📐 Article7 min read

Inside the breakdown live two discreet pieces that decide more than they appear to: the output, which governs labour cost, and auxiliary prices, which avoid repeating the same compositions a thousand times. This article fixes what they are, where they come from and how they are adjusted.

The output: the decisive multiplier

The output expresses the hours of each trade grade needed per unit of work. Its effect is direct: in labour-intensive items (partitions, coverings, building services), 20 % variations in output move the price more than any materials negotiation.

The outputs published by databases assume average conditions: a clear site, normal series, accessible work areas. Real conditions correct in both directions:

Condition Typical effect on output
Occupied renovation or fragmented work areas Noticeable penalty: more hours per unit
Working heights, difficult access Penalty through equipment and travel
Long, repetitive series Improvement: the learning curve reduces hours
Prefabrication and industrialisation Moves hours from site to workshop: it changes the structure, not just the number

Professional adjustment is not a uniform percentage across the whole budget but a directed correction to the item families affected by each condition. And the best source of outputs remains the in-house history: timesheets from comparable projects are worth more than any published table.

Auxiliary prices: the reusable pieces

An auxiliary price is an intermediate composition (a mortar, a grout, a levelling paste) that enters as a component in many breakdowns. Its function is coherence and maintenance: the mortar is defined once, with its materials and mixing, and every breakdown using it inherits any update.

The associated discipline is simple: auxiliaries are updated in their single definition, never patch by patch in each item, and their components (cement, sand, water, and the fabrication labour where applicable) follow the same adaptation rules as the rest of the system. An auxiliary patched in one item and not the others produces prices inconsistent across chapters.

The hourly cost: the product's other half

The output multiplies an hourly cost per grade (first-grade officer, second-grade, labourer), and that cost comes from the applicable provincial collective agreement plus the associated employer costs. Two checks avoid systematic errors: the agreement's consistency with the project's province, and updating to the current year, because agreements are revised and databases can run a year behind.

The essentials

The output decides the price of labour-intensive items and is adjusted for execution conditions, family by family, with the in-house history as the best source. Auxiliaries give the system coherence provided they are maintained in their single definition. And the hourly cost is anchored to the current provincial agreement. With those three pieces calibrated, the breakdown stops being a template and starts describing the real project.

Note: usual practices in Spain in 2026; agreements and hourly costs vary by province and year.

Frequently asked questions

An intermediate price several items reuse, such as mortar batched on site. It is defined once and updated in that single definition.

Because it multiplies the hourly cost. In the partition example labour accounts for €12 out of €33, so an output 30 per cent worse moves the price by several euros.

By comparing similar projects and correcting for execution conditions. Fragmented work and work at height worsen output systematically.

Updating them in their definition and never patch by patch in each item. An auxiliary corrected in one place and not another produces prices inconsistent across chapters.