Grid and structure: spans and transfer structures as cost drivers in KG 300

📐 Topic

By , construction economist

9 min read

What this article covers Why the dwelling grid and the car park grid have to be coordinated in preliminary design, what a transfer structure above the basement sets off, and how span and slab thickness can cancel each other out. Also, which decisions the structural engineer already owes in preliminary design under the HOAI, and what role cantilevers play. The structure is the part of cost group 300 that is least often discussed in preliminary design, because it remains invisible. Yet that is exactly where grid, spans and load paths are fixed. This article belongs to the guide Reducing construction costs in Germany: the decisions that fix costs at design stage; the breakdown of cost group 300 itself is explained in the article on KG 300 building fabric.

What the HOAI requires in preliminary design

The HOAI (the German fee scale for architects and engineers) expressly places the structural decision in work phase 2. Under Annex 14, the basic services of structural design include contributing to the preparation of a design concept "including examination of the possible structural solutions" (unofficial translation, as are all quotations in this article) with a statement of the main structural decisions, which are stated to include, among other things, materials, types of construction and "structural grid and type of foundation". Contributing to the cost estimate is added to this.

The structural engineer, on the other hand, only determines quantities later. Approximate determination of reinforcing steel quantities in reinforced concrete construction belongs to work phase 3 under Annex 14, and comparative calculations for several possible solutions under different project conditions are a Besondere Leistung (additional service) in work phase 2. For the client this means: anyone who wants grid variants compared with quantities should commission this service expressly, rather than assume it is included in the basic services.

The example project and its two grids

The calculation uses the guide's example project: an apartment building with 24 dwellings, four full storeys and about 2,200 m² of gross floor area under DIN 277, building 32.0 × 12.5 m, with an underground car park for 24 spaces beneath. The structure is assumed to be reinforced concrete, with loadbearing cross walls on the upper floors and columns in the car park. The amounts are example values, and the slab thicknesses are assumptions of the example that a structural engineer has to confirm for the actual project.

The underground car park has its own grid. Three parking spaces each 2.50 m wide and one column give an axis spacing of about 8.0 m, and four such bays fill the building length of 32 m. The dwellings on the upper floors, by contrast, follow the floor plan, and the plan places the loadbearing party walls where the dwelling sizes require them.

Three variants

Variant Grid of upper floors Car park grid Slab span Transfer structure above the basement
A: coordinated Cross walls every 8.0 m (4 bays) 8.0 m 8.0 m none
B: not coordinated Cross walls every 6.4 m (5 bays) 8.0 m 6.4 m 4 cross walls of 12.5 m each, 50 m in total
C: frame Flat slab on columns 8.0 × 6.25 m 8.0 m 8.0 m and 6.25 m none, partitions non-loadbearing

In variant B the cross walls of the upper floors meet the basement at 6.4 m, 12.8 m, 19.2 m and 25.6 m, while the column lines of the car park lie at 8 m, 16 m and 24 m. Not a single cross wall stands over a column line. All four therefore have to be picked up above the basement, by transfer beams, deep wall beams on the ground floor or a substantially strengthened slab over the basement.

Span against transfer structure

Variant A avoids the transfer structure but pays for it with longer spans. The slabs span 8.0 m instead of 6.4 m and become thicker. Assuming for the example a slab thickness of 24 cm instead of 20 cm, four slabs of 400 m² each between the storeys and under the roof give about 1,600 m² of slab area and therefore about 64 m³ more concrete, plus more reinforcement and more dead load on walls and foundations. The slab over the basement spans across the car park grid in both variants; its strengthening in variant B appears in the transfer structure row.

Item Variant A compared with B Cost group Difference (example)
Slab concrete +64 m³ KG 350 Additional cost
Transfer structure above the basement −50 m of transfer structure KG 340, KG 350 Lower cost
Cross walls, upper floors one cross wall fewer per storey KG 340 Lower cost
Balance KG 300 depends on the unit prices

The table shows what matters: the two variants differ in three items that work in opposite directions. Which is cheaper depends on the unit prices and on the extent of the transfer structure. The only clear point is that variant B carries its transfer structure not out of necessity, but because two grids were drawn independently of each other.

