How the linkage works
Model elements are allocated to cost groups, quantities are taken from the model and priced with benchmarks or unit rates. On that basis a cost determination structured by cost group can be generated.
What matters is how the costs reach the model: they are as a rule not held as attributes within the model but assigned to the elements afterwards through a link to external databases. Valuation therefore stays outside the model and can be exchanged at any time.
There is a good reason for this. A price is not a property of an element but a property of element, place, date and market conditions together. A price held in the model would be wrong within months and could not be adjusted for region. Separating geometry from pricing is therefore not a detour but the right architecture.
Open formats are used for exchange, in particular IFC for the model data. Separate bodies of rules and schema definitions exist for connecting model objects to commercial data.
Completion levels for cost determination
A dedicated set of guidelines exists for model-based quantity take-off, defining five completion levels for cost determination, from 100 to 500. They describe which information state of the model elements supports which kind of cost determination.
| Completion level | Supports | Information state at least |
|---|---|---|
| 100 | estimating total cost and building cost | briefing |
| 200 | quantities of a building volume, structured at an upper level | concept design |
| 300 | quantities of individual element types, finer structure | developed design |
| 400 and 500 | quantities at item and execution level | detailed design and procurement |
This grading is useful because it answers a question constantly asked in practice: from which model state is which cost statement possible. The answer is that the information state of the model and the stage of cost determination must match.
A note on application: the mapping of completion levels onto the levels of the cost structure should be reconciled with the current edition of DIN 276 before use. The relevant guideline and the reissue of the standard date from the same year, and the standard deepened the required treatment for the cost estimate and cost calculation each by one level. Anyone using both bodies of rules together should check the current editions and fix the governing requirement within the project.
Where the limits lie
Three limits act together, and the first hits precisely the fee-relevant cost group. None of them disappears with better software.
| Limit | What it consists of |
|---|---|
| The level of detail varies between disciplines | in building services the item level, meaning ducts, fittings, components and insulation, is reliably modelled only from detailed design onwards |
| Not everything in a building is a model element | site set-up, shoring, protection measures, demolition in existing fabric and a substantial part of KG 200 and 700 have no geometry |
| Model quality determines result quality | walls modelled storey by storey or continuously, openings deducted or not, the handling of layered build-ups: all of it decides the quantity |
An asymmetric situation follows, matching one already familiar: KG 300 can be determined from a model earlier than KG 400. Since it is KG 400 that triggers the fee-relevant threshold rule, the critical part of the determination stays benchmark-based the longest.
What can actually be gained
The benefit lies less in speed than in three other things. The third is economically the most significant, because it acts in the early phases where the room for management is greatest.
| Gain | What it means |
|---|---|
| Traceability | every quantity remains attributable to a model element; on a variance it is visible whether quantity or price was the cause |
| Updatability | a design change acts directly on the quantities, so the principle that costs mirror the design is technically embodied rather than asserted |
| Variant comparison | two design options can be set against each other on the same valuation basis, because valuation is separated from geometry |
The system of interventions is covered in the article on cost management. That article also explains why the room maneuver shrinks with every step of design progress.
Handling existing buildings
On projects in existing buildings, model-based cost determination meets an additional difficulty: there is no model, only a building. Here the model is not the starting point but the first deliverable.
An as-built model must first be created, from measured survey, laser scan or existing documents. That effort falls before the cost determination, is a service to be separately agreed, and is routinely underestimated in project planning.
A fundamental limit is added: a model can only represent what is known. Concealed elements, service routes and the actual condition of the fabric cannot be modelled before opening up. An as-built model therefore suggests a completeness it does not have, and in existing buildings that suggestion is more dangerous than openly stated uncertainty.
In practice it follows that an as-built model should carry its state of knowledge, that is which elements derive from survey, which from documents and which from assumption. That distinction is precisely the basis on which contingencies are justified, as described in the article on cost risks and contingencies.
What must be agreed contractually
Model-based cost determination presupposes agreements going beyond a conventional design contract. All four are settled before the project starts, or not at all.
| # | To be settled | Why |
|---|---|---|
| 1 | The modelling conventions | because they determine the quantities |
| 2 | The information level required per design phase | matched to the stages of cost determination |
| 3 | The mapping of model elements to cost groups | including the question of who maintains it |
| 4 | The handling of cost shares not modelled | particularly KG 200 and 700 |
The fourth is most frequently overlooked and creates the largest gap, because the non-modelled components are precisely those also missing from conventional benchmarks. It therefore decides the completeness of the entire determination.
This article reflects the position of the relevant bodies of rules at the date of checking and serves professional orientation. The guidelines on model-based quantity take-off are maintained and updated and must be consulted in their current editions before any application. It does not constitute legal advice and does not replace assessment of the individual case.