Reducing construction costs in Italy: the design decisions that fix the cost before detailed design

📐 Complete guide

By , construction economist

10 min read

What this article covers The six design decisions that fix the cost of a residential building before detailed design, measured on a single example: an apartment building (palazzina, a small block of flats) of 12 flats on four storeys above ground, with a basement and lock-up garages. For each decision you will find what makes it expensive, what can still be changed and the page that develops it, along with the useful references when the estimate or the bids have already come in above budget.

The cost is decided at feasibility stage

Reducing construction costs is design work before it is negotiating work. When the quotes arrive, quantities and technical solutions are already fixed: what gets negotiated are the unit prices, that is, the thinnest part of the cost. The decisions that really count are taken earlier, when the shape of the building, the number of storeys, the basement, the structural grid, the type of foundation and the facade system are chosen.

In public works this moment has a name and a content: the progetto di fattibilità tecnico-economica (technical and economic feasibility design), which already includes the calcolo sommario della spesa (summary cost calculation) and the quadro economico (overall budget statement) (D.Lgs. 36/2023, Annex I.7). In private works no rule imposes a level of estimate, but the logic is the same: every decision taken without a figure beside it becomes a cost discovered later. The budget the client sets before design is covered in Setting the budget before design; this guide starts from there and looks at the designer's decisions that make that figure move.

The example project

All the pages in this guide work on the same building, and each one varies a single assumption. The building has 12 flats, three per floor on four storeys above ground, with a rectangular footprint of 24.0 m by 12.5 m, that is 300 m² gross per floor and 1,200 m² of gross floor area above ground. The floor-to-floor height is 3.0 m and the height above ground about 12 m. Below, a basement with lock-up garages (box) and storage cellars, whose extent is one of the decisions discussed.

Item Value
Flats 12, three per floor
Footprint 24.0 m × 12.5 m = 300 m²
Gross floor area above ground 1,200 m²
Facade perimeter 73 m
Gross facade area 73 m × 12 m = 876 m²
Gross volume above ground 1,200 m² × 3.0 m = 3,600 m³
Reference basement 24.0 m × 17.0 m = 408 m², extending under the courtyard

For the above-ground part, the blog's range for a standard-specification apartment building is used, from 1,200 to 1,700 euros per m², with a central value of 1,450 euros per m² of gross floor area: about 1,740,000 euros for the 1,200 m² above ground, excluding VAT, professional fees, charges and land. The basement is counted separately, because no per-m² value for the building describes it well. How to read these ranges, and on which floor area, is explained in Construction costs per m2 in Italy.

The six decisions, in the order they are fixed

Order matters. Some decisions are locked in with the building permit (titolo edilizio), others remain open until detailed design. The table lines them up, from the least reversible to the most reversible:

Decision What drives the cost When it is fixed Page
Basement and parking Excavation, retaining walls, waterproofing, ramp, fire prevention Before the building permit Basement or surface parking
Shape and number of storeys Facade and roof area per m² of living space, step-change requirements Before the building permit Compactness and the S/V ratio
Foundations and ground Type of foundation, groundwater, retaining structures With the site investigations, before the final design Foundations and the geotechnical report
Structural grid Consistency between garages and flats, transfer beams, cantilevers Structural design Structural grid and reinforced concrete
Facade System, glazed share, details Until detailed design The cost of the facade
Cost over time Maintenance, energy, replacements At each of the previous decisions False economies

Basement and parking

The basement is the heaviest decision and the least reversible. In the example, the 408 m² reference basement holds 12 garages in two rows on a central aisle, but to do so it has to extend 4.5 m beyond the building footprint, under the courtyard. The part outside the footprint alone requires a slab able to carry vehicles or planting, with its own waterproofing, and takes the covered area of the car park (autorimessa) beyond 300 m², the threshold above which the car park becomes an activity subject to fire prevention inspections (D.P.R. 151/2011, Annex I, activity 75). Staying within the footprint means fewer garages, but also less excavation and one approval procedure fewer.

Shape and number of storeys

Every extra metre of facade is a cost that adds no saleable floor area. The example building, a simple rectangular block, has a ratio of heat-loss surface to volume of about 0.41. Recesses, loggias cut into the volume and staggered blocks raise this ratio and the cost of the envelope. The number of storeys works the other way: one more storey spreads foundations, roof and stair core further, until a step-change requirement kicks in, such as a fire safety height threshold.

