The tender analysis report: content, presentation and recommendations to the client

📐 Article⏱ 7 min read

Analysing the offers is not enough; the analysis has to be presented so that the client can take an informed decision, and so that the decision remains traceable if it is later contested. The analysis report is the centrepiece of the award stage. It is what turns a technical and financial comparison into a decision tool usable by a client who is not necessarily a specialist in works contracts.

Why formalise the analysis in a written report?

An analysis report is not an administrative formality, it is a protection for every party. For the client it documents the reasons for the award and lets them justify their choice if an unsuccessful candidate objects. For the design team and the economist it records the reasoning followed and demonstrates that the procedure was respected. For the successful candidates it is a reference on the basis on which they were selected.

On public projects the report must be kept for as long as the contract records are retained, a minimum of five years. On private projects its existence is the best defence against a challenge to the award by an unsuccessful candidate.

ℹ Who writes the report? The economist writes it, in coordination with the architect for the technical merit section. On public projects it is approved by the contracting authority before any notification. The report makes recommendations, it does not decide. The final award decision belongs to the client, and that distinction must be explicit in the document.

The standard structure

A complete report follows a seven-section structure, from the summary for decision-makers through to the traceability appendices. Each section has a specific audience and purpose.

Section Content Principal audience
1. Executive summary Outcome of the tender, number of offers, price range, recommendations by package, on one page Client, decision-makers
2. Conditions of the tender The selection criteria and weightings, list of candidates, check on formal admissibility Client, auditors
3. Financial comparison table Amounts by candidate and package, gaps against the estimate, price anomalies identified Client, economist, architect
4. Assessment of technical merit Scores by technical criterion, score table, justification of the differences Client, architect, engineers
5. Treatment of abnormally low offers Those identified, requests sent, summary of replies, conclusion on admissibility Client, legal adviser
6. Ranking and recommendation Final ranking by package, candidate recommended, the argument, residual risks Client, decision-makers
7. Appendices Original offers, technical statements, requests for justification, replies received Traceability file

Section 1 is often the only one a non-technical client reads. It must be written so that a decision can be taken without reading the rest, while pointing to the detailed sections behind every statement.

Financial analysis: beyond the total

The comparison table by package and item

At the heart of the financial analysis is the comparison table, setting every candidate's offer against the others item by item and package by package, with the economist's estimate as the reference. It must show significant gaps clearly, upward and downward, and flag them visually so that they are easy to read.

The aim is not an exhaustive table that is hard to read but a synthetic document highlighting the key points: which package concentrates the largest gaps? Which candidate is systematically under-priced on the technical items? Which offer combines coherence and competitiveness best?

Correcting arithmetical errors

Before comparing, the economist checks the arithmetic of each schedule or bill. Errors, an incorrect subtotal, a line omitted, VAT carried across wrongly, are corrected according to the contractual rules: the unit rate prevails over the extension, and the erroneous subtotal is put right. The corrections are documented in the report.

Technical merit and scoring

Technical merit is assessed from the technical statement each candidate submits. It is scored against the criteria and weightings announced in the tender rules.

Technical criterion Weight A /20 B /20 C /20 D /20
Understanding of the project 15 % 14 12 16 10
People and plant 20 % 16 14 12 15
Comparable references, last 3 years 20 % 18 10 15 12
Organisation and programme 25 % 15 16 13 11
Management of interfaces and concurrent working 20 % 14 15 12 10
WEIGHTED TECHNICAL SCORE /20 100 % 15.4 14.1 13.4 11.5
Financial score /20, price against the median 13.8 20.0 18.2 9.2
OVERALL WEIGHTED SCORE /20 (technical 40 %, price 60 %) 14.8 16.8 15.3 10.7

How to read it: contractor B takes the best overall score, 16.8/20, thanks to an excellent financial score as the cheapest offer, despite an average technical score. Contractor A is technically the strongest but its price, slightly above the median, costs it two points on the financial score.

Framing the recommendation

What a recommendation must contain

The economist's recommendation for each package must carry four elements:

  • The candidate recommended: named, with its offer corrected for arithmetical error.
  • The argument for the choice: why this candidate, its overall score, its technical strengths, its competitiveness, the absence of anomaly.
  • The residual risks identified: every point the client should watch during construction, a tight programme offered, substantial subcontracting, a specific item to monitor.
  • The unsuccessful candidates: a brief statement of why each was not recommended, technical score too low, price out of line, an unjustified abnormally low offer, so that reasoned rejection letters can be written.

What a recommendation must not do

It must not substitute itself for the client's decision. Nor should it criticise unsuccessful candidates by name in excessive terms: an analysis report may be disclosable to third parties and must stay factual and proportionate in its wording.

ℹ A word on confidentiality Candidates' offers are confidential. The analysis report, which summarises and compares them, must not be circulated to unsuccessful contractors in a way that would let them reconstruct their competitors' offers. On public projects what may be disclosed to unsuccessful candidates is governed by the procurement code. On private ones the client remains free, but should be wary of disclosures that could create an obligation to renegotiate.

Handing the report over and awarding the contract

The report goes to the client for decision. The economist presents the analysis at a review meeting, answers questions and supports the client in reaching a decision. Should the client's decision diverge from the recommendation, the client remains free to choose, but the economist must ensure the risks attached to the divergent choice are documented in the report, for their own protection.

Once the decision is taken, the economist assists with notification, award and rejection letters, drawing up the definitive forms of agreement, and prepares the contracts for signature.

In summary

The tender analysis report is the traceability and decision document of the award stage. Its seven sections cover the decision summary, the detailed financial analysis, the scored technical merit, the treatment of abnormally low offers and the reasoned recommendation. A good report lets the client decide with full knowledge, protects every party if the award is contested, and serves as a reference for managing the contract throughout construction.

The nature of the figures quoted

The percentages and amounts quoted on this page are orders of magnitude for framing, not measurements. They illustrate mechanisms and proportions, and they substitute neither for a tender exercise nor for an estimate prepared on drawings.

Sources: the BT construction cost indices published monthly by INSEE on its 2010 base, used to update the figures · construction cost statistics from SDES, the statistical service of the ministry responsible for construction · regulatory texts published in the Journal officiel and consolidated on Légifrance for the requirements cited.