Local planning documents
The local plan is the principal reference for any construction project. Municipality by municipality, or across a grouping of municipalities, it defines the rules on density, height, siting and external appearance. Reading it rigorously governs the feasibility and the massing of the project from the earliest design phases.
1 The structure of the local plan
A local plan's regulation is traditionally structured in 14 or 15 numbered articles, in the same order everywhere. The first fixes the permitted uses, the second those prohibited, the sixth addresses siting relative to public roads, the seventh and eighth siting relative to boundaries and to other buildings on the same plot, the ninth maximum site coverage, the tenth maximum height and the twelfth parking.
A commonly used instrument is the prospect rule, which imposes a minimum distance between a façade and a boundary or a facing building, calculated in proportion to the height of the scheme. It preserves daylight and limits the wall effect.
2 The zones
The zoning plan divides the territory into zones with distinct rules. Urban zones are intended for immediate construction. Zones for future urbanisation are buildable subject to conditions. Agricultural, natural and forest zones are in principle not buildable, save for construction tied to farming or to facilities of general interest.
3 The territorial coherence scheme
This is a planning document of higher rank than the local plan, drawn at the scale of a catchment area. It sets strategic orientations for the territory — densification, preservation of natural spaces, retail development. The local plan must be compatible with it.
Points of vigilance when reading a local plan
• Site coverage coefficients and minimum plot sizes were abolished by legislation in March 2014. Any local plan still imposing them is unlawful.
• Since 2015 local plans may allow massing to be exceeded for positive-energy or environmentally exemplary buildings.
• Always check the public utility easements — noise exposure plans, flood risk plans, heritage perimeters, high-voltage networks — which overlay the zoning.
Planning permission: filing, content and determination periods
1 Scope
Planning permission is mandatory for any new construction whose floor area or footprint exceeds 20 m², a threshold reduced to 5 m² in a protected area or one requiring the heritage architect's opinion. It is also required for renovation or extension above those thresholds, and for any change between the five use classes set out in the planning code — housing, hotel and tourist accommodation, offices, retail and services, and other secondary or tertiary activities — even with no works.
2 Determination periods
The ordinary determination period is three months for a standard application, extended to five months for a building open to the public. It can be extended in several cases.
| Case | Standard period | Extension | Total |
|---|---|---|---|
| Prior declaration | 1 month | + 1 month with heritage consultation | 1–2 months |
| Individual house and outbuildings | 2 months | + 1 month heritage, + 1 for a commission | 2–4 months |
| Other constructions | 3 months | + 1 month if a departmental or regional commission is consulted | 3–4 months |
| Building open to the public | 5 months | The mandatory specific period | 5 months minimum |
| Within a listed heritage perimeter | 4 months | Heritage approval mandatory | 4 months minimum |
| A listed building itself | 5 months | The regional heritage commission's opinion mandatory | 5 months minimum |
Table 1. Determination periods, running from the date a complete application is filed.
They run from receipt of a complete application. Any missing document interrupts the period and obliges the municipality to request the missing items within a month of filing. The clock then restarts from receipt of what was missing.
3 What the application contains
The application comprises the official form, the drawings — location, site plan, elevations, roof plan, sections, contextual views — a descriptive statement, a fire safety statement for buildings open to the public, an accessibility statement and, according to the case, a certificate of compliance with the environmental regulations, an acoustic compliance certificate and an energy supply feasibility study.
ℹ Certificates now mandatory with the application
• A certificate of compliance with the environmental regulations for new buildings, signed by the design team
• A certificate that the energy supply feasibility study has been carried out, for buildings above 50 m² other than individual houses
• An accessibility compliance certificate for buildings open to the public and for apartment buildings
These certificates engage the design team's liability and bring private-law requirements into the determination of a public consent.
The prior declaration: scope
The prior declaration covers smaller works not requiring planning permission: extensions between 5 and 20 m² of floor area or footprint, new construction between 5 and 20 m², alterations to façades where the local plan so requires, changes of use without works in agricultural or natural zones, and fencing in certain areas.
