The payback on an energy retrofit: how the economist calculates it

📐 Topic

By , construction economist

Information verified on 12 min read

What you will find in this article The return on an energy retrofit is the question every client asks and few professionals can actually calculate. Confusing gross cost with net cost, ignoring the grants, leaving out the annual energy saving, failing to reflect the effect on property value: those omissions produce distorted returns that hold back decisions which are in fact rational. This guide sets out the economist's method, the savings measure by measure, a full worked example on a 120 m² dwelling, and a comparison of four retrofit scenarios.

1. The four components of the return

The return on an energy retrofit is not simply the energy saved. It has four components, and the economist has to reflect all of them to produce a complete and honest calculation.

  • One, the direct energy saving: the reduction in annual consumption in kWh multiplied by the price of energy. It is the most tangible component, and the one whose projection is least certain, since the future price of energy is unpredictable.

  • Two, the grants and tax relief: the retrofit grant, the energy certificates, the reduced VAT rate and the interest-free loan. These reduce the net cost of the works, and reflecting them is indispensable to calculating the real payback.

  • Three, the effect on property value: a dwelling with a good energy rating sells for more than a comparable energy-intensive one: the French notaries measure this "green value" (study of 2024 transactions). That uplift is a real component of the return, and is routinely ignored.

  • Four, the value in use: better thermal comfort, less noise where insulation and windows are renewed, better air quality with heat recovery ventilation. These benefits are hard to monetise, but they weigh in the client's decision.

2. The savings by retrofit measure

Measure Estimated annual saving per m² Typical rating gain Indicative cost per m² Gross payback Net payback with average grants
Roof space insulation 4 – 8 € a year One band 30 – 60 €/m² 5 – 10 years 3 – 6 years
Ground floor insulation 3 – 6 € a year Half a band 25 – 50 €/m² 6 – 12 years 4 – 8 years
External wall insulation 6 – 12 € a year One to one and a half bands 100 – 200 €/m² 12 – 25 years 8 – 16 years
Replacing the windows 3 – 6 € a year Half a band 80 – 150 €/m² 18 – 35 years 12 – 22 years
Gas boiler replaced by an air-to-water heat pump 8 – 18 € a year One and a half to two bands 80 – 140 €/m² 5 – 10 years 3 – 6 years
Heat recovery ventilation 2 – 4 € a year A third of a band 25 – 50 €/m² 10 – 20 years 7 – 14 years
Whole-building retrofit 18 – 35 € a year Three to four bands 400 – 800 €/m² 15 – 25 years gross 8 – 14 years net

The three most profitable measures, roof space insulation, the heat pump and the whole-building retrofit, share a strong impact on consumption and a limited net payback, under ten years for the first two and 8 to 14 years for the whole-building retrofit. External wall insulation takes longer, 8 to 16 years, but delivers a bigger rating gain, and it is indispensable on a building with no perimeter insulation at all.

3. The method, step by step

Step 1, establish the starting position

The performance certificate before the works is the basis of the calculation. It gives the consumption in kWh/m² a year and the current energy bill. If no certificate exists or it is out of date, an energy audit or a fresh certificate has to be commissioned; that is the first expense of the exercise. Since 1 January 2026 the certificate has counted electricity with a factor of 1,9, lowered to 1,7 on 1 January 2027 (order of 19 August 2026): a dwelling heated by electricity can therefore move to another rating band, and so change its obligations, without works, and ADEME issues a free certificate of the new label.

Step 2, estimate the consumption after the works

Estimating consumption after the works rests on a thermal simulation, carried out by an engineer or included in the energy audit. It gives the projected rating for each retrofit scenario. For feasibility purposes, the savings per measure in the table above give a sufficient estimate.

Step 3, calculate the annual saving

The annual saving is the difference between consumption before and after, multiplied by the current price of energy. The calculation has to be done by fuel, gas, electricity, oil, at each unit price. Use today's price: do not extrapolate future rises, which are too uncertain to be relied on.

Step 4, calculate the net cost after grants

The net cost is the gross cost including VAT at 5,5 %, less the retrofit grant or the energy certificates according to the route, since the two cannot be combined on a whole-building retrofit. The interest-free loan does not reduce the net cost; it funds the balance at zero interest. It has to be treated separately, comparing the monthly instalment against the monthly saving.

Step 5, calculate the payback

The gross payback is the gross cost divided by the annual saving. The net payback is the cost after grants divided by the annual saving. The net figure is the one to give the client, not the gross.

Step 6, reflect the effect on property value

On a dwelling worth 250 000 € rated F, moving to a B rating can add 15 000 to 40 000 € on resale, 6 to 16 % depending on the location. That uplift belongs in the overall return, reducing the effective net cost of the works.

