Apartment building construction costs per m² of gross floor area

📐 Article

By , construction economist

Information verified on 9 min read

What you will learn Why published figures for apartment buildings diverge even further than for detached houses, why the square metre costs less in multi-storey housing, which items are added in return, and how benchmarks shift with the number of storeys and the size of units.

For apartment buildings the comparability problem is sharper than for detached houses, because two effects run against each other: fixed costs spread across more floor area, while requirements arise that do not apply to a single dwelling. The two effects can only be quantified separately.

The range in the sources

Figures published in 2026 for a new apartment building run from around 2,000 to over 5,000 euros per square metre of habitable area. The range therefore exceeds a factor of two.

Published range Stated scope
around €2,070 per m² turnkey, standard specification, including ancillary costs under DIN 276
€2,000 to €2,500 per m² masonry construction, bespoke design
€2,800 to €5,000 per m² construction cost only, average around €3,200 from top of slab
€2,500 to €4,500 per m² broad orientation, no scope stated

The lowest and highest differ by a factor of two and a half. A logical contradiction is worth noting: the lowest figure is presented as including all ancillary costs under DIN 276, while one of the higher figures is expressly labelled as construction cost excluding ancillary costs and excluding foundations. A figure with a larger scope therefore sits well below a figure with a smaller one. At least one of the two cannot be right.

For your own cost planning the same rule follows as throughout this branch: figures without complete qualifiers cannot be computed with. The conversion calculation for a figure found online is set out in the article on detached house construction costs and applies here unchanged.

Why the square metre costs less

Multi-storey housing is consistently cheaper per square metre than a freestanding house. Three robust reasons account for it.

Fixed cost degression. Heating plant, utility connections, site establishment, servicing and basic design services arise largely independently of the number of dwellings and spread across a multiple of the floor area.

A better envelope ratio. A multi-storey form with dwellings stacked above one another needs considerably less external wall, roof and foundation area per square metre of usable area. The same principle explains why a terraced house costs less than a detached one: two expensive external walls disappear and are replaced by cheaper party walls.

Repetition. Similar layouts stacked above one another reduce design effort, set-up times and material waste, and improve the position at tender because larger quantities are called for under each item.

These effects are why construction method matters less for apartment buildings than for detached houses. Masonry and prefabricated systems occupy a similar price band here, because the prefabrication advantage recedes against the scale effects of multi-storey construction.

What is added in an apartment building

Against those savings sit items that are absent or much smaller in a single dwelling. They consume a substantial part of the scale advantage.

Item Effect
Stairwell and circulation increases circulation area and therefore gross floor area without habitable area
Lift required above certain storey counts, with shaft, machinery and maintenance requirements
Fire safety escape routes, fire resistance classes, compartmentation by building class
Sound insulation raised requirements for separating floors and party walls
Accessibility requirements under the state building codes by storey count
Parking municipal parking bylaws, with underground parking as a cost block in its own right
Metering separate measurement per dwelling for heat, water and electricity

Underground parking is the largest single item here and the most frequently underestimated. It can shift the building cost of the whole scheme noticeably, and it enters gross floor area in full without contributing any habitable area.

Which of these requirements bite at which threshold depends on the applicable state building code and the building classes defined in it. The thresholds differ between the federal states, which is covered in the article on German building regulations.

The reference area effect is larger here

For apartment buildings, conversion between habitable area and gross floor area weighs more heavily than for detached houses. An evaluation of 223 residential buildings puts the habitable area share at an average of around 53 to 56 per cent of gross floor area, corresponding to a conversion factor of about 1.80 to 1.90.

By comparison, for a detached house without a cellar the factor sits at about 1.40. The difference is accounted for by stairwells, lift shafts, storage compartments, plant rooms, bicycle stores and underground parking, all of which enter gross floor area in full.

In practice this means a figure in euros per square metre of habitable area sits arithmetically almost twice as high for an apartment building as the same situation in euros per square metre of gross floor area. Placing a benchmark from a professional dataset, which works in gross floor area, beside a market figure working in habitable area produces an apparent difference of around 80 per cent arising entirely from the reference area. The system is set out in the article on reference areas.

Shifts by storey count and unit size

Storey count. As the number of storeys rises, cost per square metre initially falls, because foundations, roof and circulation core spread across more floor area. Above certain thresholds the effect partly reverses: higher building classes bring stricter requirements for fire resistance, escape routes and lifts, and above the high-rise threshold a fundamentally different regime applies. For conventional multi-storey housing the economic optimum sits at middling storey counts.

Unit size. Small dwellings cost more per square metre, because bathroom, kitchen, entrance door, meters and connections arise per dwelling rather than per square metre. A building with many small units therefore carries a noticeably higher benchmark than a building of the same area with few large ones. On micro-apartment schemes this effect is the dominant cost driver.

Cost per dwelling as a second measure

In multi-storey housing the area benchmark alone is not enough. A second measure, cost per dwelling, captures precisely what the area benchmark does not show.

The reason is the cost structure: a substantial part of building cost arises per dwelling rather than per square metre. That includes the bathroom, kitchen connections, entrance door, consumer unit, meters, entry phone and a share of the circulation. Two buildings of identical area, one containing twelve dwellings and the other twenty, differ considerably on these items.

In practice it is therefore worth carrying both benchmarks in parallel at early stages. One serves marketing, the other cost control.

Benchmark Captures Blind to
Euros per m² BGF massing, structure, specification level layout and number of dwellings
Euros per dwelling dwelling-related fixed costs size differences between dwellings

Where the two results diverge sharply, the cause is almost always an unusual unit mix. That is not an error but a signal, and the cost estimate should make it visible.

Adding storeys and infill development

A growing share of German housing arises not on open sites but by adding storeys to existing buildings or by infill development. New build benchmarks do not transfer to this work.

Costs run lower because site, servicing and in part foundations fall away. They run higher because the existing structure must be assessed and frequently strengthened, because work proceeds in occupied buildings, because site establishment and material transport are more demanding, and because fire safety must be reassessed for the building as a whole. A lift retrofit is regularly added once the additional storeys cross a threshold in the state building code.

Dispersion on such schemes is markedly wider than in new build, because a substantial part of the cost only becomes known once the fabric is opened up. The framework for work on existing buildings is covered in the branch on renovation costs per m².

Price levels in the major cities

A study of production costs in new residential construction puts the average for German major cities in the fourth quarter of 2024 at around 4,473 euros per square metre, against around 3,028 euros in 2020. That is a rise of nearly 50 per cent in five years.

These figures are valuable for reading the market, but their scope needs checking before use: production costs in that system are not congruent with the building cost of cost groups 300 and 400. What they establish above all is that benchmarks predating 2021 have become unusable without updating.

The orders of magnitude given are indicative values for Germany. They do not replace a project-specific cost estimate and vary considerably by region, storey count, unit size and specification standard.

Frequently asked questions

Because circulation, services and envelope are spread over more floor area. The effect is one of scale, not of lower quality.

Staircases, lifts and communal areas that cannot be let. They shift the ratio of gross to usable area.

Particularly strongly, because the share of circulation area rises with the number of storeys. A figure per living area sits well above one per gross floor area.

Yes, above certain heights requirements for structure and fire safety are added. The article describes the shift.