Why cost is decided before prices
The cost of a building is settled long before tenders are invited. When the construction design (proyecto de ejecución, the detailed design issued for tender and construction) reaches the contractors, the shape, the number of storeys, the basement, the grid and the facade system are already fixed, and competition only acts on the unit rates of quantities that nobody is going to change. The decisions that move the budget are taken at the feasibility and preliminary design stages, as the article on feasibility studies and preliminary design explains.
Reducing construction costs is therefore not a matter of lowering specifications at the end. It means choosing, while a change still costs a calculation rather than a redesign, the solutions that deliver the same brief with less construction work. This guide does not deal with the figure set by the developer, which is explained in setting the budget before design starts, but with the design decisions that determine whether that figure is met or not.
The example project: 30 homes in PB+4 over one basement level
Every page of this guide works on the same building, with the same areas and the same starting budget. Prices are expressed as material execution budget (presupuesto de ejecución material, or PEM, the construction cost before contractor overheads, profit and VAT), using the 2026 ranges of this blog's guide to construction cost per m², which sets the conventions: above-ground floors and basement are budgeted separately.
| Item | Value in the example |
|---|---|
| Brief | 30 homes, 6 per floor, two stair and lift cores |
| Massing | Linear block of 45 m by 12 m, ground floor plus four, 3.00 m floor to floor |
| Gross floor area above ground | 5 floors of 540 m², that is 2,700 m² |
| Facade | Perimeter of 114 m by 15 m in height, about 1,710 m², of which about 430 m² of openings and 1,280 m² opaque |
| Basement | 55 m by 17 m, 935 m², 30 spaces in two rows on either side of a central aisle, with the ramp inside; 395 m² lie outside the footprint of the block |
| PEM above ground | 2,700 m² at 1,100 €/m², about 2,970,000 € |
| PEM of the basement | 935 m² at 550 €/m², about 514,000 € |
| Total PEM | about 3,485,000 €, that is about 116,000 € per home |
The 1,100 €/m² sits in the middle of the range of 900 to 1,300 €/m² that the blog's guide gives for a multi-family building above ground, with mid-range specifications in an average-cost area. The 550 €/m² for the basement is within the range of 450 to 700 €/m² per level that the blog gives for below-ground car parks, in normal ground conditions and with no water table. The example is fictitious and the amounts are indicative: they serve to compare decisions, not to budget a real project.
The method: one assumption at a time
Each page changes a single assumption and leaves all the others as in the example. If the facade is lengthened, the brief, the basement and the specifications do not move; if the basement is reduced, the facade stays the same. This method has a price, because real decisions interact, but it allows each effect to be read separately and shows where a difference comes from.
The second rule is to compare within the same scope. All the figures in this guide are PEM, excluding general overheads, contractor's profit, fees, permits and VAT, which are dealt with in the step from PEM to total cost. A saving expressed in PEM grows when it is carried through to the contract price and the total cost, but the order of the decisions does not change.
The six decisions on the example project
Compactness and the number of storeys
A facade is paid for by the square metre of facade, not by the square metre of housing. With the same gross floor area, reducing the depth of the block from 12 to 10 m lengthens it to 54 m and adds about 210 m² of facade; six setbacks of 1.50 m add about 270 m². The number of storeys also crosses thresholds of the CTE (Código Técnico de la Edificación, the Spanish building code), such as the fire resistance required of the structure, which rises from R 60 to R 90 when the evacuation height exceeds 15 m (DB SI 6, table 3.1). The page on building compactness develops these variants.
The basement and parking
The basement in the example costs about 514,000 € of PEM, about 17,100 € per space. The average figure hides a difference: a block 12 m deep cannot take two rows of spaces with their aisle, so the basement has to extend beyond the footprint of the building, and those 395 m² outside carry a roof slab that serves only the car park. Limiting it to the length of the block reduces the basement to 765 m² and 22 spaces, about 93,500 € less PEM before paying for the eight spaces that move to the surface. The detail is in the cost of a basement parking space.
The grid and the structure
According to the blog's guide, the structure accounts for 15 to 22 % of the PEM of a multi-family building, that is between 520,000 and 765,000 € on the example. Within that range, the position is decided by the consistency between the car park grid and that of the homes, transfer structures, spans and cantilevers. The page on the grid and the structure explains why the car park usually imposes its grid on the residential floors.
