate and the duty to notify

📐 Article

By , construction economist

Information verified on 12 min read

What you will learn The full text of VÕS § 639, the three conditions under which the contractor may claim an overrun of a non-binding estimate, what happens if the contractor does not give notice, the client's right to terminate the contract because of the overrun, what case law draws from foreseeability, and what the client does when the notice arrives.

A non-binding estimate often looks to the client (tellija) like a safe compromise: the price is known, but the contractor (töövõtja) does not have to guarantee it. In fact, the law does not let the contractor exceed a non-binding estimate freely: it may claim contractual extra payment for the overrun only when three conditions are met together, and one of them is notifying the client without delay. This article is about how to check those conditions and how, when the notice arrives, to take a decision whose cost is known in advance.

What the word estimate means here

In this article, estimate (eelarve) means, in the sense of § 639 of the Law of Obligations Act (võlaõigusseadus, VÕS), the estimated cost of the work agreed in the contract for work (töövõtuleping). It is not the contractor's internal detailed budget covered in the budgeting guide. The law allows the parties to agree that the estimate is either binding or non-binding for the contractor, and if there is no such agreement, a binding estimate is presumed (§ 639(1)). How to tell the two types apart and which contract clause reverses the presumption is described in the article a binding or a non-binding estimate.

With a binding estimate, the question of an overrun does not arise in the same form. According to the Supreme Court (Riigikohus) case-law review "Töövõtuleping" ("Contract for work", 2022), where the estimate is binding the contractor cannot claim payment above it (Supreme Court judgment of 19.12.2017 no 2-15-15662/55, para 12). The procedure described below therefore applies to a non-binding estimate.

The text of the law

VÕS § 639 "Exceeding the estimate" is short, and the client's whole protection lies in three subsections. The following is an unofficial translation.

Subsection Text of the Act
subs. 1 "A contract for work may provide for an estimate of the work which is either binding or non-binding on the contractor. In the absence of such an agreement, the estimate is presumed to be binding."
subs. 2 "If a non-binding estimate is substantially exceeded, the contractor may claim payment of the fee exceeding the estimate if it was not possible to foresee that the estimate would be exceeded. In that case, the contractor must notify the client of the substantial overrun of the estimate without delay. If the contractor fails to notify, the contractor may claim the amount exceeding the estimate only to the extent that the client has been unjustly enriched."
subs. 3 "If the client terminates the contract because the estimate is exceeded, the client need not pay the fee exceeding the estimate."

Three conditions for the contractor's extra payment

The contractor may claim contractual extra payment for an overrun of a non-binding estimate only if all three conditions are met. If only the prompt notice is missing, a claim limited to unjust enrichment remains (see below). Each condition is a separate checkpoint for the client.

Condition What the law says What the client checks
The overrun is substantial § 639(2), first sentence; the law gives no percentage how large the overrun is compared with the estimate and whether it is justified
The overrun could not be foreseen § 639(2), first sentence what caused the overrun and whether it was known or knowable when the contract was concluded
The contractor gave notice without delay § 639(2), second sentence when the contractor learned of the overrun and when it notified the client

The law does not say when an overrun is substantial. The Law of Obligations Act gives no percentage or amount for this, and the client should not accept a "usual" threshold based on the other party's assertion without checking it. If the parties want to avoid the question, they can agree in the contract on the level of overrun from which the contractor must give notice.

Foreseeability is the most disputed of the conditions. According to the Supreme Court case-law review, the contractor may claim extra payment for an overrun of a non-binding estimate only if the overrun could not have been foreseen (Supreme Court judgment of 12.11.2014 no 3-2-1-102-14, paras 19 and 22). According to the same review, the mere fact that an overrun is large does not prove that it could not have been foreseen (Supreme Court judgment of 05.11.2008 no 3-2-1-79-08, para 13). On the contrary, a large overrun may suggest that the estimate was drawn up too optimistically from the start.

If the contractor does not give notice

The consequence of failing to give notice is written directly into the law: the contractor may claim the amount exceeding the estimate only to the extent that the client has been unjustly enriched (§ 639(2), third sentence). In that case there is no contractual extra payment.

The purpose of the duty to notify is to give the client a choice in good time. According to the Supreme Court case-law review, the client must be able to decide whether to accept the overrun or to terminate the contract. A final invoice that exceeds the estimate and arrives at the end of the works no longer gives the client a choice, because the work has already been done.

§ 639 does not set the form of the notice, so it is in the client's interest to require written notice in the contract. A useful clause provides that the overrun is notified in writing, that the notice states the cause of the overrun, the expected new cost and the effect on the deadline, and that until the client decides, no work is done whose price exceeds the estimate. The date of the notice is often decisive in a later dispute, and how to record it in the documents is described in this branch's article on construction records.

