1. The principle of deductions: the threshold rule
Most trades apply a threshold rule for deducting openings, windows, doors, bays, from the areas measured. That threshold varies with the trade.
A 0,50 m² threshold, the commonest: any opening larger than 0,50 m² is deducted from the area measured. Openings below that are counted in the gross area.
A 1 m² threshold, for external insulation and render: some trades apply a higher threshold of 1 m², so that a standard window of 0,80 × 1,20 m, at 0,96 m², is not deducted at all.
Limited deduction, for slabs and columns: columns carry no deduction, and slabs deduct only voids of 1 m² or more, as the table shows.
Applying these thresholds incorrectly is one of the commonest sources of divergence between the economist's quantities and the contractors' own. An economist who applies the 0,50 m² threshold to external render, where the usual threshold is 1 m², overstates the deductions and understates the quantities.
2. The reference table, trade by trade
The table below covers the commonest items across nine families of trades. For each: the correct unit, precisely what is measured, the deduction rules, the reference code, and the frequent error to avoid.
| Trade and item | Unit | What is measured | Deductions | Reference code | Frequent error |
|---|---|---|---|---|---|
| CONCRETE FRAME | |||||
| Trench excavation | m³ | Volume excavated, length × width × depth | None | DTU 12 (withdrawn) | Forgetting the allowance for battering in loose ground |
| Reinforced concrete walls | m² | Developed area of each wall, height × length | Deduct openings over 0,50 m² | DTU 21 | Measuring in m³ instead of m²; check which unit the rate is against |
| Reinforced concrete slabs | m² | Horizontal area per floor | No standard deduction; voids under 1 m² not deducted | DTU 21 | Forgetting balconies and terraces |
| Reinforced concrete columns | lm | Clear height between floor faces | None | DTU 21 | Measuring overall rather than clear, which overstates |
| MASONRY | |||||
| Brick façade walls | m² | Developed area of the walls, perimeter × height | Deduct openings over 0,50 m² | DTU 20.1 | Not deducting openings at all, overstating by 15 to 25 % |
| Single-coat external render | m² | Developed façade area including the window reveals | Deduct openings over 1 m² | DTU 26.1 | Forgetting the reveals, which understates |
| ROOF STRUCTURE AND COVERING | |||||
| Tiled roof covering | m² | Area on the slope, the real area of the pitch | Deduct rooflights over 0,50 m² | DTU 40.21 | Measuring on plan, understating by the pitch factor; at 35° the real area is 22 % greater |
| Flat roof waterproofing | m² | Horizontal area including 200 mm of upstand | Deduct penetrations over 0,10 m² | DTU 43.1 | Forgetting the upstands, understating by 8 to 12 % |
| Flashings, valleys, verges | lm | Real developed length of the profiles fixed | None | DTU 40.41 | Measuring on plan, which understates |
| FAÇADES AND INSULATION | |||||
| External insulation | m² | Developed façade area including the window reveals | Deduct openings over 1 m² | DTU 45.4 | Leaving out the reveals, which both understates and leaves a thermal bridge |
| Rainscreen cladding | m² | Developed area of the external face | Deduct openings over 0,50 m² | DTU 41.2 | Forgetting the soffits at the eaves |
| EXTERNAL JOINERY | |||||
| Windows and French doors | nr | By number, with the full description of dimensions and type | None; each window is one unit | EN 14351 | Measuring in m², which makes tenders impossible to compare |
| Roller shutters | nr | By number, tied to the corresponding window | None | EN 13659 | Counting them separately from the windows, a frequent omission |
| PARTITIONS AND LININGS | |||||
| Partitions | m² | Developed area of the partitions, height × length | Deduct openings over 0,50 m² | DTU 25.41 | Measuring gross without deducting the doors, overstating by 5 to 10 % |
| Internal wall linings | m² | Area of the walls lined, the internal faces of the façades | Deduct openings over 0,50 m² | DTU 25.41 | Confusing lining area with façade area; the lining is usually the smaller |
| Suspended ceilings | m² | Net horizontal area of the room | Deduct voids over 0,25 m², access hatches, recessed fittings | DTU 58.1 | Measuring the whole floor without allowing for the areas with no ceiling |
| FLOOR FINISHES | |||||
| Floor tiling | m² | Net area laid, the internal dimensions of the room | Deduct fixed elements over 0,10 m² | DTU 52.1 | Measuring gross from centre line to centre line, overstating by 5 to 15 % |
| Timber flooring, glued or floating | m² | Net floor area, internal dimensions | Deduct fitted cupboards | DTU 51.2 (glued), DTU 51.11 (floating) | Forgetting thresholds and transitions, a minor but recurrent item |
| Levelling screed | m² | Total floor area including circulation | Deduct plinths and services over 0,25 m² | DTU 26.2 | Confusing screed area with tiled area; the screed is the larger |
| PAINTING | |||||
| Internal wall painting | m² | Developed area of the walls including skirtings | Deduct openings over 0,50 m² | DTU 59.1 | Measuring gross without deducting openings, overstating by 15 to 25 % |
| Ceiling painting | m² | Net horizontal area, the same as the suspended ceiling | Deduct voids over 0,25 m² | DTU 59.1 | Lumping walls and ceilings into one item, distorting both |
| PLUMBING | |||||
| Water supply pipework | lm | Real developed length of the pipework, fixing included | None | DTU 60.1 | Forgetting the vertical risers and drops, understating by 20 to 40 % |
| Sanitary fittings | nr | By number: WC, basin, shower, bath, sink | None | DTU 60.1 | Counting from the floor plans without checking the service ducts |
3. The four most expensive confusions
One: roof area measured on plan instead of on the slope
Roof covering is measured on the slope, that is the real area of the pitch, not its projection on the ground. On a roof at 35°, the correction factor is the cosine of the pitch, 0,82, so the real area is 22 % greater than the horizontal projection. A roof take-off calculated on plan understates the quantities by 15 to 25 % depending on the pitch.
