False savings: what makes construction cheaper and operation more expensive

📐 Topic

By , construction economist

7 min read

What this article covers Some construction savings are paid for later, in energy, maintenance and replacement, and they are not always paid by whoever builds. This article explains what life cycle cost is, who pays each part in a residential development, which false savings appear most often and how to present the choice to the developer before it is made. The example is a 30-flat apartment building on ground floor plus four storeys (PB+4).

Life cycle cost, what the PEM does not show

The presupuesto de ejecución material (PEM, the bare construction cost) measures what it costs to build. Life cycle cost adds what it costs to use the building over its life: energy, maintenance, repairs, replacement of the elements that wear out before the structure and, finally, end of life. Ley 9/2017, de Contratos del Sector Público (the Public Sector Contracts Act, LCSP) defines it in article 148 for public procurement, works included, where it can serve as the basis for the award (article 145.1): it covers the costs of acquisition, use, maintenance and end of life, and may include costs attributed to environmental externalities.

In private construction no rule requires it to be calculated, but the reasoning is the same. A solution that is cheaper to build is only a saving if its cost of use does not cancel out the difference over the period that matters to the decision-maker. For a developer who sells, that period is short; for an owner who holds, it is the life of the building.

Who pays what

The Ley de Ordenación de la Edificación (LOE, the Building Act) allocates the roles. The developer decides, schedules and finances the works (art. 9.1), and the owners are obliged to keep the building in good condition through proper use and maintenance (art. 16). Between the two, the parties involved in the construction, jointly with the developer, are liable for physical damage during set periods: ten years for damage affecting the structure, three years for damage affecting habitability, and one year for the contractor in respect of finishing defects (art. 17). In buildings whose main use is housing, the ten-year guarantee against structural damage is compulsory, in the form of material damage insurance (the seguro decenal), surety insurance or a financial guarantee (art. 19.1.c and second additional provision).

Who What they pay Horizon
Developer who sells PEM, development cost, guarantees during the LOE periods Until sale and the liability periods
Owners' association Maintenance of common elements, replacements, energy for common areas The whole life of the building
Owner of each flat Energy and maintenance of their flat The whole life of the building
Developer who holds and lets All of the above The whole life of the building

This allocation explains why false savings are common in build-to-sell developments. What the developer saves during construction is paid later by the owners' association, outside the guarantee periods, and nobody compares the two figures at the moment of decision.

The building logbook and the maintenance plan

The LOE requires that, once the works are complete, the project with the approved changes is handed over to the users in the libro del edificio (building logbook), which includes the instructions for use and maintenance of the building and its services (art. 7). The logbook is where life cycle cost becomes visible to the owners' association: each system chosen arrives with its maintenance. The content and management of the logbook are covered on the page about the building logbook.

That document is drawn up at the end of the works, when the choices have already been made. The useful thing is to anticipate it: to ask, at preliminary design stage, what maintenance each proposed system will require and how often it will be replaced.

The most common false savings

On an apartment building like the one in the example, false savings are concentrated in a few chapters. They all lower the PEM and shift the cost to the owners' association:

  • Envelope at the regulatory minimum. Thinner insulation complies with DB HE 1 and lowers the PEM, but it fixes the energy demand of the 30 flats for decades. The chapter is one of the heaviest, between about €420,000 and €625,000 for facades and roofs according to the blog's guide, and even so the insulation share is small compared with the backing leaf and the cladding.
  • Facade finishes that need frequent maintenance. A system whose finish needs periodic repainting or repair costs less to build and more for the owners' association. This is covered in facade cost per m².
  • Waterproofing of roofs and the basement. Lower-quality waterproofing on the roof or on the car park walls saves little during construction and is repaired with the building occupied. The basement is covered in the cost of a basement parking space.
  • Common services without access. Risers, downpipes and equipment without accessible inspection points cost no more to build, but they multiply the cost of every repair.

None of these savings shows up in the ratio per square metre, and all of them appear in the owners' association fees. The blog does not publish maintenance or replacement prices for these systems, so this article does not put figures on them: the comparison is made with the prices of the specific project.

Presenting the choice before deciding

A false saving is avoided by showing both figures at the same time. The presentation that works has three parts: the difference in PEM between the two solutions, the cost of use of each over a stated period (energy, maintenance and foreseeable replacements), and who pays each part according to the allocation above. With those three pieces of information, the developer decides with full knowledge, and the decision is put in writing, as proposed in the article on the decision note.

The period is chosen according to who decides. A developer who sells looks at the LOE liability periods; a developer who holds, or a public body, looks at the life of the building. In public works, article 145.1 of the LCSP allows, where justified in the contract file, an award on the basis of life cycle cost calculated in accordance with article 148, whose method must be set out in the tender documents.

In summary

Life cycle cost adds to the PEM what it costs to use the building: energy, maintenance, replacement and end of life, as defined in article 148 of the LCSP. The LOE divides the payment between the developer, during the liability periods, and the owners, who are obliged to keep the building in good condition. False savings are concentrated in the envelope, the finishes, the waterproofing and services without access, and they are avoided by presenting the construction difference and the difference in use at the same time.

Nature of the values cited

Rules are cited with their act and article. The quantities come from the example project, calculated on fictitious assumptions, and the amounts are orders of magnitude per chapter taken from this blog's guide, given as examples.

Sources: Prices given as examples, established in November 2026 from public references: chapter weightings from this blog's guide to construction cost per m², 2026 · BOE, Ley 38/1999, de Ordenación de la Edificación, art. 7, 9, 16, 17 and 19 and second additional provision (consolidated text) · BOE, Ley 9/2017, de Contratos del Sector Público, art. 145 and 148 (consolidated text).

Frequently asked questions

The sum of the costs of acquisition or construction, use, maintenance and end of life, to which the costs of environmental externalities may be added. This is the definition given by Ley 9/2017 in article 148 for public procurement.

Yes, at least during the LOE liability periods (ten years for the structure, three for habitability, one for finishes), and because a building with predictable maintenance sells better. Beyond that, the cost falls on the owners' association.

Yes. Article 145.1 of the LCSP allows the contracting authority, where justified in the contract file, to award on the basis of life cycle cost, calculated in accordance with article 148, which requires the calculation method and the data bidders must supply to be set out in the tender documents.