The transfer structure also has consequences that do not appear in the table. Transfer beams need structural depth, and that is lost either to the car park or to the ground floor; when in doubt the basement gets deeper, and with it the excavation and the ramp. They also concentrate loads on a few columns, which strengthens the foundations at those points.

What variant C changes

A frame of flat slabs and columns solves the grid problem fundamentally, because the columns of the upper floors stand on those of the car park. The party walls between dwellings become non-loadbearing, and the floor plans can be changed later. In return, the party walls need a build-up of their own that meets the sound insulation requirements between dwellings, and the slabs span in two directions across bays of 8.0 × 6.25 m.

For the cost comparison, variant C is therefore not a pure comparison of structures. It shifts costs from the structure into the internal walls of cost group 340, and it creates a benefit that does not appear in the construction costs: flexibility for a later change of use. Whether this benefit justifies a higher price is a question for the client, not for the cost estimate.

Cantilevers and balconies

Cantilevered elements are the second typical structural decision of preliminary design. A cantilevered storey, a loggia with an open corner or a cantilevered balcony brings bending moments, greater element thicknesses and thermal breaks between inside and outside. A balcony standing on its own columns in front of the facade, by contrast, needs its own foundations but relieves the slab and the facade.

On the example project, with 24 dwellings and one balcony each, the question is not a matter of detail. Every solution is repeated 24 times, and the difference per balcony is multiplied by that factor. It therefore belongs in the cost estimate as a line of its own with a number of units, not as a lump sum in the slab benchmark.

Method and material of construction

The choice between reinforced concrete, masonry, timber and hybrid construction is a separate decision that overlaps with the grid. For halls, the article Hall construction methods compared: steel, concrete and timber compares the methods; in housing, sound insulation, fire protection according to the building class and construction time come in as additional criteria. What share of building costs the shell accounts for, and how the shares should be read, is described in the article Shell and fit-out: cost shares within building cost.

The same rule applies to the comparison of variants as to the grid. A method of construction is only cheaper if it is compared with the same grid, the same building class and the same requirements for sound insulation and fire protection. Anyone who sets a timber variant with thinner walls against a concrete variant with a different floor plan is comparing two designs, not two methods of construction.

What belongs in preliminary design

The structure should not disappear into a lump sum in the cost estimate. To prevent this, preliminary design should expressly record a few points:

  1. Grid of the upper floors and grid of the basement, shown one above the other.
  2. Position and length of every transfer structure, with the principle chosen.
  3. Slab spans and assumed slab thicknesses for each variant.
  4. Number and type of cantilevers.
  5. The variant the structural engineer recommends, and whether comparative calculations have been commissioned as an additional service.

With this information, every deviation in the later cost calculation can be attributed to a cause. Without it, the transfer structure appears in the cost calculation as an increase in quantity that nobody can explain.

Sources: gesetze-im-internet.de, HOAI, Annex 14 (no. 14.1, LPH 2 and 3) · DIN Media, DIN 276:2018-12 and DIN 277:2021-08 (title and scope). Checked on 26 November 2026. The amounts are example values, the slab thicknesses assumptions of the example.

Frequently asked questions

The structure is spread across several cost groups of KG 300, above all foundations, walls and slabs, and therefore cannot be expressed as a single benchmark. Comparing variants in quantities is more telling: slab concrete, wall lengths, length of transfer structures.

No. Longer spans make the slabs thicker, but they can save walls and transfer structures. On the example project, a thicker slab is set against a 50 m transfer structure above the underground car park.

In preliminary design. In Annex 14, the HOAI expressly names the structural grid among the main structural decisions of work phase 2 of structural design.

Under Annex 14 HOAI, preparing comparative calculations for several possible solutions under different project conditions is an additional service in work phase 2. It should be agreed if variants are to be compared with quantities.