Hotel construction cost in Spain: per room and per m²

📐 Article

By , construction economist

Information verified on 8 min read

The hotel is the commercial typology with a double ratio system: the construction sector reasons per m², operators and investors reason per room. Both are necessary and both require the scope to be specified, in particular the treatment of FF&E, the furniture and operating equipment that can represent a very significant fraction of total investment.

2026 ranges by category

In PEM (direct works budget) per built m², finished building excluding full FF&E, mid-cost area:

Category Indicative PEM 2026 Order of magnitude per room
Budget hotel and 2 stars €1,100 – 1,500/m² €60,000 – 90,000
3-star hotel €1,400 – 1,900/m² €90,000 – 140,000
4-star hotel €1,700 – 2,200/m² €130,000 – 200,000
5-star and luxury €2,200/m² and above €200,000 and above

The per-room ratio is built on the hotel's total floor area divided by the number of keys, so it incorporates all common areas; this is why it grows faster than the per-m² ratio as the category rises: a 5-star hotel does not only have more expensive finishes, it has many more m² of restaurants, spa and services per room. For that reason the two magnitudes should be presented together and never one in place of the other.

The items specific to hotel use

Catering installations. Professional kitchens, cold rooms, extraction and staff areas form a dense technical block that exists neither in offices nor in housing, with ratios well above the building's average.

Sound insulation. Acoustic insulation between rooms and against common areas is an operator requirement as much as a regulatory one, and it affects partitions, doors, services and joinery.

Serial wet rooms. A full bathroom per room concentrates plumbing, waterproofing and finishes in repetitive cycles: industrialisation (prefabricated bathroom pods) is a real cost and schedule lever in hotels.

FF&E and OS&E. Furniture, equipment and operating supplies are budgeted separately from the works and are usually procured by the operator or to its standards. In compared budgets, always check whether the figures include them: it is the first cause of apparent deviations between hotel projects.

The weight of common areas. The proportion between room area and total area (usually between 55 and 70 % depending on category) is the design parameter that most conditions the per-key ratio.

The operator's reading

Operators assess investment per room against expected revenue per available room. For cost analysis, this has a practical consequence: project trade-offs are negotiated in terms of brand standards (minimum room sizes, finish levels, service programme), and the cost consultant preparing or analysing hotel budgets needs the operator's standards manual as much as the bill of quantities. Conversions of existing buildings to hotels follow the logic of full renovation, with acoustic and services upgrading as the dominant items.

The essentials

A hotel sits in 2026 between €1,400 and €1,900/m² PEM at 3 stars and from €2,200/m² in the upper segment, with per-room ratios from €90,000 to over €200,000 depending on category. Figures are only comparable with three clarifications: FF&E included or not, proportion of common areas, and level in the budget chain as per from PEM to total cost.

Note: indicative ranges for Spain in 2026, variable by region, project and market.

Frequently asked questions

Between €60,000 and €90,000 per key in budget and 2 star categories, €90,000 to €140,000 at 3 star, €130,000 to €200,000 at 4 star, and above €200,000 at 5 star and luxury.

Because it absorbs the common areas. A 5 star hotel does not merely have more expensive finishes: it has far more m² of restaurants, spa and services for each room.

They do not include full FF&E, meaning furniture, fittings and operating equipment. That chapter is budgeted separately and its amount depends on the brand and positioning.

Kitchens and production areas, hot water systems sized for intensive occupancy, acoustic treatment between rooms, and spa and wellness areas.