Two: tiling measured gross instead of net
Floor tiling is measured net, on the internal dimensions of the room, with fixed elements and thresholds deducted. A plan measured from centre line to centre line of the partitions overstates the tiled area by 5 to 15 %, depending on the partition thickness and the density of the plan. The rule is to deduct the partition thickness to obtain the real internal dimensions.
Three: internal lining confused with façade area
The internal lining is not equal to the external area of the façade. Linings are applied to the internal faces of the façade walls, with the same deduction rules as partitions. The window reveals, however, are generally not lined, which reduces the lining area against the façade area.
Four: pipework measured on plan instead of developed
Plumbing services are measured on their real developed length, including the vertical risers and drops. In a five-storey building the vertical supply and drainage stacks often represent 30 to 50 % of the total run. A plumbing take-off calculated only from the floor plans understates the quantities by 25 to 40 %.
4. The reference areas
Before any take-off, the project's reference areas have to be calculated or verified. They are what the quantities per trade are checked against.
Habitable area: the floor area of the rooms after deducting walls, partitions, stairs, service ducts, reveals and partition thicknesses. It is the area corresponding to real use.
Gross floor area: the reference area for planning purposes, including building density (planning code, art. R111-21 and R111-22), calculated from the internal face of the façades, deducting among other things the voids and openings for stairs and lifts and any area with a headroom of 1,80 m or less.
Gross usable area: the area used in commercial property for letting and for rates per m². Its make-up depends on the convention adopted, to be checked in each document.
Which area should the rates be based on? The choice of reference area determines whether rates can be compared at all. In housing, rates are expressed per m² of habitable area. In commercial property, per m² of gross usable area. In hotels, per room or per m² of floor area. A rate expressed per m² of gross floor area is not directly comparable with one per m² of habitable area: the ratio between the two varies from 0,75 to 0,90 with the compactness of the building. Always check which area is the denominator before comparing rates.
5. The reference codes by family
Concrete frame: DTU 13.1 (shallow foundations), DTU 13.2 (deep foundations), DTU 21 (execution of concrete works), EN 206 (concrete), the former DTU 12 (earthworks) having been withdrawn.
Masonry: DTU 20.1 (walls in small units), DTU 26.1 (mortar renders).
Roof structure and covering: DTU 31.1 (timber framing), DTU 31.3 (engineered trusses), DTU 40.11 (slates), DTU 40.21 (clay tiles), DTU 43.1 (flat roof waterproofing).
Façades and insulation: DTU 45.4 (external insulation behind ventilated rainscreen cladding), DTU 41.2 (external timber cladding), DTU 26.1 (external render).
Joinery: EN 14351-1 (external windows and doors), DTU 36.5 (installation of external windows and doors).
Partitions, linings, ceilings: DTU 25.41 (plasterboard), DTU 25.1 (internal plastering), DTU 25.31 (plaster blocks), DTU 58.1 (suspended ceilings).
Tiling and flooring: DTU 52.1 (bedded floor finishes), DTU 52.2 (adhesive-fixed finishes), DTU 51.1 (nailed timber flooring), DTU 51.2 (glued timber flooring), DTU 51.11 (floating flooring).
Plumbing: DTU 60.1 (sanitary plumbing), DTU 60.5 (copper pipework), DTU 60.11 (design rules), DTU 60.32 and 60.33 (PVC rainwater, then foul and soil drainage).
Heating and ventilation: DTU 65.11 (safety devices for central heating) and DTU 68.3 (mechanical ventilation).
In summary
Measurement rules vary by trade and draw in part on the French technical standards. The deduction threshold is the commonest source of error: 0,50 m² for most trades, 1 m² for external render and external insulation. The four most expensive confusions are roof area measured on plan (15 to 25 % understated), tiling measured gross (5 to 15 % overstated), lining confused with façade area, and pipework measured without the vertical runs (25 to 40 % understated). The reference areas are not interchangeable; always check the denominator before comparing rates. The main codes to keep to hand are DTU 21 for the concrete frame, DTU 25.41 for partitions and linings, DTU 40.11 and 40.21 for roof coverings, DTU 52.1 for tiling and NF C 15-100 for electrical installations.
The nature of the figures quoted
The percentages and amounts quoted on this page are orders of magnitude for framing, not measurements. They illustrate mechanisms and proportions, and they substitute neither for a tender exercise nor for an estimate prepared on drawings.
Articles liés
- How to produce reliable quantities: methods, sources of error and a checklist
- How to build a pricing schedule: structure, coding and completion rules
- Construction costs in France: rates per m², building types and the factors that move them
- Underestimating the budget at concept stage: why the first figures are always too low
Sources: the BT construction cost indices published monthly by INSEE on its 2010 base, used to update the figures · construction cost statistics from SDES, the statistical service of the ministry responsible for construction · regulatory texts published in the Journal officiel and consolidated on Légifrance for the requirements cited.