Facade costs per m²: ETICS, brick, timber, curtain wall

📐 Topic

By , construction economist

9 min read

What this article covers How four facade systems differ on the same external wall area of an apartment building, not only in price per square metre but in wall thickness, window proportion, fire protection and upkeep. Also, why the price per square metre of a system says nothing without a quantity, and how the appearance of a design can be kept with a different system. In multi-storey housing, the facade is the largest visible surface and at the same time one of the largest items in cost group 330. Anyone searching for facade costs per square metre finds prices per system, but rarely the area by which they have to be multiplied. This article belongs to the guide Reducing construction costs in Germany: the decisions that fix costs at design stage and compares the systems on the external wall of the example project.

The area in question

The example project is an apartment building with 24 dwellings, four full storeys and about 2,200 m² of gross floor area under DIN 277, building 32.0 × 12.5 m with a storey height of 3.00 m. Its external wall measures about 1,070 m² including windows, calculated as a perimeter of 89 m times a wall height of 12 m. The amounts in this article are example values and serve only the logic of the calculation.

How strongly the form changes this area is shown in the article Compactness and the surface-to-volume ratio: four setbacks increase it to 1,260 m². Every difference in the price of the facade system acts on this area, and that is why the order is form before system. Anyone who chooses the system first and then articulates the building makes the chosen system more expensive with every corner.

Four systems on the same wall

System Cost group Price per m² of external wall, solid part (example) Difference from ETICS on the base area (example)
Wärmedämmverbundsystem (WDVS, external thermal insulation composite system or ETICS) on masonry or concrete KG 330 about 210 €/m² net, with loadbearing wall and internal plaster Base
Cavity wall with facing brick outer leaf KG 330 about 335 €/m² net about 100,000 € more, calculated on about 800 m² of solid wall
Ventilated rainscreen timber facade KG 330 about 265 €/m² net about 44,000 € more
Curtain wall, stick system or unitised KG 330 no example value no example value

The prices refer to the solid part of the wall, without windows. That is decisive for the comparison: anyone comparing one facade price with windows and one without is comparing two different scopes of work. How cost group 330 breaks down further by building element is described in the article on KG 300 building fabric.

The window proportion as the second variable

Windows cost more per square metre than solid wall, and their proportion of the external wall is a design decision. On the example project, a window proportion of 25 per cent gives about 267 m² of windows and a proportion of 40 per cent about 427 m², that is 160 m² more on the same wall. The solid area falls by the same amount, and the difference follows from the gap between the two unit prices.

Window proportion Window area Solid wall Difference from the 25 per cent variant (example)
25 per cent about 267 m² about 801 m² Base
40 per cent about 427 m² about 641 m² about 37,000 € more

The window proportion has effects beyond price. It changes summer thermal protection, the need for solar shading and the energy demand in winter. A larger glazed area is therefore rarely a purely aesthetic question and should be carried in the comparison of variants together with its follow-on items.

Wall thickness costs floor area

A facade system changes not only the external wall but also what remains inside. A facing brick outer leaf with insulation and cavity is usually thicker than an ETICS with the same insulating effect. Assuming for the example 10 cm of extra thickness, about 9 m² of floor area per storey is lost for the same external dimensions, about 36 m² over four storeys, and this area is missing from the dwellings.

For the client, this is a cost line of its own. Either the external dimensions are increased to keep the living area, and with them roof, slabs and gross floor area, or the living area falls, and with it the sales proceeds or the rent. In both cases the difference belongs in the comparison, even if it does not appear in cost group 330.

Fire protection by building class

Which materials are permitted on the facade is governed by the building code of the federal state, depending on the building class. With four storeys and dwellings of up to 400 m², the example project belongs in Bavaria to building class 4, as the article on compactness shows. In Bavaria the following applies:

  • Surfaces of external walls and external wall claddings, including insulation and substructures, must be of low flammability; substructures of normally flammable materials are permitted if fire spread on and within the external wall is limited for a sufficiently long time (Art. 26(1) and (3) BayBO).
  • For ventilated external wall claddings, special precautions must be taken against fire spread (Art. 26(4) BayBO).
  • The requirements of subsection (3) and of subsection (4) for ventilated external wall claddings do not apply to buildings in building classes 1 to 3 (Art. 26(5) BayBO).
  • By way of exception, external wall claddings that comply with the Technische Baubestimmungen (technical building rules) are permitted, insulation excepted, in normally flammable materials (Art. 26(5) BayBO).

For the cost estimate, it follows that the same facade design can require different systems in building class 3 and in building class 4. Which structural measures an ETICS with combustible insulation or a timber cladding requires in the individual case follows from the technical building rules and from the system's proof of usability. In the other federal states, the relevant state building code has to be consulted.

Upkeep and service life

A facade price is a construction price, and the systems differ more in upkeep than in construction. An ETICS with a render finish needs repainting at intervals and is vulnerable to impact at the plinth and at entrances. A brick leaf is more expensive to build and undemanding to maintain, a timber facade requires care according to its treatment or a deliberately accepted greying, and a curtain wall needs cleaning and replacement of seals.

Whether a cheaper facade stays cheaper over its service life can only be answered by comparing construction and running costs on the same line. How that comparison is built and who bears the follow-on costs is shown in the article False economies: what lowers construction costs and raises running costs.

Keep the image, change the system

The facade carries the appearance of the design, and that is why it is the most hard-fought element. Between the most expensive system on every surface and the cheapest system everywhere, there are intermediate solutions that largely preserve the image:

  • Use the high-quality material where it is seen and touched, that is at the plinth, at the entrances and towards the street, and a simpler system on the courtyard and gable sides.
  • Create the articulation of the facade through window formats, reveals and colours rather than through setbacks in the building form.
  • Limit unitised solutions to the areas that need them functionally, for example large glazed areas on the ground floor.

Each of these solutions is a design decision that belongs in preliminary design. Later, when the facade has already been agreed with the client and possibly with the permitting authority, the same decision becomes a redesign with fee consequences.

Sources: gesetze-bayern.de, BayBO, Art. 2(3) and Art. 26(1), (3), (4) and (5) · DIN Media, DIN 276:2018-12 and DIN 277:2021-08 (title and scope). Checked on 26 November 2026. Prices given as examples, established in November 2026 from public references: ARGE//eV, Vergleich verschiedener Bauweisen im Wohnungsbau 2016; FH Joanneum, Fassadensysteme im Fokus der Lebenszyklusbetrachtung 2021; VFF and Bundesverband Flachglas, Fensterstudie 2024; Destatis, Baupreisindex für Wohngebäude 2026. The extra thickness of the brick leaf is an assumption of the example.

Frequently asked questions

That depends on the system, on the window proportion and on whether windows are included in the price. For the example project, this article gives example values for three of the four systems on the same external wall area; the price per square metre must always be read together with the area to which it applies.

Often to build, but not necessarily over the service life, because the systems require different amounts of upkeep. In addition, whether it is permitted depends on the building class, which can trigger additional measures.

Because a thicker external wall costs living area for the same external dimensions. On the example project, 10 cm of extra thickness costs about 36 m² of floor area over four storeys.

That is governed by the relevant state law, depending on the building class. In Bavaria, external wall claddings in building class 4 must in principle be of low flammability, but claddings complying with the technical building rules may, except for the insulation, also be normally flammable. A timber substructure is permitted if fire spread on and within the external wall is limited for a sufficiently long time, and for a ventilated cladding special precautions against fire spread must be taken (Art. 26(1), (3) and (4) BayBO).