The design team: role, membership and responsibilities
The maître d'œuvre (MOE), the design team, is the professional body appointed by the maître d'ouvrage (MOA), the client, to design a building and to direct its construction. On most building operations the design team is multidisciplinary rather than a single practice.
Who sits on the design team
| Architect (lead consultant) | Head of the design team. Responsible for the architectural design, for the planning application and for the coherence of the project as a whole. The architect coordinates the other members. |
|---|---|
| Construction economist | Produces the cost estimates, the measured quantities, the pricing schedules (DPGF), the priced bills (DQE) and the technical specifications (CCTP). Carries the financial monitoring of the project from first sketch to handover. In public procurement, their estimates underpin the forecast cost the appointed design team commits to, settled as its appointment provides and no later than the launch of the works tender (R2432-2 and R2432-3). |
| Technical design consultants (BET) | Specialists by discipline: structure and reinforced concrete, mechanical and plumbing, power, data and communications, external works, façades. Their involvement varies with the complexity of the project. |
| OPC, programming and site coordination | A separate appointment from the core design team duties. Drives the construction programme, coordinates the contractors on site and manages the interfaces between work packages. |
The technical inspector is not part of it: it acts at the client's request, under the contract between them, and its work is incompatible with any design activity. The health and safety (SPS) coordinator is appointed by the client under a specific written contract or amendment, paid separately; where the operation exceeds 760,000 euros, the coordinator may hold no other role on it, except on operations of municipalities or groups of municipalities with fewer than 5,000 inhabitants.
On small projects, a house or an apartment refurbishment, the architect may carry the whole of the design work alone. On larger operations an all-trades design consultancy completes the team, and complex projects, public-access buildings, high-rise and commercial schemes, call on separate specialists for each technical discipline.
How fees are distributed across the stages
As an order of magnitude, French fee levels for a full appointment, ESQ through to AOR, generally sit between 7 and 15 % of the works budget depending on the size of the operation, 10 to 15 % for small operations and 7 to 10 % for larger ones, according to the orders of magnitude published by the MIQCP (the interministerial body for the quality of public buildings) in 2008, which "must in no case become methods of calculation".
| ESQ, concept design | ~8 % of the fee |
|---|---|
| APS, outline design | ~10 % |
| APD, developed design | ~17 % |
| PRO, detailed design | ~19 % |
| ACT, contract assistance | ~7 % |
| Design stages subtotal | ~61 % |
| VISA, review of contractors' drawings | ~9 % |
| DET, direction of the works | ~24 % |
| AOR, assistance at handover | ~6 % |
| Construction stages subtotal | ~39 % |
Source: Overall rate: MIQCP, "Évaluer l'enveloppe financière prévisionnelle d'un ouvrage de bâtiment", June 2008. Split by assignment element: indicative order of magnitude; each design appointment sets the breakdown of its lump-sum fee (R2432-6).
The design stages: from first sketch to the construction pack
The design stages cover all the intellectual work produced before the site opens. They follow a logical progression: each stage sharpens the technical and financial definition of the project, and commits it a little further.
ESQ, concept design
The esquisse is the first spatial translation of the brief. It tests whether the architecture is feasible and produces a first budget envelope from cost per square metre ratios. It presumes no settled technical solutions: it is a stage of intent.
- Architectural deliverables: principle drawings at 1:200 to 1:500, massing sketches, landscape integration.
- Cost deliverable: an order of magnitude obtained by applying ratios. Indicative accuracy: ±25 to 30 %.
- What is at stake for the client: confirming the project is feasible before committing to anything, and in particular before submitting the planning application.
APS, outline design
The APS turns the concept into preliminary technical options. Areas are fixed, structural principles settled, concrete, timber or steel frame, façade types, mechanical systems. APS ends with a provisional estimate of the forecast works cost (R2431-10); the design team does not commit at this stage.
- Architectural deliverables: floor plans, sections and elevations at 1:100 to 1:200, outline description.
- Cost deliverable: an APS estimate by trade or by functional element. Accuracy: ±15 to 20 %.
- What is at stake: the decision to carry the project forward on realistic financial ground. An APS estimate set too low creates difficulties that cannot be undone at APD or tender stage.