The client's choice: accept or terminate

When the notice arrives, the client has two legal routes, and the cost of each must be calculated before deciding. The first route is to accept the overrun. Consent should be given in writing and for a fixed amount or a fixed calculation method. According to the Supreme Court case-law review, a non-binding estimate is a preliminary calculation, and the parties may agree to change the price (3-2-1-79-08, para 12). Such an agreement replaces the estimate with a new price and closes the question of whether the conditions were met. Consent does not have to be unconditional: the client can accept part of the overrun or make it a condition that the new amount is binding.

The second route is to terminate the contract because of the overrun. In that case the client does not have to pay the fee exceeding the estimate (§ 639(3)). This differs from ordinary termination, which the client may carry out at any time under VÕS § 655: there, the contractor is entitled to the agreed fee, less what it saved because of the termination or what it acquired, or could have acquired, by using its workforce otherwise. How to calculate the amount payable under § 655, and when it is cheaper or more expensive, is described in the article on the client's right to terminate at any time, and what it costs.

The client's decision What the client pays Legal basis
accepts the overrun the agreed new price agreement of the parties
does not accept and disputes the conditions the estimate, if the overrun is not substantial or was foreseeable; if notice was not given, the excess only to the extent of unjust enrichment; otherwise the excess as well § 639(2)
terminates the contract because of the overrun does not have to pay the fee exceeding the estimate § 639(3)
terminates the contract for another reason the agreed fee less savings and other income § 655(1)

Termination is a decision whose cost is not measured by the contract alone. Finding a new contractor, waiting time, handing over the site and accepting the work done are costs that have to be compared with the amount of the overrun. Termination is a strong lever precisely because it exists: a contractor that knows the client is ready to terminate will justify the overrun more carefully.

What the client does when the notice arrives

The first step is to ask for the cause in writing. The client should ask the contractor to describe what caused the overrun, when it became known and why it could not have been foreseen when the contract was concluded. The answer shows whether this is an overrun of the estimate at all, or additional work, to which a different procedure applies; that distinction is explained in the branch's other article on additional work and changed work.

The second step is to check the timing of the notice. If the contractor knew about the overrun earlier and gave notice only once the work had been done, the notice was not given without delay. The construction works diary (ehitustööde päevik), the minutes of site meetings and correspondence often show when the issue was first raised.

The third step is to decide in writing and on time. Silence is dangerous, because the work continues and the client's conduct may later be interpreted as consent (VÕS § 29(5)). The decision should state clearly whether the client accepts, and for what amount, or terminates the contract, and which provision it relies on.

The fourth step is to calculate the cost of termination before deciding, not afterwards. A client that knows what ending the contract would cost can also negotiate the size of the overrun. If a contingency has been provided for separately from the contract price, using it is a separate decision; planning a contingency is covered in the article on contingency and unforeseen costs.

Fictitious example

The following example is fictitious and only illustrates the reasoning. The client of a commercial building concluded a contract with a non-binding estimate of 400,000 euros. After the foundations have been poured, the contractor gives notice that, because of a rise in the price of steel for the load-bearing structures, the expected cost is 452,000 euros, that is 52,000 euros over the estimate.

First, the client asks when the price rise became known. The correspondence shows that the contractor mentioned the price of steel at a site meeting 2 months earlier but did not give written notice. Second, the client asks whether the price rise was foreseeable when the contract was concluded: if the price rise was already public knowledge at that time, this is an argument against unforeseeability. Third, the client calculates what ending the contract and finding a new contractor would cost. On the basis of these three answers, it has grounds for negotiation: whether to accept part of the overrun in exchange for a binding new price, or to terminate the contract. Whether 52,000 euros is a substantial overrun of this estimate, the law does not say, and the example takes no position on that question.

Specific features for a contracting authority

For a contracting authority, the room for a non-binding price is limited. According to the Supreme Court case-law review, the price agreement in a public contract cannot be completely non-binding (3-2-1-102-14, paras 13, 14 and 19). For a contracting authority (hankija), the question of changing the price is therefore a question of the Public Procurement Act, covered in the public contract branch of this guide.

This article describes the state of the rules and published case law on the date of checking and is intended for professional orientation. It does not replace legal advice or a review of the specific case.

Frequently asked questions

The Law of Obligations Act does not say, and no percentage threshold can be derived from the law. If the parties want certainty, they can agree in the contract on the level of overrun from which the contractor must give written notice.

If the notice was not given without delay, under VÕS § 639(2) the contractor may claim the amount exceeding the estimate only to the extent that the client has been unjustly enriched. In that case there is no contractual extra payment.

No. According to the Supreme Court case-law review, the size of the overrun alone does not prove that it was unforeseeable (3-2-1-79-08, para 13). What matters is the cause of the overrun and whether it was foreseeable when the contract was concluded.

If the client terminates the contract because the estimate has been exceeded, under § 639(3) it does not have to pay the fee exceeding the estimate. The provision only concerns the excess, so the rest of the settlement with the contractor must be worked out before deciding.

← The construction contract and the final cost: the client's legal levers in Estonia