Skip to content

Awarding the works without losing the budget

📐 Topic

By , construction economist

Information verified on 6 min read

What you will learn The rules that the private client and the contracting authority must set before opening the bids, the four typical risks of the award stage (bids that cannot be compared, bids too high, bids too low, the wrong form of contract) and the answer to each, with the provisions that support it.

The award is the moment when the budget meets the market, and often the moment when it turns out the two had never been introduced. The budget is not defended when the quotes arrive but before: by writing the rules of the comparison, the common basis on which contractors must respond and, in public works, the options the contracting authority reserves for itself.

Private works: freedom to negotiate, one discipline

The private committente (the client) may consult whoever it wishes, negotiate, consult again and reduce the scope. The civil code imposes no procedure for choosing the appaltatore (the contractor), but where neither a price nor a way of determining it has been agreed the consideration is set "by reference to existing tariffs or to customary practice", and failing that by the court (art. 1657 of the civil code, unofficial translation): an item of work without a price is a cost the client does not decide.

That freedom has only one useful condition: comparing on the same basis. Preventivi (contractor quotes) drawn up on different quantities, with missing items or undeclared exclusions, tell you only that each contractor read the design its own way. The answer is to give all of them the same unpriced bill of quantities and the same conditions.

The form of the price prepares tomorrow's variations. If the price is fixed as a lump sum, for agreed variations the contractor "is not entitled to payment for the variations or additions, unless otherwise agreed" (art. 1659 of the civil code), whereas variations ordered by the client within one sixth must be paid for even under a lump sum (art. 1661). A lump sum quote on a vague design exposes the budget to every future clarification.

Public works: the estimate fixed at the start governs the procedure

For the stazione appaltante (the public contracting authority), the award budget is the estimated value of the contract, and that estimate has a date. The value is fixed "at the time the notice launching the tender or the contract notice is sent" (D.Lgs. 36/2023, art. 14(7)), on the total amount payable net of VAT, options and renewals included (para. 4); with several lots, the cumulative value of all lots is counted (para. 9). The applicable procedure depends on that amount, and its regime is described in the guide to award procedures for public contracts in Italy. Two tools protect the budget more than any later negotiation: the option not to award, which exists only if provided for in the tender notice or the letter of invitation (art. 108(10)), and the review of abnormally low bids (art. 110), which the authority can carry out effectively only if it has its own estimate of labour and safety costs.

Four risks, four answers

Each risk at the award stage has a recognisable signal before signature.

Risk Signal Answer in private works Answer in public works
Bids that cannot be compared Totals far apart on identical items, scattered exclusions Same unpriced bill of quantities, item-by-item table, written questions Single tender basis, price list and specification already defined
Bids above the budget All bids above the estimate Negotiate, consult again, reduce the scope Do not award if provided for (art. 108(10)), revise and start again
Bid too low Isolated discount, labour below the estimate Ask for the price breakdowns of the main items Written explanations and possible exclusion (art. 110)
Unsuitable form of contract Interfaces not allocated, coordination not provided for General contractor or separate trades, with coordination costs in the budget Lots at cumulative value (art. 14(9))

Before opening the bids

Three decisions must be taken before a single price is received: an estimate updated to the date of the bids, without which nobody knows whether a bid is high or low; the threshold beyond which you stop negotiating and revise the design; and the items that can be removed or postponed without distorting the project. Totals are read last, after the scope and the items have been checked.

The articles in this branch

This article on awarding the works sets out the state of the rules as at 21 October 2026 and is intended for guidance. It does not replace legal advice or an examination of the specific case.

Frequently asked questions

No. A private client chooses the contractor freely and may negotiate and consult again; the only useful discipline is to have every contractor respond on the same basis.

No rule sets a number for private works. Comparability matters more than the count.

The contracting authority may decide not to award if no bid is advantageous or suitable, provided the option is set out in the tender notice or the letter of invitation and the decision is taken within 30 days of the evaluation of the bids (art. 108(10)). Otherwise the estimate and the design must be revised before a new procedure.

In public works the value of the lots is cumulated, and splitting a contract to avoid the rules of the code is prohibited (art. 14(6) and (9)). In private works, separate contracts shift coordination and interfaces onto the client, and these must be budgeted for.

Explore the articles in this guide

← The client's construction budget in Italy: setting it, checking it, holding it