Where costs are fixed
The HOAI (the German fee scale for architects and engineers) describes exactly the moment at which the cost-determining decisions are made. Under Annex 10, the basic services of work phase 2 include "preparing the preliminary design, examining, presenting and assessing variants against the same requirements" and the "cost estimate under DIN 276, comparison with the financial framework" (unofficial translation, as are all quotations in this guide). Comparison of variants and cost estimate therefore sit in the same phase, and that is no coincidence: this is where it is decided which variant is taken forward.
The structural engineer also contributes in this phase to decisions that can hardly be changed later. Under Annex 14 HOAI, the engineer's basic services in work phase 2 include examining the possible structural solutions and stating the main structural decisions, and these expressly include "structural grid and type of foundation". Anyone who leaves the grid and the foundations open in preliminary design pushes two of the largest cost decisions into a phase in which they can only be corrected with effort.
The BGB (German Civil Code) comes in even earlier. Where essential design and supervision objectives have not yet been agreed, the architect submits to the client a design basis "together with a cost assessment for the project for approval" (section 650p(2) BGB). For this subject, that means: even before preliminary design there is a point at which programme and costs are on the table together.
| Phase | What is fixed | Cost statement |
|---|---|---|
| Needs planning, establishing the basis | Schedule of accommodation, number of dwellings, parking concept | Cost framework, cost assessment under section 650p BGB |
| Preliminary design (LPH 2) | Massing, number of storeys, basement, grid, type of foundation, facade principle | Cost estimate under DIN 276 |
| Design (LPH 3) | Constructions, facade build-up, building services concept, details | Cost calculation under DIN 276 |
| Detailed design and contract award | Methods of execution, products, division into contract packages | Pre-tender estimate, tenders |
The table shows why this guide stays in the first two rows. The method of the two early stages, their level of breakdown and their typical gaps are covered in the article Cost framework and cost estimate: the early stages. Here the question is which decisions in these stages move the result, and by how much.
The example project
All articles in this subject area calculate with the same project. That keeps every difference comparable, and the reader sees how much weight each decision carries.
| Item | Example project |
|---|---|
| Use | Apartment building, 24 dwellings |
| Storeys | four full storeys, one basement |
| Gross floor area under DIN 277 | about 2,200 m², of which 1,600 m² above ground (four storeys of 400 m² each) and 600 m² in the basement |
| Basement | Underground car park for 24 spaces, storage rooms, plant |
| Building | 32.0 × 12.5 m, storey height 3.00 m, flat roof |
| Living area | about 1,250 m² |
| External wall area | about 1,070 m² including windows |
| Costs KG 300 and 400 (base) | about 3,960,000 € net |
| Benchmark KG 300 and 400 per m² GFA | about 1,800 €/m² GFA net |
| Price base of the example values | August 2026, net |
The ratio of living area to gross floor area is about 57 per cent. It is therefore at the upper end of the values usual for apartment buildings, even though the basement counts in full towards the gross floor area. Anyone who mixes benchmarks per m² of living area and per m² of gross floor area will find the explanation in the article Construction costs per m² in Germany.
The method: one assumption at a time
An early cost statement is only as good as its comparability. Anyone comparing two variants in which the number of storeys, the basement and the facade change at the same time ends up with a difference they cannot explain to anyone. The method of this guide is therefore strict: each article changes exactly one assumption of the example project and holds everything else fixed.
This gives five rules. They apply unchanged to your own project:
- The same reference quantity for all variants, normally the gross floor area under DIN 277, and the same delimitation of the cost groups.
- The same price base and the same tax basis, so that the difference does not come from the reference date.
- Justify the difference through quantities: square metres of external wall, roof area, foundation area, number of parking spaces, length of transfer beams.
- Allocate every quantity difference to the cost group in which it arises, at least at the second level of DIN 276.
- Name the knock-on effects, even if they cannot yet be quantified: fees, construction time, permit, running costs.
The third rule is the most important. A benchmark per square metre of gross floor area for the whole of cost group 300 does not reveal why a variant is more expensive; the quantity per building element does. An articulated building carries more external wall per square metre of living area, a basement more excavation and waterproofing, a transfer structure more steel. How cost group 300 breaks down into groups of building elements is shown in the article on KG 300 building fabric.
