The cost of the facade: render on external insulation, ventilated facade, glazing

📐 Topic

By , construction economist

5 min read

What this article covers What sets apart in cost three facade systems for an apartment building (palazzina), render on external wall insulation, ventilated facade and glazing, measured on the same example area. The page shows the weight of the glazed share, the details that bids price separately, the maintenance of each system and what is kept of the building's image when the system changes.

The example facade: 876 m²

The apartment building of the guide to reducing construction costs has 73 m of perimeter and about 12 m of height above ground, that is 876 m² of gross facade. With a share of windows of about a quarter, that leaves about 660 m² of opaque wall and 216 m² of windows. It is these two quantities, and not the building's average cost per m², that respond to the choice of system.

In residential construction the envelope accounts for between 15 and 20 per cent of the construction cost, according to the construction cost breakdown. It is an item that should not be sacrificed: an envelope below the range generally signals energy performance that needs checking.

Three systems compared

System What it includes What drives the cost Maintenance
Render on external insulation Insulation bonded and mechanically fixed, reinforced base coat, finish Thickness and type of insulation, corners, sills, scaffolding Renewal of finishes and checks of impact-prone areas
Ventilated facade Insulation, metal substructure, cavity, cladding (ceramic, fibre cement, stone, metal) Cladding chosen, substructure, fixings to the structure Low on the cladding, periodic checks of the fixings
Glazed facade or large openings Windows, glass, shading Glazed area, glass performance, solar shading Cleaning, seals, replacement of components

For render on external wall insulation (cappotto) the blog gives an order of magnitude of 90-160 euros per m² of vertical surface, scaffolding excluded, on the page on house renovation. On the 660 m² of opaque wall in the example the range runs from 59,400 to 105,600 euros. For the ventilated facade and the glazed facade the blog gives no value per m²: the difference is measured on quotes or with the regional price list (prezzario), bearing in mind that the cladding and substructure of a ventilated facade are almost always more expensive than rendered external insulation for the same level of insulation.

The glazed share

Each square metre of glass generally costs more than a square metre of insulated opaque wall, and brings with it shading, sills and subframes. Going from a quarter to a third of glazed area in the example shifts about 76 m² from wall to window. This is not a mistake if the rooms call for it; it becomes a false economy in reverse when large glazed areas later require cooling and shading that were not planned.

The details that bids price separately

Corners, window reveals, sills, junctions with balconies and roof, joints and flashings are where quotes diverge. A simple facade with few repeated elements costs less than a facade with the same system and many details. That is why the compactness covered on the page on the S/V ratio also matters here.

What is kept when the system changes

The image of a facade depends less on the system than on the rhythm of the openings, the materials of the visible points and the details. A base in high-quality cladding can be kept on the ground floor with rendered external insulation on the upper floors, or the ventilated facade can be concentrated on the main elevation. It is the same logic as the hierarchy of finishes that the blog describes on the page on the cost of premium finishes: quality where it shows, the standard system elsewhere.

Anyone changing system must check the required performance, not just the price. Thermal insulation, facade acoustics and fire behaviour depend on the system and its components, and a substitution decided on site to save money can lose a requirement already verified at design stage.

The facade in the cost over time

The system that is cheapest on site is not always the cheapest over time. Rendered external insulation needs its finishes redone at intervals and is vulnerable to impacts at ground floor; the ventilated facade costs more at the outset and needs less work on the cladding. The comparison is made over the whole cycle, with whoever will run the building, and it is the subject of the page on false economies.

In summary

On the example apartment building the choice of facade acts on about 660 m² of opaque wall and 216 m² of windows. Render on external insulation has an order of magnitude of 90-160 euros per m² in the blog; the ventilated facade and glazing are compared on quotes. The glazed share, the details and maintenance shift the cost as much as the system does.

Nature of the values quoted

Areas and glazed shares come from the example project, on fictitious assumptions. Prices are given as examples and do not replace a priced bill of quantities (computo metrico estimativo) or contractors' quotes.

Sources: Prices given as examples, established in November 2026 from public references: ranges from the pages of this blog on house renovation and on the construction cost breakdown, 2026.

Frequently asked questions

For the same level of insulation, a ventilated facade generally costs more at the outset, because of the cladding and the substructure. The difference depends mainly on the cladding chosen and is measured on quotes.

The blog gives 90-160 euros per m² of vertical surface, scaffolding excluded. On the 660 m² of opaque wall in the example that means 59,400 to 105,600 euros.

Often yes, because a window costs more than opaque wall. The choice must however be checked against the daylighting of the rooms and summer cooling.