Foundations and ground

Without site investigations, the cost of the foundations is not known, it is assumed. The Technical Standards for Construction (Norme tecniche per le costruzioni, D.M. 17 January 2018, chapter 6) require the geotechnical design to be based on the geological characterisation and modelling of the site and on specific investigations. The blog gives no per-m² value for the raft foundation (platea) of an apartment building with a basement: the only figure it publishes concerns the raft of a prefabricated house, a different element in thickness and loads. Over the 408 m² of the basement the raft is therefore estimated from the quantities of a preliminary sizing, and before the investigations even those remain an assumption.

Structural grid

The garage imposes a grid: parking spaces of about 2.5 m, a manoeuvring aisle, columns that must not stand in front of car doors. If the flats above follow another logic, the loads have to be carried across by transfer beams in the ground-floor slab. Aligning the two grids at feasibility stage costs nothing; correcting them after the architectural design costs a complete revision.

Facade

The facade of the building measures about 876 m² gross. It is the area over which the differences between systems, from rendered external wall insulation (cappotto) to the ventilated facade, are multiplied. The blog gives an order of magnitude of 90-160 euros per m² of vertical surface for rendered external insulation, scaffolding extra: over about 660 m² of opaque wall the range is already worth tens of thousands of euros before other systems are even discussed.

Cost over time

The last decision is not an item but a criterion. A solution that costs less on site and more in maintenance, energy or replacements is not a saving for whoever runs the building. Those who sell straight away and those who keep the property do not do the same sum, and the client needs to know which of the two they are doing.

The method: one assumption at a time

Changing three things at once makes it impossible to know which one brought the cost down. The method of this guide is the opposite: start from a reference building described by its quantities, change a single assumption and measure the difference. The reference quantities (areas, perimeters, volumes, number of garages) stay the same from one page to the next, so the differences can be compared.

The same method works in the design office. For each decision, write down the assumption, the quantity that changes and the resulting cost, with the price date. A table of this kind, attached to the feasibility study, lets the client decide knowing what they are buying and what they are giving up. In public works, it is the natural content of the summary cost calculation; in private works, it is the document that makes an estimate open to discussion.

Blog prices and regional price lists

Per-m² values serve to guide decisions, not to fix an amount. For a verifiable estimate, the project quantities are measured and the unit prices of the price list (prezzario) of the Region where the site is located are applied, as explained in the construction cost breakdown. In the example, the amounts quoted in this guide use the blog's ranges and serve only to give the order of magnitude of the differences.

When it is too late for these levers

If the project estimate already exceeds the budget, the levers in this guide remain valid but cost more, because each decision has to be redesigned. The diagnosis and the order of the levers at that point are in The estimate exceeds the budget: what to do before awarding the works. If it is the contractors' bids that exceed the budget, the options are described in Bids above the budget.

The starting values for an apartment building, with the items specific to multi-family housing, are in Cost of building an apartment building in Italy and, for residential buildings in general, in Residential construction cost per m2 in Italy. The ways of saving on a detached house, from compactness to the hierarchy of finishes, are summarised on the page on the cost of building a detached house.

In summary

The cost of an apartment building is fixed by six decisions taken before detailed design: basement, shape and storeys, foundations, structural grid, facade and cost over time. The first two are locked in with the building permit and weigh the most. Measuring them one at a time, on the same reference building and with the same price date, is the simplest way to reduce the cost without hollowing out the project.

Nature of the values quoted

Regulatory thresholds are quoted from their text. Areas, volumes and the number of garages come from the example project, calculated on fictitious assumptions, and prices are given as examples: they do not replace a priced bill of quantities (computo metrico estimativo) or the consultation of contractors.

Sources: Prices given as examples, established in November 2026 from public references: ranges from the pages of this blog on construction costs per m², on apartment buildings and on house renovation, 2026 · Normattiva, D.Lgs. 31 March 2023, no. 36, Annex I.7; D.P.R. 1 August 2011, no. 151, Annex I · D.M. 17 January 2018, Technical Standards for Construction, chapter 6.

Frequently asked questions

With the least reversible ones: basement and parking, then shape and number of storeys. They are fixed before the building permit and carry excavation, structure and envelope with them. Finishes can be revised until the last moment, but they weigh on a smaller share of the cost.

No. It serves to give the order of magnitude and to check an estimate, not to compare two solutions. To decide between two options you need to measure the quantities that change and apply unit prices to them, those of the regional price list or of the quotes.

First the diagnosis, then the levers in order: brief and floor areas, finishes, options, phasing, procurement method and only at the end the prices. The process is described on the page on the estimate exceeding the budget before tendering.