Price revision and the date of the budget

📐 Article

By , construction economist

Information verified on 9 min read

What you will learn Why a budget with no price date cannot be controlled, the conditions in article 103 of the LCSP for revising prices in public works, what is excluded, how to calculate the provision with a fictitious example, what happens in private works at a fixed price and which reforms have been proposed without being adopted.

A budget is a figure at a given moment. Without a price date, the promotor (the client or developer) cannot separate the extra cost caused by design decisions from the extra cost caused by rising prices, and without that separation it does not know where to act. Price revision (revisión de precios) is the tool that carries the passage of time into the contract price; in public works it is regulated by law, in private works it exists only if the contract provides for it.

Dating the budget

Every figure in the budget carries a price month. The client's budget is set at one moment, the design estimate at another, the tenders at a third, and the works are carried out over months or years. If all the figures are compared without dates, any deviation looks like a design error or contractor overreach, when sometimes it is only the calendar.

Three dates are enough to put control in order. The price date of the client's budget, the date of the tenders or of formalisation of the contract, and the reference date of the revision formula, if there is one. Between the first and the second, the difference is explained by indices and absorbed by the client's reserve; from the second onwards, the contract decides who bears the rise.

The date also orders the total cost. Fees, charges and finance costs are not revised like the works; the order in which each item becomes certain is analysed in from works budget to total development cost. The indices used to bring a budget forward from one date to another are presented in the article on construction cost indices.

Public works: article 103 of the LCSP

Revision in public works can only be "periodic and predetermined" (art. 103.1 of Law 9/2017 on Public Sector Contracts, Ley de Contratos del Sector Público, LCSP; unofficial translation), and article 103.2 allows it in works contracts, among others. The full regime, with its formulas, is set out in the article on price revision in works contracts in the tendering guide; for the budget of the órgano de contratación (the contracting authority), what matters fits in a table.

Element Rule in art. 103 Effect on the budget
Formula set in the pliego (the tender specifications), "unchanged for the duration of the contract" (para. 4) the provision is calculated from the tender stage
Reference date formalisation, if it takes place within 3 months of the deadline for submitting tenders; otherwise, the end of that 3-month period (para. 4) delays in formalising do not shift the base indefinitely
Entry threshold at least 20% of the amount carried out and one year elapsed since formalisation (para. 5) short works, or works slow to start, are barely revised
Excluded portion the first 20% carried out and what is carried out in the first year (para. 5) that tranche remains at the contractor's risk
Non-revisable items depreciation, finance costs, general or structural overheads and industrial profit (para. 2) revision does not reach those parts of the price
Formulas and indices standard formulas approved by the Council of Ministers; monthly indices compiled by the INE (the national statistics institute) and approved by ministerial order (paras. 6 to 9) the data source is public and verifiable

The one-year threshold comes from the 2023 reform. Law 11/2023 of 8 May amended paragraphs 2 and 5 of article 103; the wording in force since 10/05/2023 requires one year from formalisation, where 2 years were previously required. For a contract awarded under the earlier wording, it is advisable to check which version applies.

A fictitious provision example

The figures are fictitious and simplified. A works contract of 3,000,000 euros, excluding VAT, with a 24-month programme. A price structure is assumed with general overheads of 13% and industrial profit of 6% on the presupuesto de ejecución material (PEM, the net works cost), so that the price equals 1.19 times the PEM.

Step Calculation Amount
First 20% of the amount 20% of 3,000,000 600,000
Carried out in the first year tracking figure 1,000,000
Excluded amount the first year already includes the first 20% 1,000,000
Remaining amount subject to revision 3,000,000 minus 1,000,000 2,000,000
Portion corresponding to the PEM (without overheads or profit) 2,000,000 / 1.19 1,680,672
Provision with a hypothetical revision coefficient of 1.04 1,680,672 × 0.04 67,227

The order of magnitude is what matters: the public client knows from the tender stage that, on that assumption, revision will cost it around 67,000 euros, and it can reserve them. If only 500,000 euros had been carried out in the first year, revision would start on reaching 20% of the amount and the excluded portion would be 600,000 euros. The actual calculation is determined by the formula in the tender specifications; this table only serves to size the provision.

Revision is kept on its own line of the dashboard, separate from modifications and from measurement overruns, as explained in tracking the final cost during the works. Mixing them makes it impossible to tell whether the deviation comes from the design or from the market.

Private works: no statutory revision

In private works, no rule imposes or organises price revision. For a lump sum (ajuste alzado), article 1593 of the Civil Code provides that the contractor "may not claim an increase in price even if the cost of wages or materials has risen". Without a clause, rising costs during the works are, in principle, the contractor's risk; the same article does, however, allow an increase in the works authorised by the owner, which is covered in extra works under a fixed-price contract.

That does not mean the fixed price comes free. A contractor taking on price risk builds it into its tender, and in tight markets it may try to renegotiate or claim by other routes. The client's decision is to choose who bears the risk and at what price, not to ignore it.

If a clause is agreed, it should say five things. The index or formula, preferably from public sources; the reference date; a threshold or excluded tranche, as the law does for public works; the excluded items, such as overheads and profit; and, if the client needs one, a cap. A clause that just says "prices revisable according to the market" is not a clause, it is a postponed dispute.

With unit rates, the question is the same. The contract fixes the price of each unit at a date; without a revision clause, those prices apply to the actual quantities throughout the works.

Reforms proposed, not adopted

Proposals to change price revision have been tabled, but none has amended article 103. In the Senate, amendments were tabled to the Bill on the comprehensive promotion of the social economy proposing to amend articles 100 and 103 and to create an article 103 bis to update prices for rises in wage costs (BOCG Senado no. 368, 16 February 2026). They were not incorporated: Law 1/2026 of 8 April, as finally adopted, only amends the fourth additional provision of the LCSP. In February 2025 a bill to update public contract prices for rises in wage costs (collective agreements and the statutory minimum wage) was also registered, with no known adoption.

As at 21 October 2026, the consolidated text of article 103 is still the 2023 wording. A budget prepared today should be calculated on that wording, not on the proposals.

This article reflects the state of the rules on the date of verification and is intended as professional guidance. It does not replace legal advice or an examination of the specific case.

Frequently asked questions

When at least 20% of its amount has been carried out and one year has elapsed since formalisation, under article 103.5 of the LCSP. The first 20% carried out and what is carried out in the first year are excluded.

No. Article 103.2 excludes in all cases depreciation, finance costs, general or structural overheads and industrial profit.

Article 1593 of the Civil Code rules it out for the lump-sum contract it governs. Only an agreed revision clause allows that rise to be passed on in the price.

No. Reform proposals were tabled in 2025 and 2026, but as at 21 October 2026 article 103 keeps its 2023 wording, and Law 1/2026 did not amend it.