4. A worked example: 120 m², from rating E to rating C

Parameter Before After Calculation
Rating E, 280 kWh/m² a year C, 120 kWh/m² a year Estimated from the energy audit
Annual consumption 33 600 kWh 14 400 kWh 120 m² × the rate per m²
Annual energy cost at 0,17 €/kWh 5 712 € 2 448 € Consumption × unit price
Annual saving 3 264 € 5 712 less 2 448 €
Works cost, net of VAT 68 000 € Insulation, windows, heat pump, ventilation
VAT at 5,5 % 3 740 € 68 000 × 5,5 %
Gross cost 71 740 € 68 000 plus 3 740 €
Retrofit grant, whole-building, middle income – 13 500 € 45 % of 30 000 € net of VAT, the ceiling for a 2-band gain
Energy certificates 0 € Cannot be combined with the whole-building grant
Net cost after grants 58 240 € 71 740 less 13 500 €
Gross payback 22 years 71 740 ÷ 3 264 € a year
Net payback 18 years 58 240 ÷ 3 264 € a year
With an interest-free loan over 15 years, capped at 50 000 € 278 € a month 50 000 € ÷ 15 years ÷ 12 months, 8 240 € paid up front
Monthly saving 272 € a month 3 264 € ÷ 12
Net monthly effort 6 € a month 278 less 272 €, close to neutral

The tipping point: savings against the loan instalment In this example the loan instalment of 278 € a month, on the 50 000 € the loan can cover, sits very close to the monthly saving of 272 €, leaving a net effort of only 6 € a month for 15 years after 8 240 € paid up front. That is the key message for the client: the retrofit does not cost 58 000 €, it costs 8 240 € up front and then 6 € a month for 15 years, during which the household saves 272 € a month on energy. The net value of the decision is clearly positive from the outset.

5. Four scenarios compared

The economist's real work on a retrofit project is to put a comparison of scenarios in front of the client, not a single figure. Each has a different return profile according to the owner's time horizon and situation: a landlord facing a letting ban, an owner-occupier under no constraint, an investor holding for the long term.

Scenario Measures Net cost after grants Rating gain Annual saving Net payback When it fits
A, minimal measure Heat pump alone 8 000 – 12 000 € One and a half bands 1 500 – 2 500 € 4 – 6 years Short term, a dwelling caught by the current letting ban
B, partial retrofit Heat pump, roof insulation, windows 28 000 – 38 000 € Two bands 2 500 – 3 500 € 10 – 14 years Good performance, outside the 2028 obligation
C, whole-building retrofit Heat pump, external insulation, roof, windows, ventilation 55 000 – 75 000 € Three to four bands 3 000 – 4 500 € 14 – 20 years Optimal for grants, the whole-building retrofit grant applies
D, full retrofit Scenario C plus ground floor insulation and controls 65 000 – 90 000 € Four bands 3 500 – 5 000 € 16 – 22 years Maximum comfort and the largest effect on value

Scenario C is generally the most rational for an owner who wants to maximise the grants: it is the one that maximises the whole-building retrofit grant, which requires a gain of at least two rating bands, a threshold that scenario B only just reaches and that scenario D also exceeds. Scenario A is the emergency answer for a landlord whose dwelling is caught by the current ban, but it does not solve the 2028 and 2034 thresholds.

6. What the payback does not tell you

Every payback calculation rests on assumptions, and presenting them honestly to the client is an intellectual obligation of the economist.

  • The price of energy is uncertain: a 20 % rise mechanically improves the return, a fall degrades it. Projections over 15 to 20 years are trends, not certainties.

  • The rebound effect: a better-insulated dwelling is often heated warmer. Part of the theoretical saving is spent on additional comfort; the rebound is estimated at 10 to 30 % depending on the study.

  • Maintenance costs: a heat pump lasts 15 to 20 years and costs 150 to 300 € a year to service. Those costs belong in the whole-life calculation over the payback period.

  • The effect on value is local: the premium a good rating commands on the sale price depends on the local market. It is strong in the larger cities and weak in rural areas with low demand.

In summary

The return on an energy retrofit has four components: the direct energy saving, the grants and reduced VAT, the effect on property value, and the value in use. The three most profitable measures are roof space insulation with a net payback of 3 to 6 years, the heat pump at 3 to 6 years, and the whole-building retrofit at 8 to 14 years. The method runs in six steps: initial rating, projected consumption, annual saving, net cost after grants, net payback, effect on value. On the 120 m² example moving from E to C, the net cost is 58 240 €, the net payback 18 years, and the loan instalment of 278 € a month, on a loan capped at 50 000 €, sits against a saving of 272 €, a net effort of 6 € a month for 15 years after 8 240 € paid up front. The whole-building scenario maximises the grants and is the most rational choice for an owner under no immediate constraint.

The nature of the figures quoted

The percentages and amounts quoted on this page are orders of magnitude for framing, not measurements. They illustrate mechanisms and proportions, and they substitute neither for a tender exercise nor for an estimate prepared on drawings.

Sources: the BT construction cost indices published monthly by INSEE on its 2010 base, used to update the figures · construction cost statistics from SDES, the statistical service of the ministry responsible for construction · regulatory texts published in the Journal officiel and consolidated on Légifrance for the requirements cited.

← Refurbishment economics in France: the economist's tools and methods