Its determination period is one month, extended to two within a heritage perimeter or a protected sector. No answer within that period constitutes tacit approval, except where the heritage architect's opinion is required, in which case silence means refusal.
Using an architect: thresholds and legal obligations
The architecture act of 1977 requires an architect for the design of non-agricultural construction whose floor area exceeds 150 m². For agricultural construction the threshold is 800 m².
Below those thresholds the client may file the application themselves, but remains responsible for the project's compliance with planning, construction and safety rules. In practice, even below the thresholds, using an architect is strongly advisable for projects subject to heritage consultation or carrying complex regulatory constraints.
Thresholds for using an architect
• Above 150 m² of floor area: an architect is mandatory for a non-agricultural client
• Above 800 m² for agricultural construction: an architect is mandatory
• Every building open to the public, whatever its area, where permission is sought
• Every high-rise building
• Every construction subject to a prior declaration where the client is not a private individual
The heritage architect: scope and procedure
The heritage architect is a state official within the departmental architecture and heritage service. Their remit covers projects within 500 metres of a listed building, within architectural, urban and landscape protection zones, and within remarkable heritage sites and protected sectors.
1 Advisory and binding opinions
The heritage architect's opinion is advisory, not legally binding on the prefect, in most cases, but binding within perimeters of intervisibility with a listed monument. An unfavourable binding opinion blocks planning permission.
An appeal against an unfavourable binding opinion exists: the client may petition the regional prefect, who decides after the regional heritage and architecture commission has given its opinion, within three months. That appeal is rarely used but can unblock an impasse.
ℹ What the heritage opinion covers
• Façade and roof materials: colours, textures, the nature of the materials
• External joinery: the form, colour and materials of windows and doors
• The general appearance of the building: massing, volume, façade composition
• Signs and advertising visible from public space
• Fences, gates and external landscaping elements
The heritage architect can also be consulted before the application is filed, to obtain guidance — strongly recommended for projects in a constrained perimeter.
2 The economic impact of heritage constraints
Heritage requirements can impose traditional materials — natural slate, dressed stone, painted timber joinery — significantly dearer than standard solutions. The premium is highly variable, but can represent 5 to 20 % of the façade and roof packages according to what is required. The additional determination time of one to two months must also be built into the programme.
Floor area: calculation, deductions and its relation to the local plan
Since 1 March 2012, floor area has replaced the former gross and net area measures, which generated confusion and inequality between projects.
1 Definition
Floor area is the sum of enclosed and covered floor areas under a ceiling height above 1.80 m, measured from the internal face of the façades. Unlike the former measure, the thickness of external walls is excluded.
2 Deductions
| Element | Treatment |
|---|---|
| The thickness of external insulation | Excluded, and deductible where existing insulation is moved outward |
| Balconies and terraces | Excluded |
| Stair and lift voids | Excluded |
| Parking areas, including ramps | Excluded |
| Cellars under 1.80 m ceiling height | Excluded |
| Plant rooms | Excluded |
| Apartment buildings: a further deduction | −10 % of the habitable area where dwellings are served by internal common parts |
Table 2. Elements excluded from the floor area calculation.
3 Footprint
Footprint is the vertical projection of the volume of the construction, including all overhangs and projections. It is used to calculate the thresholds for permission or prior declaration, and for the maximum coverage rules in the local plan.
Special consents
1 Classified installations for environmental protection
These are installations presenting a risk to the environment or to health, listed in a national nomenclature. According to the level of risk they require a declaration, a registration or an environmental authorisation — the most demanding, with a public inquiry. Determination of an environmental authorisation can take 12 to 18 months, which requires very early anticipation in the programme.
The headings most commonly encountered in construction are filling stations, warehouses storing combustible materials, laundries, livestock buildings, and certain industrial or food-processing activities. The nomenclature changes regularly and must be consulted on the ministry's official site.