APD, developed design
APD is the hinge of the project. Technical choices are settled and the drawings are precise enough to support the planning application. APD produces the definitive estimate of the forecast works cost, broken down by trade (R2431-11). In public procurement, the forecast cost the design team commits to may be settled on that estimate: the design appointment sets out how, and the code only sets a deadline, before the launch of the works tender procedure (R2432-2 and R2432-3). If tenders exceed that cost beyond the tolerance, the client can ask the design team to adapt its studies at no extra fee, except, for design appointments whose tender was launched or contract notice sent for publication on or after 1 January 2023, where the overrun results from circumstances the design team could not foresee (decree no. 2022-1683, art. 3 and 8). A fee reduction only follows the second commitment, checked after completion (R2432-4).
- Architectural deliverables: accurate drawings at 1:100, outline description of the works, complete planning file.
- Cost deliverable: preliminary APD measured quantities, with a description by trade. Accuracy: ±10 %.
- What is at stake: in public procurement, the APD quantities can underpin the forecast cost the design team commits to (R2432-2 and R2432-3). Reliable APD quantities are the best shield against later claims.
PRO, detailed design
The PRO stage produces the technical documents the tender process requires. Drawings at 1:50 and details, technical specifications by work package, detailed quantities, priced schedules: a contractor must be able to price its bid precisely from the PRO pack alone. It is the most demanding stage in sheer volume of documents.
- Architectural deliverables: detailed design drawings at 1:50, with details from 1:20 to 1:2, technical details, detail books, drawings by work package.
- Cost deliverables: technical specifications (CCTP) by package, PRO quantities, priced bills (DQE).
- What is at stake: the quality of the PRO pack governs the quality of the bids received. An imprecise specification breeds ambiguity, and ambiguity breeds variations.
Structural works and finishing trades: two distinct cost worlds The structural works, gros œuvre, cover earthworks, foundations, reinforced concrete and frame. They generally represent 30 to 40 % of the works cost depending on structural complexity. The finishing trades, second œuvre, cover everything that clothes the building and makes it work: roofing, waterproofing, external joinery, plasterwork, insulation, finishes, mechanical services, electrical and plumbing. They represent 60 to 70 % of the works cost, and that is where budget control is really won or lost. The milestone known as hors d'eau, hors d'air, watertight and weathertight, reached when the roof and the external joinery are in place, is a key contractual marker: it opens the internal finishing works.
Going out to tender: DCE and ACT
Tendering is the stage that joins design to construction. It carries two distinct duties: assembling the tender pack (DCE) and analysing the bids received (ACT).
DCE, the tender pack
The DCE gathers every document issued to tendering contractors so that they can price the work. The design team assists the client in assembling the administrative and technical pieces of the pack.
| CCAP | Particular administrative conditions: a contractual document drafted by the client or its procurement department. Sets the conditions of performance, programme, damages, payment terms. |
|---|---|
| CCTP | Particular technical specifications: the technical document drafted by the design team and its consultants. Describes precisely what is expected, package by package. |
| DPGF | Pricing schedule, broken down by package and sub-package, allowing bids to be compared and the works to be monitored financially afterwards. |
| DQE | Priced bill of quantities at unit rates, used to price variants and any additional works. |
| Tender drawings | The graphic pieces of the PRO pack, re-titled for tender or for contract. Architectural and technical drawings by package. |
The packaging strategy, deciding whether contracts will be let trade by trade or to a single main contractor, rests with the client. It bears directly on the final cost and on how demanding the site coordination will be.
ACT, assistance with the works contracts
Once the bids are in, the ACT duty is to analyse them, compare them and support the client through negotiation with the contractors. The economic stakes are high: bid analysis reveals under-pricing, a well-known source of later variations, and abnormally low bids.
- Economic analysis of the bids: checking that prices hold together, comparing package by package, exposing the gaps against the estimate.
- Comparative bid table: the summary that lets the client see every offer in a single document and decide on an informed basis.
- Settling the contracts: technical and financial negotiation with the selected contractors before signature.
Spotting an abnormally low bid: the B&A mechanism
A contractor's bid breaks down into direct costs (DS), site overheads (FC), operational costs (Fop), general overheads (FG) and B&A, profit and contingency. The B&A is the contractor's risk provision and its margin.
