Who controls cost for the client

📐 Topic

By , construction economist

Information verified on 7 min read

What you will learn Who decides, designs, checks and organises the cost of a private or public project, who signs what, the scope of the project manager, the role of the RUP and the two articles in this branch.

Around a building site, many people talk about cost. Only one decides, the committente (the client); the others help, and the budget holds only if each of them knows, in writing, where their own responsibility ends. When roles overlap, the final cost becomes a figure nobody answers for.

Four functions not to be confused

Deciding, designing, checking the works and organising are four distinct jobs, which the contract must keep apart even when one person carries out several of them. The client decides. The client sets the limite di spesa (spending limit), approves the design, chooses the contractor, authorises varianti (variations) and, if need be, withdraws from the contract. In private work "the authorisation must be proved in writing" (Civil Code, art. 1659, unofficial translation), and withdrawal remains the client's right, provided the appaltatore (the contractor) is indemnified for expenses, work carried out and loss of profit (Civil Code, art. 1671).

The progettista (the designer) designs, and the spending limit written into the appointment sets the economic boundary. According to a Corte di Cassazione decision reported by BibLus (Cass. civ. no. 8058/2023, concerning planning compliance, not budget), the designer "owes a result", a design that can actually be used; the law also requires the designer to provide in writing "all useful information on the foreseeable charges" together with an outline quote for the fee (Decree-Law 1/2012, art. 9(4)).

The direttore dei lavori (works director) checks the works and the accounts. In private work, according to the ANCE guide on variations (April 2024), the works director represents the client on technical matters and does not bind the client on prices and variations without express delegation. In public work, the director's duties are set by Annex II.14 (Allegato II.14) to Legislative Decree 36/2023.

The project manager organises. In private work the role has no statutory basis: the project manager's power over cost is exactly what the appointment confers.

Who signs what, who answers for what

The simplest way to avoid grey areas is a table attached to the contracts.

Act affecting cost Who proposes Who decides in private work Who decides in public work
Spending limit client, with technical support client, in the designer's appointment stazione appaltante (contracting authority), within the economic limits of the DIP (design brief)
Estimate at each stage designer client, who approves the stage RUP, after verification and validation
Priced variation works director or contractor client, in writing works director proposes, RUP assesses, contracting authority approves
New rate works director and contractor, jointly client, or works director if delegated in writing RUP; contracting authority if the quadro economico (economic summary) is exceeded
Final cost forecast works director or project manager client RUP

In public work the chain is laid down in the rules. The works director proposes changes and variations to the RUP; the RUP assesses them; the contracting authority approves them (Annex II.14, art. 5(1) and (3)). New rates are approved by the RUP, but if they lead to expenditure above the economic summary they are approved by the contracting authority on the RUP's proposal (paras. 7 and 8). The works director answers for changes ordered or allowed to be carried out without authorisation (para. 4).

In private work the chain exists only if the client writes it down. A specification stating who may authorise a variation, up to what amount and in what form avoids the most common case: an instruction given on site by the technical adviser, carried out by the contractor and disputed by the client when the invoice arrives.

The private project manager: a scope to be written

A project manager without a written scope organises, but does not control cost. The appointment states at least the acts the project manager may perform for the client, the threshold above which the decision goes back to the client, the frequency of cost reporting and the link with the works director, so that the contractor does not receive instructions through two channels. The project manager replaces neither the works director nor the safety coordinators; and the "responsabile dei lavori" (works manager) whom Legislative Decree 81/2008 places alongside the client (art. 90) is a safety role, not a cost role.

In public work: the RUP holds the whole cycle

The contracting authority has a single person responsible for the whole life of the project. The RUP (responsabile unico del progetto, the single project manager) is appointed in the first act relating to the project and covers programming, design, award and performance (Legislative Decree 36/2023, art. 15(1)). The RUP directs performance with the support of the works director, the safety coordinator and the collaudatore (acceptance inspector) (art. 114(1)); the works director is appointed on the RUP's proposal before the award procedure starts (para. 2). The RUP can rely on a support unit and on support assignments of up to 1 per cent of the amount put out to tender (art. 15(6)). The general rules of the performance stage, seen from the bidder's side, are covered in the guide to performance of the public contract.

The articles in this branch

This article sets out the rules as they stood on the date of checking and is intended as professional guidance. It does not replace legal advice or an examination of the specific case.

Frequently asked questions

Only if the appointment allows it, within the threshold and in the form provided. Without written delegation, the variation remains a decision of the client, to be proved in writing.

The works director answers for technical and accounting control, not for the agreed price. In public work the director proposes variations to the RUP and answers for those ordered or not authorised.

No rule requires one. What is always needed is to know who decides, who checks and how often an updated forecast arrives; a clear appointment for the works director may be enough.

The RUP runs the cycle and authorises changes and variations according to the organisation of the contracting authority (art. 120(13)); variations and new rates beyond the economic summary are approved by the contracting authority.