Structural grid and frame: the decisions that set the cost of the structure

📐 Topic

By , construction economist

7 min read

What this article covers The structure accounts for between 15 and 22 % of the presupuesto de ejecución material (PEM, the construction cost before overheads, profit and VAT) of a multifamily building, according to the blog's guide, and where it sits within that range is decided by a few choices made at anteproyecto (preliminary design) stage. This article goes through them on a building of 30 flats in PB+4 (ground floor plus four storeys): the consistency between the car park grid and the grid of the flats, transfer structures, floor slab spans and cantilevers. It does not give a price per square metre of structure, which depends on the project, but explains what moves it.

What the structure weighs in the example

The example in the guide to reducing construction costs has a total PEM of about €3,485,000, basement included. Using the chapter weightings from the guide to construction cost per m², the structure represents between about €520,000 and €765,000. The width of that range, about €245,000, is what is at stake in the decisions on this page.

The structure of an apartment building in Spain is almost always reinforced concrete, with columns and floor slabs, and its design is governed by the Código Estructural (Structural Code), approved by Royal Decree 470/2021, together with the structural safety basic documents of the CTE (Código Técnico de la Edificación, the Spanish building code). The required fire resistance, R 60 on the residential floors of the example and R 120 in the car park below them (DB SI 6, the fire safety basic document, table 3.1), governs concrete cover and section sizes; it is covered in the page on structural fire resistance.

The car park grid rules

The car park has the most demanding grid in the building. Spaces 2.45 m wide give modules of two or three spaces between columns, that is about 4.90 or 7.35 m, and the central 5.00 m aisle cannot take columns. The flats, on the other hand, are organised around bays, partitions and cores that have no reason to match that module. When the columns of the flats do not land on those of the car park, they have to be carried on transfer structures at the basement roof.

In the example, the 12 m block sits on a basement 17 m wide with two rows of spaces and an aisle. If one facade of the block lands on the basement perimeter wall and the other, 12 m further on, on the line of columns along the opposite edge of the aisle, the grid is continuous and the basement roof is an ordinary slab meeting the car park requirements. If a facade lands in the middle of a row of spaces, every column on that facade has to be transferred, and the transfer slab becomes a structure of a different order.

Situation What happens at the basement roof Effect on cost
Continuous grid from car park to roof Ordinary slab, continuous columns Low position in the range
Flat columns offset from car park columns Transfer beams or a strengthened slab under each offset column More concrete, more steel, more formwork and time
Facade over parking spaces, no alignment Systematic transfer of the whole facade line High position, sometimes above the range

The decision is made at preliminary design stage, when the car park and the typical floor are drawn together. Adjusting the depth of the block or the width of the spaces so that the lines coincide costs a drawing; correcting a transfer structure in the proyecto de ejecución (detailed design) costs a structure.

Floor slab spans

The span between columns determines the slab depth and the quantity of reinforcement. Moderate, regular spans allow slabs of ordinary depth repeated on every floor; a larger span in a single area, to free up a ground floor commercial unit or a column-free car park aisle, means increasing the depth or strengthening that area, and breaks the repetition.

Repetition is a saving in its own right. An identical slab on all five floors allows formwork to be reused and reinforcement to be repeated, with output rates that rise from one floor to the next. Every exception, an offset opening, a floor with a different layout or a change in slab depth, takes away part of that saving.

Walls or columns in the flats

In Spain the usual solution for multifamily housing is a frame of columns and slabs, with independent partitions. Alternatives with loadbearing walls or concrete walls follow a different logic: the wall acts as both structure and separation, but it fixes the layout and almost always requires transfer structures where it reaches the car park, whose grid does not accept continuous walls. In a building with a basement car park, the column frame is the one that best fits the car park grid.

Cantilevers

A cantilevered balcony or terrace extends the slab beyond the line of columns. Its cost is not only that of the cantilever itself: it increases the moments in the adjacent span, requires the thermal bridge at the junction with the facade and its waterproofing to be dealt with, and adds facade if it is enclosed. Terraces supported on their own structure or balconies set within the volume avoid part of those effects, in exchange for others.

The choice is made by looking at the structure, the facade and the thermal envelope together. The last two are covered in building compactness and in the cost of the facade per m².

What to settle before the basic design (*proyecto básico*)

Four checks place the structure in the lower part of its range. All of them are carried out on the preliminary design, with the car park and the typical floor drawn together:

  • Aligned lines. The column lines of the typical floor land on those of the car park, with the central aisle kept clear.
  • Regular spans. One ordinary span repeated, with no exceptional area imposing a deeper slab.
  • Repeated typical floor. All five floors with the same structure, with no one-off floors.
  • Cantilevers decided. Their number and system fixed together with the facade, not added later.

None of these checks has a price of its own in the published ratios. Their effect shows in the position within the chapter's range, and it is confirmed by the structural engineer's preliminary sizing from preliminary design stage onwards.

In summary

In the example, the structure weighs between about €520,000 and €765,000 of PEM according to the blog's guide, and the grid decides the position. Consistency between the car park and the flats is the main decision: a block whose column lines land on those of the car park avoids the transfer structures at the basement roof. Regular spans, repeated floors and cantilevers decided together with the facade complete the list.

Nature of the values cited

Regulatory requirements are cited with their wording. Dimensions come from the example project, calculated on fictitious assumptions, and amounts are orders of magnitude per chapter taken from this blog's guide, given as examples.

Sources: Prices given as examples, established in November 2026 from public references: chapter weightings from this blog's guide to construction cost per m², 2026 · Royal Decree 470/2021, approving the Código Estructural · Código Técnico de la Edificación, DB SI, section SI 6, table 3.1.

Frequently asked questions

Between 15 and 22 % of the PEM of a standard multifamily building, according to the blog's guide. On the 30-flat example, between about €520,000 and €765,000.

Because it imposes a grid of spaces and aisles that does not naturally match the grid of the flats. Every column that does not land on the car park grid has to be transferred at the basement roof, with a transfer slab or beam.

The Código Estructural , approved by Royal Decree 470/2021, together with the structural safety basic documents of the CTE. Fire resistance is governed by DB SI 6.