1. The fundamental rule: state the uncertainty before any figure
Producing a refurbishment budget without complete drawings is legitimate; it is indispensable to any feasibility decision. But any budget produced in those conditions has to state explicitly how reliable it is and what contingency it carries. An estimate presented without that information creates a false precision that turns against both the client and the architect.
The rule is simple: the more incomplete the documentation, the wider the range and the higher the contingency. That is not a sign of poor work by the economist, it is an honest quantification of the uncertainty remaining in a building whose secrets are not all known.
ℹ The sentence to include in any refurbishment budget without complete drawings "This estimate is prepared on the basis of the drawings available, a partial measured survey, or a visit without drawings, at the date stated. In the absence of complete drawings, an asbestos survey or a structural survey, a contingency of the stated percentage has been applied. The estimate will be revised once the measured survey, the survey findings or the developed design drawings are available. Current accuracy: the stated range."
2. Four methods by documentation available
| Documentation | Recommended method | Accuracy | Contingency | Points to watch |
|---|---|---|---|---|
| Existing drawings plus a recent survey | Semi-detailed quantities by package | ± 10–15 % | 10 % | Check the drawings against what is on site; old drawings are not reality |
| Old drawings, no survey | Rates per m² plus partial checking on site | ± 20–25 % | 15 % | Identify the risk zones, floors, roof, services, and plan a survey before developed design |
| No drawings, survey to be commissioned | Envelope budget on overall rates | ± 30 % | 15–20 % | State the uncertainty explicitly; do not produce a line-by-line estimate |
| No drawings and no access | Order of magnitude with a wide range | ± 40–50 % | 20 % | For a go or no-go only; any commitment requires a survey first |
The overall rates method is the only one possible without complete drawings. It works from the building's approximate areas, measured by eye or taken from the land registry, and from cost rates by type of work. The result is a range, not a line-by-line estimate. Presenting a line-by-line estimate with no drawings amounts to inventing precision, and it is the commonest and most dangerous error of all.
3. The rates method in five steps
Step 1, collect the reference areas
Even with no drawings, approximate areas are obtainable. The land registry record gives the footprint and the number of storeys. The energy performance certificate, where one exists, states the habitable area. A quick visit with a laser measure gives floor areas to within 10 %. Those imprecise areas are enough for an estimate from rates: their precision matches the precision of the method.
Step 2, define the scope
The scope has to be defined package by package: which trades are involved, at what level of specification, light, intermediate or heavy, and which parts of the building are included. A vague scope produces a vague estimate, and it is for the economist to force that clarification with the client before producing any figure at all.
Step 3, apply current market rates
Rates are applied package by package on the reference area appropriate to each trade. The reference area is not the same for every package: habitable area for the internal trades, partitions, floors, paint, electrical, plumbing, façade area for external insulation, roof area on the slope for the covering, and numbers for the windows.
Step 4, add the items specific to refurbishment
Three items specific to refurbishment always sit on top of the ordinary trades: strip-out and selective demolition, at 5 to 12 % of the budget before surveys; the compulsory surveys for asbestos and lead and the advisable ones for structure and energy; and waste disposal, calculated in tonnes by waste stream. These items are systematically missing from do-it-yourself estimates, and their omission is the leading cause of divergence between the initial budget and the final cost.
Step 5, apply an explicit contingency
The contingency is calculated as a percentage of the works total and shown as an explicit line in the estimate, never as a hidden uplift. Its rate depends on the precision of the documentation: 10 % as a minimum, 15 to 20 % on an old or poorly documented building. That line should carry a note stating the conditions under which it can be reduced, after the survey, after the survey findings, after the developed design drawings.
4. A worked example: a 320 m² town house, complete refurbishment
The example below is an estimate from rates on a 320 m² town house built in 1935. No drawings exist. A visit allowed the approximate areas to be measured. The asbestos survey has been commissioned but not received, so a provision is carried. The scope is a complete refurbishment including insulated façades, the roof, all the finishing trades and the services.