2 Water law applications
Projects affecting the water cycle — sealing surfaces, discharging surface water, modifying a watercourse, abstracting water — may fall under the water law nomenclature in the environmental code. According to the threshold reached, the project requires a declaration or an authorisation, with determination periods reaching 6 to 12 months. This obligation is frequently forgotten on large development projects: business parks, housing estates, car parks.
3 Buildings open to the public: five months and the safety commission
For such buildings, planning permission carries a five-month determination period instead of three. It incorporates consultation of the fire safety commission on the scheme. A complete technical file — the safety statement, fire safety system drawings, smoke control drawings — must be included so that consultation can happen within the period. An incomplete file leads either to refusal or to a permission subject to conditions.
4 High-rise: review by the central safety commission
High-rise projects — above 50 m for dwellings, above 28 m for others — must go to the interior ministry's central safety commission before the application is determined. An unfavourable opinion blocks the procedure. Designing a high-rise therefore requires very early consultation with the commission, before the application is even filed.
The economic impact for the construction economist
Planning and administrative constraints bear directly on the cost and the timescale of an operation. The economist must build them in from the feasibility study.
1 Local plan constraints and massing
Limits on height, prospect, coverage and density can considerably reduce the buildable programme against the economic optimum of the site. A buildable massing study from the local plan should be carried out at feasibility.
2 Determination periods and finance costs
The determination period represents a non-negligible cost of holding the land and of pre-financing. For a public building with heritage consultation: five months minimum plus two if the opinion is binding, that is seven incompressible months. For a project requiring environmental authorisation: 12 to 18 months more. The monthly holding cost must enter the appraisal.
3 Heritage requirements and materials
Heritage requirements can impose significantly dearer façade and roofing materials. Natural slate against concrete tile: 40 to 80 €/m² more on the roof. Dressed stone against standard render: 200 to 610 €/m² more on the façade according to the stone. These premiums must be provided for from the concept stage.
4 Challenges and litigation
Any planning permission may be challenged, informally or in court, by third parties within two months of the notice being posted on site. A challenge can block the start of work for several years. On sensitive operations — housing in dense urban areas, facilities generating nuisance — the risk should be assessed at feasibility and a provision can be built into the funding plan.
✔ Summary for the economist: administrative consents
• Standard determination: 3 months, 5 for a building open to the public, 4–5 within a heritage perimeter
• Additional time for a binding heritage opinion: + 1 to 3 months
• Environmental authorisation: + 12 to 18 months
• Water law authorisation: + 6 to 12 months
• Material premium from heritage requirements: + 5 to 20 % on the façade and roof packages
• Provision against litigation on sensitive operations: 2 to 5 % of the land cost
• A local plan and massing feasibility study: indispensable before any offer on a site
ℹ To go further on building regulation
→ Construction regulations in France: the overview and general framework
→ Accessibility in construction: obligations and measures
→ Fire safety and fire resistance
→ Buildings open to the public: classification, categories and compliance
→ The environmental regulations: requirements and their measured impact
→ Building in a protected sector or heritage perimeter
The construction economist on demand.
A complex application, local plan constraints, a heritage objection? Submit your project on quostra.com and an economist assesses the regulatory constraints and prices their effect on your budget.
→ quostra.com
Reference basis of the figures
The ratios per square metre and per item on this page are stated in January 2026 values. They were updated from January 2025 values, the basis adopted for the whole cocoon, using the BT01 all-trades index published monthly by INSEE on its 2010 base: 132.0 in January 2025, 134.7 in January 2026, a coefficient of 1.0205.
The global amounts quoted as examples, and any rents, charges or receipts expressed per year or per night, remain on their own basis: a building cost index does not apply to them.
To bring the ratios forward, apply the usual revision formula: updated value = page value × (BT01 for the month in question / 134.7). The BT01 measures contractors' input costs, labour at 44.9 % and materials at 36.5 %, not the prices actually tendered.