Works direction and execution direction

📐 Article6 min read

What you will learn

Which functions the LOE assigns to the works director and the execution director, how those functions translate into the daily life of the site, which documents each figure signs and where the overlaps and frictions worth governing occur.

Blog › Project phasesConstruction phase › Works direction and execution direction

The Spanish dirección facultativa (design team's site direction) is a two-piece system, and its effectiveness depends on each piece doing exactly its job. The LOE defines the functions precisely enough to distribute liabilities, but the daily translation, who decides what, who signs what, who visits when, is craft and organisation. This article brings the legal distribution down to site level; who the usual holders of each function are is explained in the article on architect and technical architect, and the phase's complete system in the one on the construction phase.

The works director: the site as development of the design

The LOE entrusts the director de obra (works director) with directing the development of the works in their technical, aesthetic, planning and environmental aspects, in accordance with the design, the licence and the contract, with the aim of ensuring their fitness for the intended purpose. From that formula derive the core tasks: verifying the setting out and the fitness of the designed foundations and structure to the ground conditions; resolving the works' contingencies, recording in the libro de órdenes y asistencias (site order book) the instructions for the correct interpretation of the design; drafting the design modifications the progress of the works may require; and signing the setting-out minutes and the final works certificate.

The position is that of the design's guarantor: when the site asks, the works director answers for the design, and when reality forces a change, it is the works director who modifies with the author's authority. That is why the design's indefinitions end up on their desk, and why the quality of the detailed design determines how much of their time the site consumes resolving what should have been resolved on paper.

The execution director: the control of what is built

To the director de la ejecución (execution director) the law entrusts directing the material execution of the works and controlling it qualitatively and quantitatively. The core tasks: verifying the on-site reception of construction products, ordering tests and trials; directing material execution by checking setting-out, materials and the correct execution and arrangement of the construction elements and services; recording in the order book the instructions proper to this function; and signing, together with the works director, the setting-out minutes and the final certificate, besides preparing and signing the interim certifications and the final settlement of the executed units.

The position is that of the independent verifier: nothing enters the site without their reception, nothing is covered without their check and nothing is paid without their valuation. The two systems operating under their baton, quality control with its programme and testing and cost tracking with its certifications, have their own articles developing their mechanics.

The signature map

Document Works director Execution director
Setting-out minutes Signs Signs
Site order book Design instructions Execution instructions
Design modifications Drafts and signs Applies in control
Product reception and testing Is informed Orders and verifies
Interim certifications Is informed Prepares and signs
Final works certificate Signs Signs

The map teaches the system's grammar: the design's documents carry the signature of the one who governs it, the control's documents that of the one who verifies, and the acts closing phases, setting out and completion, carry both because they attest both things at once. That distribution of signatures is what sustains the cross-control.

Typical frictions and their governance

Three overlaps concentrate the system's real friction. Modifications: the execution director detects on site what does not fit, but the design solution belongs to the works director; without a fast circuit between the two, the gap is filled by the contractor with accomplished facts. The rejection of units: the execution director's authority not to accept what is badly executed needs the backing of the whole site direction against schedule pressure. And informal instructions: works directed by calls and messages manufacture diffuse liabilities; the discipline of the order book, written instructions, dated and signed by their author, is the cheap vaccine.

For the developer, the practical reading is organisational: agree each direction's commitment and visits, demand the documentary circuit from day one and never bypass the execution director in the negotiation of certifications. All three decisions are taken when contracting rather than during the works.

Frequent errors

The first is treating the two directions as redundancy and cutting one: the system loses exactly the cross-control that justifies it. Both functions are legally distinct and do not combine in one person.

The second is letting modifications accumulate unformalised, with the works advancing on verbal decisions nobody signed. Each decision is recorded in the order book on the day it is taken.

The third is the certification negotiated apart from the execution director, turning independent economic control into scenery. Certification is based on the real measurement of what was executed.

The fourth is the empty order book: months of works without written instructions describe a direction that did not direct or will not be able to prove it did. The book is kept current like any other site document.

Note: the functions cited are those of articles 12 and 13 of the consolidated LOE; their concrete distribution may be nuanced in singular works and in projects with partial designers.

Frequently asked questions

Because the system separates whoever directs the design from whoever verifies what is built. That cross control is what justifies the duplication.

The works director those of the design and its modifications; the execution director those of control and the certificates; setting out and completion carry both signatures.

No. Both functions are legally distinct and do not combine; cutting one removes exactly the control the system seeks.

The direction will not be able to prove it directed. Months of works without written instructions later read as months without direction.