Checking the design team's cost estimate

📐 Topic

By , construction economist

Information verified on 7 min read

What you will learn Which cost figure the design delivers at each stage and what each one is worth, the three checks the client should make before accepting an estimate, the role of an independent counter-estimate, and the four articles in this branch.

The design estimate, the presupuesto del proyecto, is not a figure the client receives and files away. It changes in nature at every stage, and it is only useful for decision-making if it is compared with the client's budget on the same scope, the same price date and the same items. This branch, the second of the guide to construction budget control for the client, covers that check, from the proyecto básico (basic design) to the proyecto de ejecución (detailed design).

A different figure at each stage

The first trap is to read as a price what is only a valuation. The Código Técnico de la Edificación (the Technical Building Code, Royal Decree 314/2006, art. 6) provides that the proyecto básico "shall define the general characteristics of the works" (unofficial translation) and is enough to apply for the building licence, but not to build; the proyecto de ejecución develops it. The cost figure follows the same path: approximate at the start, detailed at the end. For the proyecto básico, Annex I of the CTE, as worded by Royal Decree 173/2010, requires at least an approximate budget, that is, an "approximate valuation of the material execution of the designed works, by trade section".

Stage Cost figure What it is for What it is not for
Preliminary studies and outline design (estudios previos, anteproyecto) whatever the appointment asks for validating the order of magnitude of the brief committing the budget
Proyecto básico approximate budget of the net works cost applying for the licence, first comparison with the budget contracting the works
Proyecto de ejecución itemised quantities and a detailed budget by trade section obtaining comparable bids, setting the contract budget knowing the total development cost
Public works budget with unit prices, price breakdowns and schedule of quantities (LCSP art. 233.1.d) underpinning the base tender budget replacing the review of the design

The content of each document is described in the articles on the basic design and on the detailed design in the guide to project phases. Here, only the effect on the budget matters. None of these figures is the total cost: fees, licences, insurance, utility connections, financing and VAT (IVA) are added by the client in its own budget.

Three checks before accepting an estimate

Comparing two figures that do not measure the same thing produces false reassurance or a false alarm. Before discussing the amount, the client checks three things.

The scope. What does the design estimate include? Internal site works, demolition, fixed furniture, special installations, provisional sums still to be defined. Every exclusion should be written down.

The price date. An estimate prepared with prices from a year ago cannot be compared with a client budget set this month. Ask for the date of the prices and the database they come from.

The structure. The trade sections of the design estimate must be readable against the items in the client's budget: if one works by trade sections and the other by major building systems, the difference cannot be located. It is worth setting a common structure in the appointment and keeping it from one stage to the next.

Once the three checks are done, the difference that remains is real and has a cause: brief, specifications, quantities or prices. The brief and the specifications come down to a decision of the client; quantities and prices are discussed with the designer.

The independent counter-estimate

When the figure is decisive, it is tested against an estimate made by someone else. This is not about redoing the design, but about pricing the same documents with one's own measurements and prices, to see where they diverge. The method is simple: same scope, same price date, same structure of trade sections, and a list of the assumptions made where the design does not define them.

What weighs most is usually the measurement, not the price. A quantity forgotten or counted twice in a major trade section moves the result more than a difference in unit price. The usual mistakes are reviewed in the article on quantity take-off errors. The best time to commission the independent counter-estimate is before each stage is closed, above all at the end of the proyecto básico and before going out to tender.

Who decides

The decision on the budget belongs to the promotor (the client). Law 38/1999 on Building Regulation (Ley de Ordenación de la Edificación, LOE) defines the promotor as the person who "decides, drives, plans and finances" the works (art. 9.1), and the designer works "on the instructions of the promotor" (art. 10.1). No text makes the architect the keeper of the client's budget: what is required of the architect on cost depends on the appointment. That is why every deliverable should come with its cost figure compared in writing with the budget, and every deviation with a signed decision.

The articles in this branch

This article describes the state of the rules on the date of verification and is intended as professional guidance. It does not replace legal advice or an examination of the specific case.

Frequently asked questions

No. It is an approximate valuation of the net works cost that accompanies the licence application. Comparable bids require the measurements and detailed budget of the proyecto de ejecución.

Generally not: it refers to the net works cost or, at most, to the contract price. Fees, licences, financing and VAT are added by the client in its own budget.

When the figure decides feasibility or financing, and above all at the close of the proyecto básico and before going out to tender. It is carried out on the same documents, with the same scope and the same price date, to see where the figures diverge.

The texts reviewed do not contain such a general obligation; it depends on what was agreed in the appointment. Hence the importance of writing the budget, its date and its tolerance into the contract.