| Package | Basis | Rate | Amount | Contingency at 12 % | Total | Reliability |
|---|---|---|---|---|---|---|
| Demolition and strip-out | 320 m² | 45 €/m² | 14 400 € | 1 728 € | 16 128 € | ★★★ |
| Structure | Subject to the structural survey | To be confirmed | To be confirmed | ★ conditional | ||
| Roof structure and covering | 320 m² of roof footprint | 120 €/m² | 38 400 € | 4 608 € | 43 008 € | ★★★ |
| Façades and external insulation | 260 m² of façade | 180 €/m² | 46 800 € | 5 616 € | 52 416 € | ★★★★ |
| External joinery | 28 units, estimated | 1 200 € each | 33 600 € | 4 032 € | 37 632 € | ★★★ |
| Partitions and linings | 320 m² | 85 €/m² | 27 200 € | 3 264 € | 30 464 € | ★★★ |
| Floor finishes | 280 m² of finished floor | 65 €/m² | 18 200 € | 2 184 € | 20 384 € | ★★★★ |
| Plumbing and sanitary | 320 m² | 95 €/m² | 30 400 € | 3 648 € | 34 048 € | ★★★ |
| Heating and ventilation | 320 m² | 110 €/m² | 35 200 € | 4 224 € | 39 424 € | ★★★ |
| Electrical | 320 m² | 75 €/m² | 24 000 € | 2 880 € | 26 880 € | ★★★ |
| Painting and finishes | 320 m² | 55 €/m² | 17 600 € | 2 112 € | 19 712 € | ★★★★ |
| WORKS TOTAL | 285 800 € | 34 296 € | 320 096 € | |||
| Asbestos and lead surveys | Lump sum | 1 200 € | 1 200 € | Compulsory | ||
| Measured survey | Lump sum | 2 500 € | 2 500 € | Advisable | ||
| GRAND TOTAL | 289 500 € | 34 296 € | 323 796 € | 891 €/m² |
The table makes two points. The structure is not priced at all: the visit revealed cracking in the façade and old floors of doubtful condition, and pricing that package without a structural survey would be manufacturing false precision. The final figure of 891 €/m² is consistent with the heavy refurbishment range of 700 to 1 200 €/m², which validates the overall order of magnitude even with one package missing.
5. The five items most often forgotten
1. The compulsory surveys: the asbestos survey before works is compulsory on any building predating July 1997, and the lead survey on any dwelling predating 1949. Their cost is modest, 800 to 4 000 € together, but their findings can move the estimate by tens of thousands.
2. Strip-out and disposal: removing the existing fabric costs money, and so does taking it away. Asbestos waste is charged at five to ten times the rate for inert waste. This item is 3 to 8 % of the budget depending on the extent of the strip-out.
3. The measured survey: with no drawings, a survey is indispensable before the tender. Its cost, 1 000 to 5 000 € depending on the size of the building, is negligible against the measurement errors it prevents, and it is systematically missing from feasibility budgets.
4. Compulsory compliance works: accessibility, bringing the electrical installation up to standard, gas compliance. These can represent 5 to 12 % of the budget depending on the starting condition, and they are often discovered at tender stage when no regulatory review was done beforehand.
5. Design and consultancy fees: architect at 8 to 12 % of the works, economist at 1 to 3 %, services and structural engineers at 2 to 4 %, approved inspector at 0,5 to 1,5 %, structural damage insurance at 2 to 4 %. Together these can be 15 to 20 % of the works cost, and they are systematically absent from feasibility budgets.
6. The checklist before any refurbishment estimate
| Check | What is verified | Blocking? | Impact if missing |
|---|---|---|---|
| The building has been visited | Access to every area: cellars, roof spaces, plant rooms | Yes | Risk of a major item omitted, roof or services |
| Date of construction known | Before or after 1949 for lead, before or after July 1997 for asbestos | Yes | The compulsory surveys cannot be budgeted |
| Asbestos survey available or commissioned | A current survey, or one commissioned | Yes for pre-1997 buildings | Risk of a major unprovisioned extra |
| Existing drawings identified and dated | Revision, date, and consistency with what was seen | Recommended | Measuring from superseded drawings distorts the estimate |
| Client's brief confirmed | Exact scope: which packages, what level of specification | Yes | Without a clear brief the estimate answers a question nobody asked |
| Occupied-building constraints identified | Occupation maintained, tenant access, safety planning | Recommended | The occupation premium is unprovisioned and drift follows |
| End use defined | Dwelling, public building or commercial, which sets the accessibility and energy obligations | Yes where the use changes | Compliance works unbudgeted |
| Client budget known or expected | The order of magnitude, which calibrates the level of specification | Recommended | Risk of producing an estimate outside the budget without knowing |
In summary
A refurbishment budget with no drawings is legitimate provided it states its reliability and its contingency explicitly. The method depends on the documentation available, from semi-detailed quantities on existing drawings at ± 15 % with a 10 % contingency, to an order of magnitude on an inaccessible building at ± 50 % with 20 %. The rates method runs in five steps: areas, scope, rates by package, refurbishment-specific items, explicit contingency. The five items most often forgotten are the compulsory surveys, strip-out and disposal, the measured survey, compliance works, and the design fees. The eight-point checklist confirms the prerequisites before any calculation.
The nature of the figures quoted
The percentages and amounts quoted on this page are orders of magnitude for framing, not measurements. They illustrate mechanisms and proportions, and they substitute neither for a tender exercise nor for an estimate prepared on drawings.
Articles liés
Sources: the BT construction cost indices published monthly by INSEE on its 2010 base, used to update the figures · construction cost statistics from SDES, the statistical service of the ministry responsible for construction · regulatory texts published in the Journal officiel and consolidated on Légifrance for the requirements cited.