1. What the category is and why its costs differ
A building open to the public is any building or space to which people other than those who work there are admitted. The definition covers an immense spectrum: from the corner shop to the international airport, from the doctor's surgery to the teaching hospital.
The French fire and panic safety regulations classify establishments by type according to their activity, restaurants, shops, hotels, schools and so on, and by category according to their occupancy, from the first category for the largest to the fifth for the smallest. That dual classification determines which requirements apply.
This regulatory framework is the principal source of the premium over housing. An apartment building and a restaurant of the same floor area do not face the same requirements on smoke control, accessibility, ventilation or structural fire resistance. Those technical differences translate directly into euros.
The rule of categories
Establishments in the first three categories, above 300 people (over 1,500 for the first, 701 to 1,500 for the second, 301 to 700 for the third; CCH, R143-19), are the most demanding. Whether an automatic sprinkler system is required does not depend on the category alone: the fire safety regulations allow one to be required in all or part of an establishment (order of 25 June 1980, art. MS 25), and the cases where it is mandatory are set in the specific provisions for each type of establishment. Those provisions also take the category into account for other fire-fighting means, such as fire hose reels (for example art. U 42 and T 47). Fifth-category establishments, below the occupancy thresholds, face lighter requirements but remain subject to accessibility, often the most visible premium for small shops and restaurants.
2. Ratios by sub-type
The table gives cost bands excluding VAT by sub-type, with the dominant items and the recommended contingency. The ratios exclude land, fees and external works, in values for a provincial location.
| Type | Regulatory type | Ratio excl. VAT, provincial | Reference area | Dominant items | Contingency |
|---|---|---|---|---|---|
| Staff restaurant | N | 2,240 – 3,570 €/m² | Total area | Professional kitchen, ventilation, extraction | 10–15 % |
| Commercial restaurant | N | 2,550 – 4,590 €/m² | Total area | Professional kitchen at 35–50 % of the works cost, dining room | 10–15 % |
| Retail unit | M | 1,220 – 2,550 €/m² | Sales area | Light structure, shopfront, technical equipment | 8–12 % |
| Shopping centre | M | 1,840 – 3,270 €/m² | Floor area | Malls, parking, central services, fire safety | 8–12 % |
| One- or two-star hotel | O | 71,500 – 112,000 €/room | Per room | Repeatable structure, simple equipment | 8–12 % |
| Three- or four-star hotel | O | 122,500 – 204,000 €/room | Per room | Kitchen, spa, premium common areas | 10–15 % |
| Five-star hotel | O | 255,000 – 612,000 €/room | Per room | Suites, fine materials, bespoke fittings | 12–18 % |
| Nursery and primary school | R | 2,040 – 2,860 €/m² | Usable area | Acoustics, ventilation, full accessibility, playgrounds | 8–12 % |
| Secondary school | R | 2,240 – 3,270 €/m² | Usable area | Laboratories, specialist rooms, boarding | 10–12 % |
| Municipal sports hall | X | 1,840 – 2,860 €/m² | Floor area | Long-span structure, acoustics, changing rooms | 8–12 % |
| Multi-purpose hall | L | 2,040 – 3,270 €/m² | Usable area | Acoustics, stage, seating, dressing rooms, services | 10–15 % |
| Clinic and medical centre | U | 2,860 – 4,590 €/m² | Usable area | Medical gases, operating theatre, reinforced acoustic separation | 12–18 % |
| Day nursery | R | 2,550 – 3,570 €/m² | Usable area | Adapted living spaces, non-toxic materials, safety | 10–12 % |
Note: hotels are expressed as a cost per room, the sector's reference unit. To convert to a cost per square metre, divide by the average area per room, 30 to 50 m² according to the standard. Apply the regional factor for your area.
3. What the regulatory premiums really represent
The cost difference between a public building and housing of the same area is not a matter of more luxurious finishes; it comes from requirements that impose works with no residential equivalent. The table details the principal premiums and their order of magnitude.
| Requirement | Applies to | Estimated premium over housing | Principal effect |
|---|---|---|---|
| Full accessibility | All such buildings, every route | + 5 to 12 % | Ramps, oversized lifts, accessible sanitary accommodation, adapted signage |
| Reinforced fire safety | All, by category | + 4 to 10 % | Active smoke control, sprinklers where the type of establishment requires them, compartmentation, early detection |
| Use-specific ventilation | Restaurants, shops, schools, medical | + 3 to 8 % | Statutory air flow rates by use, kitchen extraction, filtration |
| Regulated acoustics | Schools, sports halls, event spaces | + 3 to 7 % | Reinforced sound insulation, absorbent ceilings, treatment of noisy rooms |
| Professional kitchen | Restaurants | + 30 to 45 % on the kitchen item | Stainless equipment, cold rooms, extraction canopy, high-pressure gas |
| Medical gases | Medical | + 15 to 25 % of the works cost | Oxygen, vacuum and medical air, contamination control, HEPA filtration |
| Long-span structures | Sports and multi-purpose halls | + 8 to 15 % | Clear spans of 25 to 40 m, steel or prestressed concrete, roof insulation |
| Access control and security | All, according to use | + 2 to 5 % | CCTV, access control, intercom, emergency lighting |
The premiums accumulate according to type. A commercial restaurant combines accessibility, specific ventilation, reinforced fire safety and a professional kitchen, which is why its ratio often exceeds 3,060 €/m² even for an architecturally simple programme. A sports hall adds to these the long-span structure with clear spans of 25 to 40 metres.
