Aller au contenu principal

Off-plan sale: buying before completion, and the guarantees

📐 Article

By , construction economist

Information verified on 5 min read

Sale in a future state of completion is the legal regime governing the purchase of a property before, or during, its construction. It is the dominant contractual framework of residential development in France: the great majority of new flats sold in the country are sold this way.

For the buyer, whether a private individual or an investor, off-plan purchase offers advantages, a new dwelling to current standards, statutory guarantees, staged payment, but also specific risks that must be understood before committing.

What you will learn

  • How off-plan sale works legally and financially
  • The statutory payment schedule
  • The statutory guarantees that protect the buyer
  • The points to check before signing a reservation contract or the deed

How it works

In an off-plan sale the buyer acquires a property that does not yet exist, or is not yet finished, at the moment of signature. The sale deed is signed before the works are complete, and the price is paid progressively as construction advances.

The developer, as seller, retains the powers of the client until practical completion of the works (Civil Code, art. 1601-3). It signs the contracts with the contractors, manages the site and bears the risks of cost and programme overrun.

The key steps

The reservation contract A preliminary contract between developer and buyer. It describes the property, the price, the anticipated delivery date and the withdrawal conditions for a non-professional buyer, ten days (CCH, art. L271-1). The deposit is capped at 5 % of the anticipated price where the sale is to take place within a year, 2 % within two years, and none beyond (CCH, art. R261-28).
Obtaining planning permission The permission must be free of challenge before the deed is signed. A key point of vigilance for the buyer.
The sale deed Signed before a notary. This is when the off-plan sale is definitively constituted and the statutory payment schedule begins.
Staged payments Progressive payments according to the progress of the works, as set out below.
Handover Keys handed over and a joint inspection made. The buyer can record defects in the visible work. The start of the warranty periods.

The statutory payment schedule

The law strictly frames the rhythm of payments where the building is for residential use or for mixed professional and residential use. The developer may then not claim more than the following ceilings (CCH, art. R261-14):

35 % of the price On completion of the foundations
70 % of the price When the building is weathertight, the roof or roof slab being in place
95 % of the price On completion of the building
100 % of the price On handing over the property

A key point: the remaining 5 % can be held in escrow where defects are recorded at handover. If the buyer records significant defects, they can lodge the 5 % with a third party, a notary or the state deposit institution, rather than paying the developer. Those funds are released only when the defects are cleared.

The statutory guarantees

The completion guarantee Provided by a financial institution, bank or insurer, assuring that the building will be completed even if the developer fails. Mandatory where the building is for residential use or for mixed professional and residential use and the buyer pays funds before completion: the seller then takes out a financial guarantee of completion or of repayment (CCH, art. L261-10 and L261-10-1). For any other use, those articles do not impose it, and the financial guarantee is negotiated in the contract. It is the buyer's principal protection against developer insolvency.
The one-year defects liability It obliges the contractor, for one year from practical completion, to make good the defects reported by the client (Civil Code, art. 1792-6). In an off-plan sale, it is the seller who accepts the works, since it retains the powers of the client until practical completion (art. 1601-3). Towards the buyer, the seller answers for apparent construction defects and non-conformities (Civil Code, art. 1642-1).
The two-year warranty Covers equipment separable from the structure, boiler, shutters, taps, for two years.
The ten-year warranty Covers damage affecting the soundness of the building, or rendering it unfit for its purpose, for ten years. Taken out by the contractors and the design team.

Points to check before signing

  • Verify the existence and validity of the completion guarantee: ask for the name of the guaranteeing institution and the reference of the guarantee.
  • Examine the planning permission: make sure it is free of third-party challenge before signing the deed.
  • Read the descriptive schedule closely: it sets out the materials, equipment and finishes provided. Any later change will be charged as a buyer variation.
  • Assess the developer's financial strength: track record, number of operations delivered, level of pre-sales on this one.
  • Allow margin on the delivery date: dates announced off plan are often optimistic. Build three to six months of margin into your return calculations.

Related articles: calculating the return on a property project · Financial risks in construction projects

The statutory provisions mentioned are those of the French construction and housing code in force in 2026. Off-plan sale is a complex contract; take advice from a notary and a specialist lawyer for substantial acquisitions.

The nature of the figures quoted

The time margins quoted (three to six months) are orders of magnitude for framing, not measurements. The percentages and the withdrawal period set by law are tied to their articles.

Sources: the BT construction cost indices published monthly by INSEE on its 2010 base, used to update the figures · construction cost statistics from SDES, the statistical service of the ministry responsible for construction · regulatory texts published in the Journal officiel and consolidated on Légifrance for the requirements cited.

← Construction economics: the complete guide for professionals