Foundations and the geotechnical survey
Earthworks and foundations account for 5 to 12 % of the PEM according to the blog, between 175,000 and 420,000 € on the example: it is the chapter with the greatest variance, and the ground decides the position in the range. The geotechnical survey, required by the CTE to design the foundations (DB SE C, section 3), is what makes it possible to move from that bracket to a figure. The page on the geotechnical survey and foundations shows when to commission it and what site investigation the CTE requires for a building like the one in the example.
The facade
Facades and roofs account for 12 to 18 % of the PEM, between 420,000 and 625,000 € on the example. The facade system (facing brick, SATE, the Spanish term for external thermal insulation composite systems, ventilated facade, curtain wall) and the proportion of openings decide the position. The page on facade cost per m² compares the systems and what each one demands of the rest of the building.
Life cycle cost
Some construction savings are paid for later, in energy, maintenance and replacement, and they are not always paid by whoever builds. The page on false savings distinguishes what lowers the cost for the developer who sells from what lowers it for the owner who keeps the building.
Summary: what each decision moves
| Decision | Variant compared | Effect on the example |
|---|---|---|
| Compactness | Block 10 m deep instead of 12 m | About 210 m² more facade |
| Compactness | Six setbacks of 1.50 m | About 270 m² more facade |
| Basement | Basement limited to the length of the block, 22 spaces | About 93,500 € less PEM, plus the cost of 8 surface spaces |
| Basement | All spaces at surface level, if planning rules and the plot allow it | The 514,000 € of the basement, in exchange for about 750 m² of plot |
| Structure | Car park grid consistent with that of the homes | Position in the range of 520,000 to 765,000 € |
| Foundations | Favourable or unfavourable ground | Position in the range of 175,000 to 420,000 € |
| Facade | System and proportion of openings | Position in the range of 420,000 to 625,000 €, with the roof |
| Life cycle | Replacements and energy | Outside the PEM, borne by the owner |
The last three rows give a range rather than a saving: the blog's percentages are orders of magnitude per chapter, and the position within each range depends on the project. The first two decisions, on the other hand, can be measured from the feasibility study, because they change quantities.
The order of decisions and the thresholds worth knowing before drawing
The order matters because each decision conditions the next. The number of spaces and the shape of the basement are set with the planning rules, before the massing; the car park grid conditions that of the upper floors; the foundations depend on the ground and on the basement level; the facade comes afterwards, on a massing already fixed.
| Stage | Decision | Threshold or rule worth checking |
|---|---|---|
| Feasibility study | Parking spaces | Provision required by the municipal planning rules, which vary from one municipality to another |
| Feasibility study | Number of storeys | Evacuation height of 15 m for the fire resistance of the structure (DB SI 6) |
| Feasibility study | Site investigation | Geotechnical survey at the initial stage of the project (DB SE C, 3.1) |
| Preliminary design | Grid | Consistency between spaces, circulation aisle and the walls of the homes |
| Preliminary design | Facade | Requirements of DB HE 1 and DB HS 1 for the chosen system |
The parking provision deserves a warning. There is no national rule: it is set by the planning rules of each municipality, sometimes as minimums per home and sometimes per built area. The example assumes one space per home, but the first check in a feasibility study is to read the rule that applies to the plot.
When it is too late for these decisions
If the design has already been drawn up and its estimate exceeds the developer's budget, the levers are different: reducing the brief, changing technical solutions with their redesign cost, phasing or accepting a financed increase. They are covered in the design estimate exceeds the developer's budget and, once the way out has been chosen, in the decision note when the design exceeds the budget.
If it is the tenders that come in above budget, the situation changes again, because the design can no longer move without losing the tender. The article on tenders above budget sets out the options in private construction. In both cases, the decisions in this guide remain useful, but they cost design hours and time rather than a calculation.
In summary
The cost of an apartment building is set mainly by six decisions taken before measuring: compactness, the basement, the grid, the foundations, the facade and the life cycle. On the example of 30 homes, the first two change quantities that can be measured from the feasibility study, and the next four decide the position within ranges of several hundred thousand euros. Taking them in order, one assumption at a time and within the same budget scope, is what shows which decision saves money and which merely shifts the cost.
Nature of the values cited
Regulatory thresholds are cited with their document and section. Areas, perimeters and the number of spaces come from the example project, calculated on fictitious assumptions, and prices are given as examples: they do not replace consulting contractors or an estimate based on measured quantities.
Sources: Prices given as examples, established in November 2026 from public references: 2026 ranges from this blog's guide to construction cost per m² and from its page on the multi-family residential building · Código Técnico de la Edificación, DB SE C (Foundations), section 3, and DB SI, section SI 6, table 3.1, in the version published on codigotecnico.org.