A facade is paid for by the square metre of facade
The ratio per m² of built area hides a quantity that the design fixes early: the square metres of facade needed to enclose that area. Two buildings with the same area and the same specification do not have the same facade if one is deeper, taller or more broken up than the other. The blog's guide sums it up in one sentence: compactness is the most reliable early indicator of the final ratio, as the page on the construction cost of a multi-family residential building explains.
The example in the guide to reducing construction costs is a linear block of 45 m by 12 m, ground floor plus four (PB+4, planta baja plus four upper floors), with 3.00 m between floors and 2,700 m² built above ground. Its perimeter is 114 m and its facade around 1,710 m², of which around 430 m² are openings. The roof covers 540 m². According to the blog's guide, facades and roofs account for between 12 and 18 % of the PEM (presupuesto de ejecución material, the net construction cost) of an apartment building, between €420,000 and €625,000 on a total PEM of around €3,485,000.
Compactness also has an energy meaning, which DB HE 1 (the basic document of the CTE on energy saving, section 1) uses to set the limit value of the overall transmittance of the envelope. That aspect is covered in the pages on DB HE energy saving and on HE 0 and HE 1. Here we look only at the quantity of work.
Variant 1: plan depth
With the same area per floor, 540 m², the depth of the block sets its length and, with it, its perimeter. The table compares three depths:
| Depth | Length | Perimeter | Facade (15 m high) | Difference from the example |
|---|---|---|---|---|
| 10 m | 54 m | 128 m | around 1,920 m² | around 210 m² more |
| 12 m (example) | 45 m | 114 m | around 1,710 m² | reference |
| 14 m | around 38.6 m | around 105 m | around 1,580 m² | around 130 m² less |
A deeper block saves facade, but it does not come free. The dual-aspect flats of a 14 m block have rooms further from the facade, which calls for light wells or a different layout, and the car park changes shape with the block. What is gained in facade is checked on plan, flat by flat, before it is counted as a saving.
Variant 2: setbacks and projections
Six setbacks 1.50 m deep in the main facade add 18 m of perimeter, that is around 270 m² of facade over the 15 m height, without a single extra square metre of dwelling. On top of that area come the corners, the waterproofing junctions and the trims, which the ratio per m² of facade does not capture.
Enclosed projections raise another question. Besides the facade they add, they count towards the built area according to the municipal ordenanza (local building by-law), which decides how they are computed, and they change the structure at the slab edge. A setback or a projection is justified by the architecture or by the by-law; what matters is knowing, from the preliminary design, how many metres of facade each one costs.
Variant 3: number of storeys
With 2,700 m² above ground, the example could be built on fewer, larger floors or on more, smaller floors, if the planning rules allow it. The quantities move in opposite directions: fewer storeys reduce the facade per square metre but increase the roof, the foundations and the basement under a larger footprint; more storeys do the opposite.
The ratio per square metre is not linear with height. The blog's guide describes it as the height effect: beyond a certain number of storeys the ratio rises again, because structure and cores grow, lifting equipment becomes more expensive and site productivity falls. The blog gives no percentage per storey, so this article does not put a figure on the variant; the following thresholds explain where the jumps appear.
The thresholds that make one storey dearer than the others
Some storeys do not cost the same as the others because they cross a CTE threshold. On the example, two thresholds are close:
- Fire resistance of the structure. In residential dwelling use, the structure of the floors above ground must be R 60 if the evacuation height does not exceed 15 m and R 90 if it does not exceed 28 m (DB SI 6, the fire safety document, section 6, table 3.1). With 3.00 m between floors, the example at PB+4 has an evacuation height of 12 m; at PB+5 it would reach 15 m and at PB+6 18 m, which takes the whole structure to R 90. The detail is covered in the fire resistance of the structure.
- Lift. DB SUA 9 (the accessibility section of the safety in use document) requires an accessible lift or an accessible ramp in residential buildings where more than two floors must be climbed from an accessible main entrance to any dwelling, or with more than 12 dwellings on floors without an accessible main entrance. At PB+4 the lift is mandatory and its cost is spread over 30 flats; the number of cores, more than the number of storeys, is what makes that chapter vary.
The basement has its own threshold in the same document: when the car park lies beneath a different use, table 3.1 of DB SI 6 requires R 120. It is one of the reasons why the soffit slab of the car park and the columns passing through it are not budgeted like an ordinary floor.
What ratios per m² do not tell you
A ratio per m² of built area applies the same facade cost to the whole area, as if all buildings had the same compactness. On the example, going from 12 to 10 m of depth adds 12 % of facade without changing the ratio that would be used in a feasibility study. That is why, from the first massing, it pays to estimate the facade and the roof by their own area and not only by the built area.
The method is simple: perimeter times height for the facade, footprint for the roof, and a ratio per square metre of facade that is adjusted once the system is known. Facade systems and what they cost are covered in the cost of a facade per m².
In summary
On the 30-flat example, the shape of the block decides how many metres of facade are paid for: around 210 m² more with a depth of 10 m, around 270 m² more with six setbacks. The number of storeys moves the quantities in opposite directions and crosses CTE thresholds, such as the step from R 60 to R 90 above 15 m of evacuation height. All these quantities are measured at feasibility stage, before any price.
Nature of the values cited
The thresholds are cited with their basic document and their table. Areas and perimeters come from the example project, calculated on fictitious assumptions, and the amounts are given as examples.
Sources: Prices given as examples, established in November 2026 from public references: chapter weightings from this blog's guide to construction cost per m², 2026 · Código Técnico de la Edificación, DB SI, section SI 6, table 3.1; DB SUA, section SUA 9, paragraph 1.1; DB HE, section HE 1.