A bid whose B&A falls below 3 to 4 % of the selling price excluding VAT is in a fragile position: at the first hazard on site, weather, unforeseen ground conditions, a change of brief, the contractor is in deficit and will try to recover through claims and variations.
An architect and a quantity surveyor who can read that price structure are able to warn the client before the contract is signed, and to spare everyone an expensive dispute later.
The construction stages: VISA, DET and AOR
Once the contracts are signed, the design team enters its construction duties. These stages are less documented than the design stages, and yet they decide the final cost.
| VISA, review of contractors' drawings | The design team checks that the construction drawings produced by the contractors, or by consultants they have appointed, are consistent with the contractual PRO pack. A visa does not technically validate the contractor's calculations, which remain its own responsibility, but confirms that they conform to the PRO pack. |
|---|---|
| DET, direction of the works | Weekly monitoring of the site: site meetings, minutes, validation of the contractors' interim applications, issuing of instructions, handling of variations, checking the draft final account and drawing up the general account (R2431-16, 4°). DET is the longest stage in duration and the most demanding in responsiveness. |
| AOR, assistance at handover | AOR supports the client through the handover operations: pre-handover inspections, the schedule of defects, the clearing of those defects and receipt of the as-built file (DOE). |
Financial monitoring during DET is particularly critical. The architect and the quantity surveyor must validate the contractors' monthly applications against real progress on site, not against declared progress. Any over-validation creates an imbalance that is hard to correct at the end of the job.
The general account of each works contract belongs to site direction (DET), not to handover assistance (AOR): the design team checks the contractor's draft final account and draws up the general account (R2431-16, 4°). Where the works contract refers to the 2021 CCAG-Travaux, the design team prepares the draft, which the client validates, signs and notifies to the contractor; once the contractor signs it without reservation, it becomes the final general account (DGD), which binds the parties for good and settles the balance of the contract (art. 12.4.1 to 12.4.3). It brings together every validated application, every signed variation and any liquidated damages. Drafting it rigorously is the client's last financial protection.
Loi MOP and private appointments: two regimes, two logics
Whether the client is public or private determines the legal frame the design team appointment sits in.
The core appointment under loi MOP
Book IV of Part Two of the Public Procurement Code sets the mandatory frame for design appointments awarded to private-law firms by the clients it lists (L2411-1 and L2430-1), except for state-aided rental housing built by public housing offices, private social housing bodies and semi-public companies (L2430-2), for tenders launched since 1 April 2019. It codified the former loi MOP, law no. 85-704 of 12 July 1985, repealed except for the last paragraph of its Article 1, and decree no. 93-1268 of 29 November 1993 on design assignments, also repealed; design appointments tendered before that date are still governed by those texts. Its founding principle: entrust the design to a single team, answerable for the coherence of the project from first sketch to handover.
The core appointment under loi MOP necessarily comprises ESQ, APS, APD, PRO, ACT, VISA or EXE, DET and AOR, except the concept design on refurbishment (R2431-5). It cannot be broken up or split between different teams for design and for construction, save in particular circumstances.
One point is essential and often misunderstood: the fee stated in the original appointment is provisional. Where the forecast works cost is not yet known when the design appointment is awarded, the fee it states is provisional and is calculated on the share of the client's provisional financial envelope allocated to the works (R2432-7). APD must allow the lump-sum fee to be set on the terms of the appointment (R2431-11), a fee that takes account of the forecast cost based on either the APS or the APD estimate (R2432-6). If tenders exceed the forecast cost the design team committed to, beyond the tolerance, the client can ask it to adapt its studies at no extra fee (R2432-3). If the final total cost of the works exceeds the tolerance of the second commitment, checked after completion, the design team's fee is reduced, by up to 15 % of the fee for the assignment elements after award of the works contracts (R2432-4). For design appointments whose tender was launched, or contract notice sent for publication, on or after 1 January 2023, rework at no extra fee cannot be required where the overrun results from circumstances the design team could not foresee, and only an overrun caused by a failing in its duties of site direction and assistance with handover triggers the reduction (decree no. 2022-1683, art. 3 and 8).
