Blog

PEM and PEC: definition, differences and uses

📐 Article8 min read

PEM and PEC are the two most used and worst distinguished acronyms of the Spanish budget. The confusion is not harmless: on a one-million-euro project, confusing levels produces reading errors of almost 20 % before VAT is even mentioned. This article fixes the definitions, the arithmetic and the map of documents where each level lives.

The definitions

PEM (presupuesto de ejecución material, direct works budget). The sum of all the project's work items at their unit prices: materials, labour, machinery and auxiliary means, with site indirect costs already distributed inside the prices. It is the cost of executing the works, without the contractor's corporate structure or its profit.

PEC (presupuesto de ejecución por contrata, contract budget). The PEM increased by the company's overheads and industrial profit. The dominant convention, inherited from public procurement, applies 13 % overheads and 6 % industrial profit on the PEM; the private market uses it as a reference with freedom of agreement.

The arithmetic

Item Calculation On a PEM of €1,000,000
PEM Sum of work items €1,000,000
Overheads (13 %) 0.13 × PEM €130,000
Industrial profit (6 %) 0.06 × PEM €60,000
PEC 1.19 × PEM €1,190,000
PEC with VAT (10 % housing) 1.10 × PEC €1,309,000
PEC with VAT (21 % general) 1.21 × PEC €1,439,900

Two usage clarifications. The 13+6 percentages are convention, not a law of nature: private contracts can agree other values, and the only firm rule is to declare them. And the PEC is not the project's total cost: professional fees, permits and the ICIO tax, utility connections, insurance and land remain outside; the complete chain up to development cost is developed in from PEM to total cost, in the cost guide.

The document map: where each level lives

Document or use Level employed
Execution design (quantities and budget document) PEM
Building permit and ICIO tax calculation PEM in general municipal practice
Professional fees referenced to the budget Usually PEM
Tender and works contract PEC (plus VAT)
Progress certificates and valued statement Contract prices, consistent with the contracted level
Ten-year warranty and technical inspection Referenced to the declared budget per the policy

The operating rule that avoids all errors: every circulating figure carries its level label. A budget that says "€1,190,000" and nothing else is a source of conflict; one that says "PEC, VAT excluded, overheads 13 % and profit 6 % on a PEM of €1,000,000" is data.

The three classic errors

Comparing a PEM with a PEC. It happens when comparing the design budget with a contractor's offer: the 19 % difference is not an increase, it is a change of level.

Applying ratios at the wrong level. Published ratios per m² exist at both levels depending on the source; applying a PEC ratio on a PEM base inflates the framing by 19 % without anyone getting a number wrong.

Forgetting the level in derived percentages. Fees, ICIO and charges are agreed or calculated "on the budget": without specifying which, the same contract admits two readings separated by 19 %.

The essentials

PEM is the cost of executing; PEC is the PEM plus the company's structure and profit (13+6 convention, factor 1.19). The design, the permit and the fees usually live in PEM; the contract and the certificates in PEC plus VAT. The discipline that resolves everything: no figure without its level label, and no derived percentage without its declared base.

Note: usual conventions in Spain in 2026; each contract's agreement and the applicable municipal ordinances prevail.

Frequently asked questions

The material execution budget: the sum of the items at unit prices, with site indirect costs already inside the prices. It is the level from which the others are calculated.

Overheads and industrial profit, under the usual 13 and 6 per cent convention on the PEM. The result is the contract budget, excluding VAT.

No. It is applied to the contract budget, at 10 per cent on housing and 21 per cent generally.

The PEM in the design budget, the PEC in tendering and the contract, and total development cost in the feasibility study. Comparing levels is the classic error.

Quantities and budgets in Spanish construction: complete guide