The open and simplified open procedures in Spain

📐 Article⏱ 7 min read

What you will learn in this article

  • How the ordinary open procedure runs and what its deadlines are.
  • The requirements of the simplified open procedure: value limits, ROLECE registration and criteria caps.
  • What changes in bidding practice between the two.

Blog › Public works tenders in Spain › Procurement procedures › The open and simplified open procedures in Spain

The vast majority of Spanish public works are awarded through the open procedure, either in its ordinary form or in the simplified version of article 159 of the LCSP. For bidders, mastering these two routes means mastering the market: the remaining procedures are statistically marginal in works.

The ordinary open procedure: maximum competition, maximum formality

In the open procedure, any interested company may submit a bid directly, with no prior selection stage. The sequence is linear: notice on the contracting profile (and in the OJEU if the contract is SARA), submission period, opening and scoring by the evaluation committee, request to the top-ranked bidder and award.

Minimum submission periods for works are 26 calendar days from publication for below-threshold contracts and 35 days from dispatch of the notice to the OJEU for SARA contracts. Documentation is organised into separate electronic envelopes: supporting documents (usually replaced by the self-declaration of the European Single Procurement Document), judgement-based criteria and automatic criteria. Opening follows that order to preserve the objectivity of the evaluation.

The ordinary open procedure admits contracts of any value and any combination of criteria. It is the default route for large works and for all SARA contracts.

The simplified open procedure: the workhorse of mid-sized works

The simplified open procedure of article 159 was created to speed up mid-value procurement and has become the star procedure of local public works. Its conditions of use in works contracts:

Condition Rule
Estimated value Up to EUR 2,000,000
Judgement-based criteria Maximum 25% of the score
Bidder registration Mandatory in ROLECE (or the equivalent regional register)
Minimum submission period 20 calendar days
Bid guarantee Not allowed

The simplifications are tangible. Documentary proof is replaced by registration in the ROLECE (Registro Oficial de Licitadores y Empresas Clasificadas, the official register of bidders and classified companies): the committee consults the register instead of requesting papers. Scoring is concentrated into one or two sessions, with automatic criteria at the centre. And the bid guarantee is excluded by law.

ROLECE registration deserves emphasis: it is an admission requirement, not a later formality. The registration application must be filed before the bid deadline expires, and an unregistered company risks exclusion. For any contractor aiming to bid regularly, registering (and keeping classification data and powers of attorney up to date) is a task to complete before any specific tender.

The super-simplified route: the express lane

Within article 159, paragraph 6 regulates an even faster variant, the so-called super-simplified open procedure, for works with an estimated value below EUR 80,000: a submission period of only 10 working days, exclusively automatic criteria, no proof of standing and no performance guarantee. It is a regime designed for small municipal works and has its own bidding logic, developed in the article on the super-simplified procedure.

What changes in bidding practice

Between the ordinary and the simplified open procedures, the operational difference for bidders comes down to three points. All three affect the calendar and the documentary load of the bid.

The calendar. Twenty calendar days (which in August or December shrink to little more than two working weeks) demand a fast decision loop: early detection of the notice, go/no-go within 48 hours, cost study running in parallel with the technical submission.

The weight of price. With judgement-based criteria capped at 25 per cent, the simplified procedure is dominated by automatic criteria. The price scoring formula and the abnormality threshold are the heart of the analysis; the technical submission, where there is one, is short and must answer the sub-criteria surgically. Formulas are covered in the article on award criteria.

Formal risk. The speed of the procedure does not forgive defects: a badly completed bid form, an offer submitted outside the designated electronic tool, unproven registration. In the simplified procedure, most exclusions are formal, not technical.

Worked example: 20 counted days, day by day

A town council publishes on a Friday the notice for refurbishing a municipal market: EUR 1,640,000 estimated value, simplified open procedure, 20 calendar days, 75 automatic points (price and warranty extension) and 25 judgement-based (construction method statement). The real calendar of the company that wins:

Days Action
1 to 2 Platform alert received the same Friday; go/no-go on Monday with the first pass through the documents
3 to 5 Quotation requests to key subcontractors; verification of the quantities of the dominant items
6 to 12 Full cost study; technical submission drafted against the documents' sub-criteria
13 to 14 Discount simulation against the council's track record; discount decision by management
15 to 17 Documentary close-out: bid form, ESPD, ROLECE check
18 Electronic submission (the day before the deadline)
19 to 20 Safety margin for incidents

Two details win the file: the alert configured by CPV code allows starting on day 1 rather than day 6, and the ROLECE check in the first week uncovers an expired power of attorney in time to renew it. The same bid prepared with late detection would have arrived with the documentation barely ready and no simulation margin.

Opening in the simplified procedure: fewer acts, more speed

The simplified procedure's compression shows especially in the evaluation phase. When all criteria are automatic, opening and scoring can be resolved in a single act: the committee opens, applies the formulas and issues the award proposal in the same session. When judgement-based criteria exist (capped, remember, at 25 per cent), the mechanics keep two stages (qualitative scoring first, financial opening after), but with fixed internal deadlines so the file does not stall.

For bidders, that speed has two practical consequences. First: file monitoring must be weekly, because only a few days may pass between opening and the documentation request, and the request runs on a deadline. Second: committee errors (a misapplied formula, an admitted bid that should have been excluded) are spotted by reading the minutes published on the profile, and the window to react is short. The discipline of downloading and reviewing every set of minutes on its publication day is the difference between being able to challenge and finding out too late.

Note: the amounts, deadlines and references cited reflect Spanish legislation in force in 2026 (Ley 9/2017). Always check the documents of each specific tender.

Frequently asked questions

The consolidated position admits the bid where the registration application was filed before the bid deadline expired, attaching the receipt. It is a safety net, not a strategy: effective registration remains required for award, and an incomplete application offers no protection.

No: the law expressly excludes it in this procedure. The 5 per cent performance guarantee remains payable by the awardee, except in the super-simplified variant, which does not require it either.

Not below the legal minimum, but counting on more is unwise: most authorities publish with the bare minimum. The 20 days are calendar days, so a notice published before a long weekend or in August leaves even fewer real working days.

← Public works tenders in Spain: Ley 9/2017, procedures and award