The private appointment: freedom and exposure
For a private client, a developer, a private individual or a company, no regulation dictates what the appointment must contain. The contract is freely negotiated. That freedom has its advantages, tailored duties and negotiated fees, and its risks.
| Loi MOP, public client | Core appointment mandatory, ESQ to AOR on new build and APS to AOR on refurbishment. Content of each stage set by decree. Commitment to the forecast cost settled as the appointment provides, no later than the works tender, then to the cost resulting from the works contracts. Rework at no extra fee if the client asks, then a fee reduction capped at 15 %, on the conditions set out above (R2432-3 and R2432-4). Public procurement rules govern the choice of design team. |
|---|---|
| Private appointment | Content freely negotiated. Partial appointments possible, planning application only, design only, and so on. Lump sum or time-based fees by agreement. No statutory penalties, but contractual liability throughout. Risk of dispute where the scope is not precisely defined. |
The trap of an incomplete private appointment: an architect engaged only for the planning application and the design stages, with no site duties, loses the ability to check that what is built matches the drawings. Defects then become the architect's liability without any means of having prevented them.
Cost deliverables, stage by stage
Every design stage carries one or more cost deliverables. Their quality governs the reliability of the client's financial decisions, and the exposure of the design team.
| Stage | Cost deliverable | Accuracy | Produced by |
|---|---|---|---|
| ESQ | Order of magnitude from ratios | ±25–30 % | Architect / economist |
| APS | APS estimate by trade | ±15–20 % | Construction economist |
| APD | APD quantities, definitive estimate of the forecast cost | ±10 % | Construction economist |
| PRO | Specifications by package, quantities, priced bill | Contractual | Economist and consultants |
| DCE | Priceable schedule, price analysis | Contractual | Construction economist |
| ACT | Comparative bid table | n/a | Construction economist |
| DET | Validation of monthly applications and general account (R2431-16, 4°), signed and notified by the client (CCAG-Travaux 2021, art. 12.4.2) | Actual progress and contract balance | Economist and architect |
| AOR | n/a | n/a | Construction economist |
Producing these deliverables is a considerable workload, and small architectural practices routinely underestimate it. A poorly calibrated APS estimate can absorb several days of research into ratios, adjustment and presentation, for a result that nonetheless binds the design team for the whole of the operation.
The stages at a glance
| Stage | Purpose | Key deliverable | What is at stake | % of fee |
|---|---|---|---|---|
| ESQ | Architectural feasibility | Sketches and budget ratio | Order of magnitude | ~8 % |
| APS | Preliminary technical options | APS estimate, drawings at 1:200 | Provisional estimate of the forecast cost | ~10 % |
| APD | Settled technical definition | Quantities and planning file | Definitive estimate of the forecast cost | ~17 % |
| PRO | Construction pack | Specifications, quantities, priced bill | Maximum documentary precision | ~19 % |
| DCE | Going out to tender | Pricing schedule, conditions, contract drawings | Pack quality decides bid quality | within PRO |
| ACT | Selecting the contractors | Comparative table and contracts | Detecting abnormal bids | ~7 % |
| VISA | Reviewing construction drawings | Visas on the contractors' drawings | Conformity with the contract | ~9 % |
| DET | Directing the works | Minutes, validated applications and general account (R2431-16, 4°) | Keeping variations in hand and settling the contracts | ~24 % |
| AOR | Closing the job | As-built file, handover | Clearing of defects | ~6 % |
Documentary sources: Léonard Hamburger, Maître d'œuvre Bâtiment, guide pratique, technique et juridique, 3rd ed., Eyrolles, 2016 · Yves Widloecher and David Cusant, Manuel d'analyse d'un dossier de bâtiment, 2nd ed., Eyrolles, 2018.
The nature of the figures quoted
The percentages and amounts quoted on this page are orders of magnitude for framing, not measurements. They illustrate mechanisms and proportions, and they substitute neither for a tender exercise nor for an estimate prepared on drawings.
Sources: the BT construction cost indices published monthly by INSEE on its 2010 base, used to update the figures · construction cost statistics from SDES, the statistical service of the ministry responsible for construction · regulatory texts published in the Journal officiel and consolidated on Légifrance for the requirements cited.