The professional kitchen: the item that always surprises
In a commercial restaurant the professional kitchen can represent 35 to 50 % of the works cost, according to the level of equipment and the culinary concept. It is not an item to reason per square metre but per piece of equipment: the cooking range, positive and negative cold rooms, the wash-up, the extraction canopy and its ventilation, the high-pressure gas supply.
A restaurateur who pre-budgets by applying a housing ratio makes an error of several hundred thousand euros. The construction economist is the only party able to price this item precisely before the production drawings.
4. The economics of each family
Restaurants and retail: fit-out as the dominant item
For restaurants and shops the structure is often simple, a concrete or steel box with a commercial frontage. What costs money is what goes inside: the kitchen, the ventilation, the specific electrical installation with an installed capacity often three to five times that of a home, the refrigeration. On the refurbishment of an existing unit the shell is often acceptable and the budget concentrates entirely on the technical fit-out, which is why refurbished retail fit-out runs at 820 to 2,550 €/m².
Hotels: reason per room, not per square metre
The hotel is the only type where the cost per room is more relevant than the cost per square metre, because the room is the unit of production and of revenue. An 80-room three-star at 150,000 € a room costs 12,000,000 €, but its floor area can vary from 3,500 to 5,000 m² according to the architectural concept. The cost per square metre therefore varies from 2,400 to 3,400 € for the same cost per room.
The items that concentrate the value are the common areas, lobby, restaurant, bar, which often represent 25 to 35 % of the budget for only 15 to 20 % of the area, and the technical facilities such as spa, pool and kitchen, whose effect on the cost per room is spectacular: adding an indoor pool to a four-star can take the cost per room from 180,000 to 250,000 €.
Public facilities: the procurement issue
Schools, sports halls and sports facilities are mostly public commissions, subject to the procurement code. That affects the construction cost in two ways: the technical requirements are stricter, full universal accessibility, durability of materials, ease of maintenance, and the procedural timescales lengthen the period of inflation risk.
For local authorities the economist is often the first port of call for confirming the budget feasibility of a public facility before it enters a multi-year investment programme. A realistic outline estimate, incorporating the regulatory premiums specific to the category, is the foundation of a responsible public investment decision.
5. Public against private procurement
The great majority of sports halls, schools and cultural facilities are procured publicly. Restaurants, hotels and shops are private. Their funding and their construction procedures are radically different.
| Criterion | Public procurement | Private procurement |
|---|---|---|
| Typical client | Local authority, the State, a public body | Investor, private group, operator |
| Tender procedure | Mandatory under the code: open, restricted or adapted according to thresholds | Free, direct negotiation possible |
| Tender period | 3 to 6 months longer than private | Flexible, 3 to 8 weeks |
| Effect on prices | Greater competition, sometimes more competitive prices in a slack market | Direct negotiation possible |
| Inflation risk during the procedure | High in a tight market | Limited, the tender is quick |
| Additional technical requirements | Full universal accessibility, sustainability, standard conditions | Level freely defined |
| Technical statements | Mandatory, weighted against price | Optional |
| Estimated premium over private | + 5 to 12 %, requirements plus timescales | The reference |
6. Contingencies: higher than in housing
Buildings open to the public justify higher contingencies than housing, for several reasons. The technical complexity of the specific packages, professional kitchen, ventilation, sports equipment, is hard to price precisely at outline stage without detailed drawings. The interfaces between packages are numerous, and the regulatory requirements can change between concept and construction, as accessibility, acoustic and fire regulations are updated.
The recommended contingency is 10 to 15 % for ordinary cases, and 12 to 18 % for complex ones such as hospitals, medical buildings and those with bespoke equipment. That is not pessimism, it is an order of magnitude for framing, not a statistic, which takes account of what these operations often reveal during design and on site.
In summary
Buildings open to the public form the most heterogeneous family in construction, with ratios running from 1,220 €/m² for a simple shop to more than 612,000 € a room for a luxury hotel. What they share is a structural premium over housing generated by regulation: universal accessibility at 5 to 12 %, reinforced fire safety at 4 to 10 %, specific ventilation, regulated acoustics. The professional kitchen is the most under-estimated item in restaurant budgets and can represent 35 to 50 % of the works cost. Hotels are reasoned per room; public facilities carry a premium of 5 to 12 % tied to procurement requirements. In every case the recommended contingency is 10 to 15 %, reflecting the technical and regulatory complexity of these programmes.
Reference basis of the figures
These bands are orders of magnitude for framing. Unless the page names another area, their reference market is standard provincial France, outside the major cities (regional cost factor 1.00). They serve to place a budget at the earliest stages and to compare building types with one another. They replace neither a tender exercise nor an estimate prepared on drawings, and they are not a record of prices actually charged.
The ratios per square metre and per item on this page are stated in January 2026 values. They were updated from January 2025 values, the basis adopted for the whole cocoon, using the BT01 all-trades index published monthly by INSEE on its 2010 base: 132.0 in January 2025, 134.7 in January 2026, a rise of about 2 %.
The global amounts quoted as examples, and any rents, charges or receipts expressed per year or per night, remain on their own basis: a building cost index does not apply to them.
To bring the ratios forward, apply the usual revision formula: updated value = page value × (BT01 for the month in question / 134.7). The index has kept rising since: it stood at 139.4 in August 2026, the last value published when this page was checked (Journal officiel of 16 October 2026), that is 3.5 % above the reference base. BT01 measures contractors' input costs, wages and social charges, materials, plant and energy, not the prices actually tendered.
Sources: the BT construction cost indices published monthly by INSEE on its 2010 base, used to update the figures · construction cost statistics from SDES, the statistical service of the ministry responsible for construction · regulatory texts published in the Journal officiel and consolidated on Légifrance for the requirements cited.