What is unknown without a geotechnical survey
Before the ground investigation, the foundation budget is a gamble. The guide to construction cost per m² gives earthworks and foundations a weighting of 5 to 12 % of the PEM (presupuesto de ejecución material, the construction cost before overheads, profit and VAT) of a multifamily building, and warns that unfavourable ground can double that weighting without the rest of the building changing. On the PEM of about €3,485,000 of the example in the guide to reducing construction costs, that means between about €175,000 and €420,000.
Three unknowns explain that range. The first is the bearing capacity of the ground at basement level, which decides between shallow and deep foundations. The second is water: a water table above the bottom of the excavation changes the excavation, the retaining structures and the slab. The third is what lies in the ground, made ground, remains of earlier buildings or soils with special behaviour, which the DB SE C requires to be investigated from the outset.
What the CTE requires
The DB SE C (Foundations) defines the geotechnical survey as the quantified information on the characteristics of the ground needed to analyse and size the foundations (section 3.1). It also sets its timing: since its conclusions may affect the structural concept and the type and level of the foundations, it must be carried out at the initial stage of the project and, in any case, before the structure is fully sized. It is the responsibility of the designer, another competent technician or, where applicable, the site director.
The minimum investigation depends on the type of construction and the ground group. Basements are included in the storey count, so the example, with five storeys above ground and one below, is a C-2 building, a construction of between 4 and 10 storeys (table 3.1). Unless justified, the investigation cannot be less than that set out in the document.
| DB SE C requirement for a C-2 building | Favourable ground (T-1) | Intermediate ground (T-2) |
|---|---|---|
| Minimum number of investigation points | 3 | 3 |
| Maximum distance between points | 30 m | 25 m |
| Indicative depth below final excavation level | 12 m | 25 m |
| Minimum number of boreholes | 2 | 3 |
Along the 55 m length of the example basement, three points are enough on favourable ground, about 27.5 m apart. On intermediate ground, the maximum distance of 25 m requires a fourth point. Unfavourable ground (T-3), including expansive, collapsible and soft soils, made ground deeper than 3 m or ground sloping more than 15°, has no minimum in the table: the investigation is decided case by case.
Three types of ground for the same building
The table compares three ground assumptions on the example, all else being equal. It gives no amount per row, because the blog's percentages are a range for the whole chapter, not a price per solution:
| Ground | Likely foundations | What changes in the basement | Position in the range of €175,000 to €420,000 |
|---|---|---|---|
| Favourable, no water | Pad footings or raft at basement level | Ordinary excavation and walls | Lower part |
| Intermediate, made ground less than 3 m deep | Deeper foundations or improved bearing | More excavation, denser investigation | Middle part |
| Unfavourable or with a high water table | Piles or raft, watertight retaining structures | Dewatering during works, basement waterproofing | Upper part, or above the range |
Water is the assumption that changes the basement most. Beyond the foundations, it requires retaining and dewatering during excavation and designing walls and slab against water pressure and ingress, which also affects the car park chapter covered in the cost of a basement car park space. The blog says so in its page on the multifamily building: the basement figure rises with a high water table or when party walls have to be retained.
When to commission the survey
The DB SE C requires the survey at the initial stage of the project, but the developer has an interest in bringing it forward even further. The purchase of the land, the decision to build a basement and the number of car park levels depend on the ground, and are made in the feasibility study. The guide to preliminary studies and the anteproyecto counts the geotechnical survey, or at least provision for it, among the physical checks of that stage.
If the developer does not yet own the land, the information available is what the DB SE C requires to be gathered in every case: surveys of neighbouring plots, information on groundwater, the history of use of the site and the foundations of adjoining buildings. It does not replace the investigation, but it places the plot in a probable ground group and indicates which part of the range to budget in.
Holding the budget while there is no survey
While there is no survey, the foundations are budgeted with a written assumption and a visible reserve. The method is simple: take the position in the range that corresponds to the probable ground group, write down the assumption (ground, water, level) and set aside the difference up to the upper part on a separate line. When the survey arrives, the reserve is released or used up, and the decision is documented. The contingency reserve by stage is covered in the contingency reserve at each design stage.
What should be avoided is budgeting the foundations in the lower part of the range without a survey. The basement, the structure and the foundation level are drawn together, and ground worse than assumed does not only make the foundations more expensive: it may force the basement and the structural grid to be redesigned.
In summary
On the 30-flat example, earthworks and foundations range between about €175,000 and €420,000 of PEM according to the blog, and the ground decides the position. The DB SE C requires the geotechnical survey at the initial stage of the project, with at least three investigation points and two or three boreholes for a C-2 building like the example. Commissioning it before deciding on the basement, and budgeting with a visible reserve in the meantime, is what avoids discovering the ground on site.
Nature of the values cited
DB SE C requirements are cited with their section and table. Dimensions come from the example project, calculated on fictitious assumptions, and amounts are orders of magnitude per chapter taken from this blog's guide, given as examples.
Sources: Prices given as examples, established in November 2026 from public references: chapter weightings from this blog's guide to construction cost per m², 2026 · Código Técnico de la Edificación, DB SE C (Foundations), section 3.1 and tables 3.1 to 3.4, version including the amendments of Royal Decree 732/2019, at codigotecnico.org.