The example basement: 30 spaces in 935 m²
The example project in the guide to reducing construction costs has 30 flats at PB+4 (planta baja, ground floor, plus four upper floors) on a block of 45 m by 12 m, and one space per flat, a provision assumed for the example. Geometry comes before price. Two rows of perpendicular spaces, 5.00 m deep, on either side of a 5.00 m aisle, need around 15 m of clear width, and around 17 m with walls and columns. A block 12 m deep does not have that: only one row with its aisle fits under its footprint.
The example basement therefore measures 55 m by 17 m, 935 m², and extends 395 m² beyond the footprint of the block. With spaces 2.45 m wide, the row that takes the internal ramp loses around 23 m of length and holds 13 spaces; the other loses around 10 m to the two stair and lift cores and holds 18. That leaves 31 positions, 30 spaces and a plant room, or around 31 m² per space, ramp and aisles included. The minimum dimensions of spaces and aisles are set by the municipal ordenanza (local building by-law), which is what gets checked before this calculation is closed.
With the 550 €/m² of PEM (presupuesto de ejecución material, the net construction cost) per level that the example takes from the range of 450 to 700 €/m² given by the blog for below-ground parking, the basement costs around €514,000, around €17,100 per space. The guide to construction cost per m² insists on budgeting it separately: diluted into the residential ratio, it disappears from the comparison.
What one basement level sets off
The basement is paid for through the works it brings with it, most of which do not appear in a price per space. The table lists them for the example:
| Work | What triggers it | In the example |
|---|---|---|
| Excavation and removal of spoil | Volume excavated, type of ground, distance to the licensed tip | Around 3,300 m³ for an excavation depth of around 3.50 m |
| Retaining structures | Party walls, public road or nearby buildings that prevent excavating to a slope | Perimeter wall of around 144 m; diaphragm wall if there are party walls |
| Raft or ground slab and walls | Earth pressure, presence of water | 935 m² of ground slab or raft |
| Roof slab outside the footprint | Part of the basement under the courtyard | 395 m² of slab carrying the waterproofing, drainage and finishes of the courtyard |
| Ramp and waiting area | Level difference and permitted gradient | Internal ramp of around 20 m plus the waiting area |
| Ventilation and fire protection | DB HS 3 and DB SI | Own fire compartment and car park ventilation |
| Groundwater | Level of the water table relative to the excavation depth | No water in the reference assumption |
The ramp waiting area is a requirement of DB SUA 7 (the section of the CTE safety in use document on vehicle areas): car park areas must have, where they meet the outside, an access and waiting space at least 4.5 m deep with a gradient of no more than 5 %. That almost flat stretch lengthens the ramp, which is why it weighs on the number of spaces that fit in the row receiving it.
Car park ventilation is covered in the page on ventilation and indoor air quality, DB HS 3. The presence of water changes the order of magnitude of the basement and depends on the geotechnical survey, covered in the page on foundations and the geotechnical survey.
Fire resistance of a car park under flats
A car park located beneath a different use requires its structure to have a fire resistance of R 120 (DB SI 6, the fire safety document, section 6, table 3.1), against R 60 on the residential floors of the example. The roof slab and the columns of the car park are designed for that requirement, which shows in cover and section sizes. The car park also forms its own fire compartment, with the conditions of communication with the cores set by DB SI 1.
The grid imposed on the flats
The car park imposes its grid: spaces on either side of an aisle and columns falling between spaces. The walls or columns of the flats must come down onto that grid or be transferred at the basement roof. That cost does not appear in the car park chapter, but it stems from the basement, and it is covered in the structural grid and frame.
Three ways of providing the 30 spaces
The table compares three solutions on the example, all else being equal. The solutions with surface spaces assume that the plot and the planning rules allow it:
| Solution | Basement spaces | Surface spaces | Basement | PEM difference |
|---|---|---|---|---|
| A. Reference | 30 | 0 | 935 m², of which 395 m² outside the footprint | reference |
| B. Basement limited to the length of the block | 22 | 8 | 45 m by 17 m, 765 m² | around €93,500 less, before the cost of the 8 surface spaces |
| C. All at surface level | 0 | 30 | none | around €514,000 less, before the cost of the 30 surface spaces |
In solution B, the row with the ramp keeps around 22 m of usable length and 8 spaces, and the other around 35 m and 14 spaces. The saving is calculated with the average price of 550 €/m², and is therefore a minimum: the 170 m² removed lie outside the footprint, where the roof slab serves only the car park and also carries the courtyard finishes. Their marginal cost exceeds the average.
Solution C removes the basement but takes up around 750 m² of the plot for 30 outdoor spaces of around 25 m² each, manoeuvring included. That land is no longer available for communal areas, garden or buildable floor area, and its value is judged in the development appraisal as much as in the PEM. On an urban plot between party walls, it simply does not exist.
Reducing the provision before building it
The cheapest space is the one that does not have to be built. In Spain there is no national rule on the number of spaces: it is set by each municipality's planning rules, with minimums per dwelling or per floor area, and with their own exceptions, which may take into account proximity to public transport or the impossibility of building them on the plot. The check is made at feasibility stage, because the basement is drawn from the number of spaces retained.
The provision is also read against the market. If the spaces are sold separately, the developer compares the €17,100 of PEM per space, plus its share of overheads, contractor's profit, fees and taxes, with the price at which they can be sold in the area. If they are included in the price of the flat, the comparison is made on the cost per dwelling, as explained in the construction cost of a multi-family residential building.
The cost per space, related to the dwelling
On the example, the basement represents around €17,100 of PEM per flat, against around €99,000 of above-ground PEM per flat (€2,970,000 divided by 30). It is the least reversible decision in the project: it is fixed with the number of spaces before the planning permission and almost nothing is recovered once the excavation is let. That is why the guide places it at the start of the order of decisions, before the massing and the grid.
In summary
A basement space costs what it sets off: excavation, retaining structures, water, a ramp with its waiting area, R 120 in the car park structure and a grid imposed on the flats. Geometry decides before price: a block 12 m deep does not allow two rows of spaces, and the example basement extends 395 m² beyond the footprint. Limiting it to the length of the block saves at least around €93,500 of PEM, and the provision of spaces, set by the municipal planning rules, is discussed before drawing.
Nature of the values cited
The CTE requirements are cited with their basic document. Areas, volumes and numbers of spaces come from the example project, calculated on fictitious assumptions, and prices are given as examples: they do not replace consulting contractors or a measured estimate.
Sources: Prices given as examples, established in November 2026 from public references: 2026 ranges from this blog's guide to construction cost per m² and from its page on the multi-family residential building · Código Técnico de la Edificación, DB SUA, section SUA 7; DB SI, sections SI 1 and SI 6, table 3.1; DB HS, section HS 3.