Additional works and changed works during the contract

📐 Topic

By , construction economist

Information verified on 8 min read

What you will learn Four situations that look like the same extra invoice on the client's desk, their different legal bases, the three decisions the client has to make on every change, and the four articles in this branch.

No construction project runs exactly to the design, and a change during the works is not in itself a sign of a bad contract or a bad client. It is not the change that raises the final cost, but the fact that it is not classified, approved or evidenced at the moment it is made. This branch covers the client's (tellija's) right to request, accept and refuse a change; how the price of a change is calculated is a topic for another guide.

Four situations, one extra invoice

An additional claim can arise from four different sources, and each has its own legal basis. The client's first step is not to check the amount but to ask which of the four situations is at issue, because that decides whether there is anything to pay at all.

Situation What happened Legal basis The client's key question
Additional work (lisatöö) work was done that falls outside the subject matter of the contract agreement of the parties; the concept comes from case law did I order this work and agree a price for it?
Changed work (muudatustöö) within the subject matter of the contract, work was done differently from what was agreed interpretation of the contract (VÕS § 29) how large is the difference between the planned and the actual execution?
Substantial overrun of a non-binding estimate the same work costs more than estimated VÕS § 639(2) was the overrun impossible to foresee, and was I notified without delay?
Price rise input prices rose during the contract the contract; by exception VÕS § 97 does the contract or the law put this risk on me?

In this branch, the word estimate (eelarve) means, in the sense of § 639 of the Law of Obligations Act (võlaõigusseadus, VÕS), the estimated cost of the work agreed in the contract for work (töövõtuleping), which is either binding or non-binding for the contractor (töövõtja). It is not the contractor's internal detailed budget discussed in the budgeting guide.

The law has no word for additional work

The Law of Obligations Act uses neither the term additional work nor the term changed work: both come from practice and case law. According to the Supreme Court (Riigikohus) case-law review "Töövõtuleping" ("Contract for work", 2022), additional works are works that fall outside the subject matter of the contract and require an agreement of the parties; without such an agreement, the contractor is not entitled to payment for them under the contract. Changed works stay within the subject matter of the contract but are carried out differently from what was agreed. Which is which is determined by interpreting the agreement of the parties.

This is why the outcome often depends on what is written in the contract and its annexes. The more precisely the contract describes what belongs to its subject matter, the easier it is later to say whether new work lies outside that subject matter or is a different way of executing it.

Protection that works by default

The Law of Obligations Act protects the client even when the contract says nothing. If the parties have not agreed that the estimate is non-binding, it is presumed to be binding (VÕS § 639(1)), and according to the Supreme Court case-law review, where the estimate is binding the contractor cannot claim payment above it (Supreme Court judgment of 19.12.2017 no 2-15-15662/55, para 12). For an overrun of a non-binding estimate, the contractor may claim extra payment only if the overrun is substantial and could not have been foreseen, and the contractor must give notice of it without delay; without notice, the excess can be claimed only to the extent that the client has been unjustly enriched (§ 639(2)).

The client often gives this protection away in its own contract. A sentence such as "the estimate is indicative" or "the price will be refined as the works proceed" reverses the presumption. Another common way of weakening the protection is to let works go ahead without a written agreement and to pay invoices without challenge, because the conduct of the parties is one of the circumstances taken into account when interpreting a contract (VÕS § 29(5)).

Three decisions on every change

For every change, the client has to make three decisions, and they must be made before the work is done. A decision taken afterwards is already a dispute.

The first decision is classification: is the work requested or claimed additional work, changed work, or part of the subject matter of the contract that has already been paid for? The second is agreement: a description of the work, the price or the method for setting it, and the effect on the deadline. The third is evidence: the agreement must be in writing and easy to find, whether in a separate change order, in the minutes of a site meeting or in the construction works diary (ehitustööde päevik).

It is worth stating in the contract who may order a change on the client's behalf. If this is not written down, an oral instruction given on site may later become evidence that additional work was ordered. A clause stating that no additional work starts before a written agreement, except work needed to remove a hazard, is also useful.

What this branch does not cover

Pricing and tracking changes belong to the budgeting guide. How to price a change using unit rates and the structure of the budget is described in the article on variations and additional works from a budgeting perspective. How to track costs throughout the works is described in the article on tracking costs during construction. This branch deals only with the right to claim, accept and refuse.

For a contracting authority (hankija), an agreement of the parties is not enough. Changes to a public contract are limited by the Public Procurement Act, which is covered in the public contract branch of this guide.

The articles in this branch

This article describes the state of the rules on the date of checking and is intended for professional orientation. It does not replace legal advice or a review of the specific case.

Frequently asked questions

According to the Supreme Court case-law review, additional work requires an agreement of the parties, and without one the contractor is not entitled to payment for it under the contract. The question is therefore whether an agreement exists, and the conduct of the parties can also prove it.

No. Changed work stays within the subject matter of the contract, and the question is the price difference between the planned and the actual execution, which may also be in the client's favour.

Yes. If the contract does not state that the estimate is non-binding, it is presumed to be binding under VÕS § 639(1).

In a dispute, the existence and content of the agreement must be proved, and consent given only orally is hard to prove. That is why an oral agreement should be entered straight away in the minutes of a site meeting or in the construction works diary.