The cost of premium finishes

📐 Focus

By , construction economist

Information verified on 4 min read

Finishes are the most elastic item in any estimate: between current level and high-end, the budget for the same work can triple, at equal area and installation. This article gives the reference bands for the main packages, so that choosing the level becomes an informed decision rather than a discovery once works have started.

Bands by package

Package Current level High-end Note
Porcelain floor tiles EUR 25 - 45/m2 EUR 70 - 150/m2 Large formats and textured effects at the top
Wood flooring EUR 50 - 80/m2 EUR 120 - 300/m2 Premium species, thicknesses, patterned laying
Natural stone and marble EUR 60 - 120/m2 EUR 180 - 500/m2 Bespoke cutting and special finishes
Bathroom wall finishes EUR 25 - 50/m2 EUR 90 - 250/m2 Large-format slabs, mosaics
Windows EUR 400 - 600/m2 EUR 800 - 1,600/m2 Timber-aluminium, minimal frames, wide openings
Complete bathroom EUR 8,000 - 12,000 EUR 20,000 - 45,000 Sanitaryware, taps, enclosures, furniture
Internal doors EUR 350 - 600 EUR 900 - 2,500 Flush-to-wall, timber species, non-standard heights

Prices include supply and installation, with the caveat that in the high-end installation grows faster than supply: large-format slabs, bespoke stone and minimal-frame windows require specialist crews, longer times and tight tolerances. A premium material badly installed costs like premium and is worth like ordinary.

Where premium pays off and where it does not

It pays off where you touch and live every day: floors of the main areas, windows (which combine appearance, performance and durability), taps and ironmongery, kitchen and bathroom worktops. These are high-contact elements, where the quality difference is perceived daily and durability justifies the price.

It pays off less where it is invisible or replaceable: finishes in utility rooms, doors to secondary spaces, surfaces in low-traffic areas. Here high-end is spending without perceptual return.

From this asymmetry comes the most effective strategy: the hierarchy of finishes. Concentrating the premium budget on three or four decisive elements and keeping current level elsewhere produces a result perceived as high-end at an intermediate cost. Spreading high-end uniformly across everything, by contrast, multiplies the spending without multiplying the perception.

The effect on total cost

On the 80 m2 apartment of the reference bill of quantities, moving the finishes alone from current level to high-end shifts the total as follows. Structural and services work remains unchanged.

Scenario Finishes items Total works
Current level ~EUR 32,000 ~EUR 78,000
High-end throughout ~EUR 78,000 ~EUR 124,000
Hierarchy (premium on floors, windows, main bathroom) ~EUR 50,000 ~EUR 96,000

The third row is the most frequent case in successful renovations: 23 per cent more than current level, against 59 per cent for indiscriminate high-end, with a perceived result very close to it. Concentrating spend on a few rooms gives a perceived result close to high-end.

Note: the figures shown are 2026 orders of magnitude for the Italian market, for guidance only, and in the high-end the variability is by nature very wide. The figures refer to summer 2026: in June 2026 the ISTAT construction cost index for a residential building stood at 121.1 (base 2021=100). Every choice must be verified against samples and specific quotes.

Frequently asked questions

Partly and not proportionally: the market recognises perceptible quality and general condition, but rarely returns the whole extra cost, especially where choices are highly personal. The elements that hold value best are the neutral and durable ones, not the strongly characterised ones.

It can reduce supply cost, but it shifts responsibility for quantities, delivery times and installation compatibility onto the client; and in case of defects the warranty chain becomes complicated. If done, it must be agreed in the specification before works begin.

A great deal: particular timber species, bespoke stone and special windows have procurement times that can exceed two or three months. They must be ordered before the site opens, on pain of weeks of standstill on a project already under way.