The six decisions at a glance
The following overview sets the six decisions side by side. The amounts are example values at the August 2026 price base, net; where no amount is given, the difference depends on the project's unit prices. The quantities and the cost groups affected apply regardless of the price level.
| Decision | Variant compared with the base | Effect on quantities | Mainly affected | Difference (example) |
|---|---|---|---|---|
| Compactness | Building with four setbacks instead of a rectangle | +192 m² external wall | KG 330 | at least about 51,000 € more |
| Parking | 24 parking spaces above ground instead of an underground car park | about 500 m² less GFA in the basement, but about 600 m² of paved area on the site | KG 310 to 360, KG 400, KG 500 | about 528,000 € less |
| Grid | Dwelling grid drawn without regard to the car park, with a transfer structure above the basement | Transfer beams or a strengthened slab above the basement | KG 340, KG 350 | depends on the unit prices |
| Foundations | Piled foundation instead of a raft after the geotechnical report | Piles under about 600 m² of foundation area | KG 320 | depends on the geotechnical report |
| Facade | Facing brick outer leaf instead of ETICS | same area of about 1,070 m², different build-up | KG 330 | about 100,000 € more, calculated on about 800 m² of solid wall |
| Life cycle | cheaper building elements with a shorter service life | no change in quantities, different renewal cycles | Running costs under DIN 18960 | ETICS instead of brick: about 100,000 € less to build; the gap in present value depends on the maintenance costs |
Two rows break the pattern. The foundations are not a free decision but a consequence of the ground; the lever lies in knowing it early. And the last row does not reduce construction costs but tests whether a saving on construction costs becomes more expensive later.
Compactness and number of storeys
The envelope of a building is among its most expensive elements, and its quantity is created with the first sketch. On the example project, four setbacks each 2 m deep increase the external wall area from about 1,070 to 1,260 m², with floor area and living area unchanged. The number of storeys also shifts the quantities: with three storeys instead of four the roof area grows, with five storeys it shrinks, and at certain building heights requirements of the state building code are added. The article Compactness and the surface-to-volume ratio: how facade area and number of storeys determine construction costs works through five variants with external wall, roof and surface-to-volume ratio.
Basement and parking
In the example project, the underground car park is the largest single item that can be changed by a single decision. It brings excavation, waterproofing, ramp, ventilation and fire protection with it, and it counts in full towards the gross floor area. How many parking spaces have to be provided at all, and whether a commuted payment is possible, is governed by state law, often through a municipal bylaw; in Bavaria, for example, parking spaces only have to be built under Art. 47(1) BayBO if the municipality has required this by bylaw. The article Underground or surface parking: the cost per space and what it sets off compares the solutions per space and shows what the underground car park means for the grid of the upper floors.
Grid and structure
A dwelling plan and an underground car park follow different grids. If they are not coordinated early, walls of the upper floors have to be picked up above the basement, with transfer beams or strengthened slabs that are contained in no benchmark. Spans, slab thicknesses and the choice between shear walls and columns work in the same direction. The article Grid and structure: spans and transfer structures as cost drivers in KG 300 compares a continuous grid and a transfer structure on the example project.
Ground and foundations
The ground is the greatest unknown of preliminary design. As long as there is no Baugrundgutachten (geotechnical report), cost group 320 rests on an assumption, and cost group 310 depends on the groundwater level. The HOAI lists geotechnics as an advisory service whose basic services include, among other things, a recommendation for the foundations and advice on keeping the excavation dry (Annex 1, no. 1.3). The article Ground and foundations: what the geotechnical report changes in the budget explains when the report should be commissioned and what contingency should be shown until then.
Facade
With about 1,070 m² of external wall, of which about 800 m² is solid wall, every difference in the price per square metre of the facade system acts on these 800 m². The comparison between an external thermal insulation composite system, a facing brick outer leaf, a ventilated timber facade and a curtain wall is therefore a decision of preliminary design and not a question of materials at execution stage. Added to this are the window proportion, fire protection requirements according to the building class and the cost of upkeep. The article Facade costs per m²: ETICS, brick, timber, curtain wall compares the systems on the same area.
