Radon zone municipalities in Spain: is your project affected?

📐 Focus

By , construction economist

Information verified on 6 min read

What you will learn

How to check whether a municipality appears in appendix B of section HS 6, which classifies municipalities by their radon potential, what distinguishes zones I and II, what consequences each classification has for the design and its budget, and what to do in municipalities not on the list.

The radon protection requirement of section HS 6 has a particularity unique in the CTE (Código Técnico de la Edificación, the Spanish building code): it is triggered or not depending on the project's municipality. The instrument is the section's appendix B, the classification of municipalities by zones according to their radon potential, and the check is as simple as it is decisive: looking the municipality up in the list is the first box to tick at the start of any project. The full technical context of the requirement is developed in the article on radon protection, and its place in the document in the one on the DB-HS.

What the appendix is and where it comes from

Appendix B, "Clasificación de municipios en función del potencial de radón" (classification of municipalities according to radon potential), is part of the HS 6 section incorporated into the CTE by Royal Decree 732/2019. It gathers the municipal territories where radon potential studies, drawn from the mapping of the Consejo de Seguridad Nuclear (Spain's nuclear safety council) based on geology and available measurements, estimate an appreciable probability of high concentrations in buildings. The list organises municipalities by province and assigns them one of two categories, zone I and zone II, in increasing order of potential.

The resulting geography is that of the substrate: granitic territories and certain formations of the west and northwest of the peninsula dominate, with a notable presence in Galicia, western Castilla y León, Extremadura and the sierras of Madrid, among other areas, alongside scattered municipalities in other provinces. But the operational rule is not to trust geological intuition: the list is nominal, municipality by municipality, and the only valid check is direct consultation of the appendix in its current version.

Zone I and zone II: what changes

The classification is not informative, it is prescriptive: it determines the level of protection required of new buildings and of interventions on existing ones within the section's scope of application. Consulting the appendix belongs at the start of the appointment.

In zone I municipalities, the requirement is satisfied with a protection barrier between the ground and the habitable rooms, the membrane or equivalent system that limits the entry of the gas, with its continuity and sealing conditions, or, alternatively, with a ventilated air cavity. The barrier's continuity is resolved at the service penetrations.

In zone II municipalities, the barrier alone is no longer enough: the section requires combining it with a second front, either a ventilated containment space interposed between the ground and the rooms, the ventilated crawl space as the typical solution, or a ground depressurisation system under the building, sumps or collection pipes connected to mechanical extraction, which capture the gas before it enters and discharge it, as a general rule, above the roof. The choice between the two routes depends on how the building meets the ground.

The reference objective in both cases is the same one governing the whole section: keeping the annual average radon concentration in habitable rooms below the reference level of 300 becquerels per cubic metre. The barrier is sized by calculation, except for the membranes the section deems valid, and the effectiveness of the ventilated cavity or of the depressurisation is checked by measurements after the works, according to appendix C of the section.

Practical consequences for the project

Situation Design consequence
Municipality not on the list No HS 6 requirement; voluntary measurement possible in bordering areas
Municipality in zone I Protection barrier, or ventilated air cavity as an alternative, with its continuity detail and seals
Municipality in zone II Barrier plus ventilated cavity or depressurisation; specific item

The budget reading is direct. In planned new construction, radon protection is a modest item: the barrier integrates into the ground-contact waterproofing package, and the cavity or depressurisation, where applicable, is resolved with the foundations. The serious cost is that of forgetting: discovering the requirement with the slab already poured turns a minor item into a change order, and in renovation, retrofitted solutions on a finished building multiply the price of what an early detail would have resolved.

Hence the routine this article wants to establish: checking the municipality against the appendix, in the current consolidated version of the document, belongs on the project kick-off checklist, next to the DB-HE climate zone and the DB-HR exterior noise. One minute of consultation, and the requirement sits inside the budget from day one, following the general regulatory traceability principle developed in the article on the cost of CTE compliance.

Two final nuances

First: the list can evolve. Radon potential mapping is refined with new measurements, and CTE revisions can update the appendix; the valid check is always against the consolidated text in force at the project date, not against the archived copy from a previous project.

Second: off the list, the requirement does not apply, but radon exists. In municipalities bordering classified zones, or for sensitive uses with permanent occupation of floors in contact with the ground, prior measurement and the provision of a barrier are quality decisions of marginal cost that some developers adopt voluntarily, and that are at least worth raising with the client.

Note: each municipality's classification and the required solutions are those of the appendix and provisions of the consolidated DB-HS 6 in force, published on the official CTE portal.

Frequently asked questions

By consulting appendix B of section HS 6, which classifies municipalities into zone I and zone II according to their radon potential. The check is made at the start of the appointment.

A protection barrier between the ground and the habitable rooms, with its continuity and sealing conditions, or, as an alternative, a ventilated air cavity.

The barrier combined with a second front: a ventilated containment space, the crawl space being the typical solution, or a ground depressurisation system.

An annual average concentration of 300 becquerels per cubic metre in habitable rooms. The barrier is justified by calculation, and the effectiveness of the ventilated cavity or of the depressurisation is checked by measurement after the works.