The cost and programme of a renovation

📐 Topic5 min read

What you will learn Why renovation is harder to estimate, what affects the cost, why a rate per square metre misleads, and what to allow for in the programme.

The cost of new construction can be estimated from the drawings. The cost of a renovation depends on what is inside the wall, and nobody knows that before the wall is opened.

1. Why renovation is harder to estimate

Three structural reasons, and the third is decisive for apartment buildings. It concerns the actual condition of the building.

The initial situation is not fully known, unlike new construction where everything has been designed. The work is carried out on the terms of the existing structure rather than in ideal conditions. And the building is usually in use, which limits the organisation and lengthens the time, as covered by the article on living in the building during works.

The first two mean that part of the cost only emerges as the work proceeds, as covered by the article on unforeseen circumstances. A contingency has to be built into the budget.

2. What affects the cost

Four factors of different character, and the fourth is the most often left out of the discussion. It concerns later running costs.

Factor What it determines
The building's present condition how much preparatory work is needed
The required class gain the volume of work
The shape and size of the building on a smaller building the fixed costs spread over less area
The organisation and duration of construction site costs

The fourth is dealt with separately by the standard on the classification of construction costs and is explained in the budgeting guide: site-related costs depend on the organisation and the duration rather than on the design solution. Shortening or lengthening the programme therefore changes the cost even where the works are the same.

3. Why a rate per square metre misleads

Three reasons apply more strongly in renovation than in new construction, and the third is decisive in support terms. It concerns residents being in occupation.

The same rate per square metre may cover very different volumes of work, depending on the initial condition. A rate per square metre does not include unforeseen circumstances, which are the rule in renovation. And a rate per square metre does not say what class gain it achieves.

A cheaper rate per square metre that does not reach the required class is not cheaper but useless. Orders of magnitude for construction cost and price indices are covered in a separate guide, which also explains why the Estonian renovation index does not cover residential buildings. This guide states no rates per square metre, because they depend on the initial condition more than on anything else.

4. What to allow for in the programme

Four stages, of which only one is construction. The other three together last longer.

Stage Note
Preparation and decision covered in a separate branch
Application and funding decision the duration depends on the round
Procurement and contracts
Construction and final measurements the measurement protocols must be planned into the programme

The required measurement protocols are covered by the article on the full package. Seasonality is a separate factor in Estonia, since facade works are not carried out in winter on the same terms, and this affects both the programme and the price.

Summary and four practical rules

Renovation is harder to forecast for three structural reasons: the initial situation is not fully known, the work is done on the terms of the existing structure, and the building is usually in use. Four factors affect the cost, of which the organisation and duration of construction are the most often left out of the discussion, even though changing the programme changes the price for the same works. A rate per square metre misleads because it does not say what class gain it achieves, and a cheap solution that does not cross the threshold is useless.

Four rules: do not judge a renovation by its rate per square metre. Ask what class gain the price achieves, not only what the price is. Allow for the effect of the programme on the cost, not only the volume of works. Plan the final measurements and seasonality into the programme from the start.

This article offers professional orientation as at the date of verification. It is not a quotation.

Frequently asked questions

For three structural reasons, the decisive one for apartment buildings being the actual condition of the building. Part of the cost emerges only as the work proceeds, so the budget needs a contingency.

Four factors of different character, and the one most often left out of the discussion is later running cost. It affects the real cost year after year.

For three reasons that apply more strongly here, the third being that residents remain in occupation. The work is carried out in an occupied building, which limits working hours and sequence.

Four stages, of which only one is construction. The other three, deciding, preparing and designing, usually last longer together.