Blog

Contract modifications and new rates in Spanish public works

📐 Article7 min read

What you will learn in this article

  • The exhaustive grounds on which a Spanish public works contract may be modified and their quantitative limits.
  • When a modification is mandatory for the contractor and when it can be refused.
  • How prices for new work items are set and why proceeding without approval creates no right to payment.

BlogPublic works tenders in SpainExecuting a public works contract › Contract modifications and new rates

This article approaches modifications from their legal regime in public procurement: what the LCSP allows, within what limits and through what procedure. The financial mechanics of change orders (how they are valued, documented and absorbed into the budget) are common to public and private works and are developed in the articles on change orders and new rates; what matters here is what public law adds: the prerogative, the caps and the consequences of skipping them.

The starting point: the contract is performed as signed

Spanish public contracting rests on the contractor's risk and fortune principle and on the immutability of the bargain: what was tendered is what gets built, because every later modification alters the conditions under which the other bidders competed (and lost). That is why the LCSP does not regulate modifications as a matter between the parties but as an administrative prerogative, exhaustively listed and controlled: only the administration can modify, only on the legal grounds and through a formal procedure.

The two modification routes and their limits

The law distinguishes according to whether the modification was announced from the start:

Route Requirements Quantitative limit
Modifications provided for in the documents A clear, precise and unequivocal clause: cases, scope and procedure Up to 20% of the initial price
Unforeseen modifications: additional works Necessary, where changing contractor is impossible or seriously inconvenient Up to 50% of the initial price, alone or combined
Unforeseen modifications: unforeseeable circumstances Supervening and unforeseeable with due diligence, without altering the overall nature Up to 50% of the initial price
Non-substantial modifications Not altering the essential conditions of the tender Per their justification

The most important operational threshold is another one: a modification approved by the administration is mandatory for the contractor when it does not exceed 20 per cent of the initial price. Above that, the contractor may accept it or not; if not, the contract is terminated without fault on either side. That 20 per cent is, in practice, the line separating an order from a negotiation.

In works contracts, the law adds a specific valve: measurement excess, the variation in the number of units actually executed against those foreseen, is not treated as a modification if it stays within 10 per cent of the initial price, and is settled directly in the final certificate. It is the legal acknowledgement that no design measures with perfect accuracy.

New rates: items missing from the price schedule

Where the modification introduces work items absent from the contract's price schedule, their price is set through the new rate procedure (precio contradictorio): the supervising team proposes the new rate from the design's elementary costs and market prices, the contractor states its position in a hearing and, failing agreement, the contracting authority sets it, the contractor's right to claim remaining intact. New rates incorporate the award discount: the new item is paid with the same coefficient as the rest of the contract, a rule worth remembering before accepting optimistic build-ups. The decomposition and negotiation technique for these rates is developed in the article on new rates.

Proceeding without approval: the mistake that never gets paid

The golden rule of public works execution: no modified work is executed without prior approval. Verbal instructions from the supervising team, site urgencies, trust that "it will be regularised later" all lead to the same place: works executed without contractual cover whose payment the administration cannot approve, because doing so would validate an unlawful modification. Case law exceptionally admits compensation for unjust enrichment, but that is a years-long lawsuit with an uncertain outcome, not a collection route.

The contractor's protection is documentary and preventive: faced with an instruction altering the design, request its formalisation in writing; faced with refusal, record it in the order book or in minutes; and under schedule pressure, remember that formally suspending the affected work front (with its minutes and compensation effects) protects, while voluntarist execution does not. Each of those steps costs minutes and later sustains the whole position.

How a modification is processed, step by step

The formal procedure is the border between a valid modification and the unpaid de facto route, and its stations are worth knowing: a technical report from the supervising team justifying the legal ground and quantifying the proposal; a hearing for the contractor, which is the moment to dispute quantities and new rates in writing; legal and expenditure control reports; approval by the contracting authority; readjustment of the performance guarantee in proportion to the new price, which is a condition of effectiveness; signature and publication on the contracting profile. Skipping any of those stations turns the modification into unpaid work.

Two practical consequences of that circuit. The first is calendar: a serious modification takes weeks or months to travel it, and that time must be managed with the correct mechanism (documented partial suspension of the affected work fronts, reprogramming of the rest), not with anticipated execution. The second is documentary strategy: the contractor's hearing is the only station where the company speaks in the file; the observations submitted there (on quantities, rates or added time) are the ones that will exist later, in the final certificate or before a tribunal. What was not raised at the hearing is much harder to resurrect.

Worked example: the same modification on both sides of 20 per cent

A project with an initial price of EUR 1,500,000 hits ground worse than the geotechnical study predicted. The supervising team prices the necessary foundation reinforcement at EUR 270,000: 18 per cent. Staying below 20 per cent, once the modification is approved on unforeseeable circumstances grounds, the contractor is obliged to execute it at the resulting prices (schedule prices and, for new items, new rates with the discount applied).

Had the pricing reached EUR 330,000 (22 per cent), the scenario changes: the contractor may accept or seek termination without penalty. That four-point difference turns the critical review of the modification's valuation (are the new items properly measured? do the new rates reflect real costs?) into negotiating leverage: accepting a badly valued 22 per cent modification is voluntary; executing a well valued 18 per cent one, mandatory.

Note: the percentages and references cited reflect Spanish legislation in force in 2026 (Ley 9/2017, articles 203 to 207 and 242). Always check the documents and regime applicable to each specific contract.

Frequently asked questions

Only if it exceeds 20 per cent of the initial price. Below that threshold, a duly approved modification is mandatory, without prejudice to disputing its valuation through administrative channels.

If the affected part of the works cannot continue, the formal suspension of that part applies, documented in minutes, generating a right to the legally defined damages. Continuing to execute what is not approved "so as not to stop" is exactly the unpaid de facto route.

Yes: they are published on the contracting profile with their justification. A competitor who considers that the modification masks a substantial alteration of the contract (which would have required a new tender) can challenge it, including through the special procurement review for contracts within its scope.

Public works tenders in Spain: Ley 9/2017, procedures and award