Life cycle
Not every saving on construction costs is one. A building element that is cheaper to build and has to be renewed after half its service life shifts costs into the use phase, and who bears them depends on whether the client sells or holds. For these running costs in building construction, DIN 18960 is a separate standard alongside DIN 276. The article False economies: what lowers construction costs and raises running costs shows how construction and running costs are compared on one line.
The order of the decisions
The six decisions depend on one another, and their order is not arbitrary. Anyone who chooses the facade before the massing is settled is optimising an area that is still changing. Anyone who fixes the grid of the dwellings before the parking concept is clear creates the transfer structure that they later pay dearly for.
| Step | Decision | Why at this point |
|---|---|---|
| 1 | Parking concept and basement | determines excavation, foundation area and the grid of the basement |
| 2 | Massing and number of storeys | determines envelope area, roof area and building class |
| 3 | Grid and structure | coordinates the dwelling grid and the basement |
| in parallel from step 1 | Investigate the ground | under Annex 14 HOAI the type of foundation belongs to preliminary design |
| 4 | Facade system | acts on the external wall area, now settled |
| across all steps | Check the life cycle | test every saving for its follow-on costs before it is adopted |
The ground investigation does not stand in the sequence but alongside it. It takes time, and its result can overturn step 1: a high groundwater level fundamentally changes the calculation for the underground car park. Anyone who commissions the report only after the design learns this at a point when the basement has already been drawn.
What a saving is and what it is not
Anyone who wants to reduce construction costs has to keep two things apart: a cost statement falls either because the building changes or because the figure changes. Only the first is a saving. Anyone who lowers a unit price in the cost estimate without any change in quantity, quality or construction pushes the difference into the tender stage, where it comes back with interest. The article Cost management: intervening rather than recalculating describes this principle in detail.
For the early phase, a second distinction follows. A decision that reduces quantity acts on all the prices attached to that quantity: less external wall saves insulation, render, scaffolding and windows at once. A decision that only lowers the standard acts on a single item and is often reversed later, because in the end the client wants the standard after all. The six decisions in this guide are therefore mainly decisions about quantity.
A saving also has its price. Every variant examined beyond the basic services can generate design work; the HOAI, for example, lists "examining alternative approaches against different requirements, including cost assessment" as a Besondere Leistung (additional service) of work phase 2. And if a design that has already been settled is changed on the client's instruction, the fee under section 650q(2) BGB follows the fee calculation rules of the HOAI, insofar as the services are covered by it. In preliminary design this price is at its lowest.
When the figure is already too high
This guide assumes that the decisions are still open. If the cost calculation of work phase 3 is already above budget, the situation is different: it is then a matter of diagnosis, decision paper and the fee consequences of a redesign. Separate articles cover this:
- Setting the budget before design starts: what information the budget needs, against which the variants in this guide are measured.
- The cost calculation exceeds the budget: deciding before tendering: separating the causes and testing the levers in the right order.
- Preparing the decision paper on a budget overrun: assessing savings potential on a comparable basis and recording the decision.
The three articles describe the second chance. This guide describes the first, which is cheaper because no contracts, no detailed design and no tenders yet depend on it.
Sources: gesetze-im-internet.de, HOAI, Annex 10 (no. 10.1, LPH 2 and 3), Annex 14 (no. 14.1, LPH 2) and Annex 1 (no. 1.3) · gesetze-im-internet.de, BGB, section 650p(2) and section 650q(2) · gesetze-bayern.de, BayBO, Art. 47(1) · DIN Media, DIN 276:2018-12, DIN 277:2021-08 and DIN 18960:2020-11 (title and scope). Checked on 26 November 2026. Prices given as examples, established in November 2026 from public references: ARGE//eV, Wohnungsbau-Tag 2026, Wohnungsbau in Deutschland 2024, Bezahlbarer Wohnraum 2021 and Vergleich verschiedener Bauweisen im Wohnungsbau 2016; VFF and Bundesverband Flachglas, Fensterstudie 2024; Destatis, Baupreisindex für Wohngebäude 2026.